Karnataka High Court
Administrative and Public LawProperty and Real Estate Law

Acquisition did not lapse under the BDA Act or Section 24(2) while its validity challenge remained pending.

SRI CHANNAPPA vs STATE OF KARNATAKA

Karnataka High CourtJUDGMENT: August 18, 20263 MIN READSOURCE JUDGMENT
Acquisition did not lapse under the BDA Act or Section 24(2) while its validity challenge remained pending.. SRI CHANNAPPA vs STATE OF KARNATAKA. Karnataka High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner claimed ownership of three acres in Survey No. 56, Kodigehalli Village, acquired through sale deeds executed in 2001 and 2003.

Source reference: pp. 4–6

The land was included in the acquisition for formation of Nadaprabhu Kempegowda Layout.

Source reference: pp. 4–6

After the final notification dated 18 February 2010, the petitioner objected to the acquisition, but alleged that the authorities neither took possession nor determined or paid compensation.

Source reference: pp. 4–6

He sought a declaration that the acquisition had lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (“2013 Act”) or Section 27 of the Bangalore Development Authority Act, 1976 (“BDA Act”), or, alternatively, a direction to determine compensation under the 2013 Act.

Source reference: pp. 3–6

The BDA submitted that a Division Bench had upheld the acquisition in W.A. No. 1783/2014 and connected appeals, while permitting affected landowners to seek exclusion of their lands by representation.

Source reference: p. 6
02

Issues

1. Whether the acquisition of the petitioner’s land had lapsed under Section 24(2) of the 2013 Act or Section 27 of the BDA Act.

Source reference: pp. 3–6

2. Whether the petitioner should pursue the remedy of seeking exclusion of the land by representation under the Division Bench’s decision, rather than obtain the relief sought in the petition.

Source reference: pp. 6–8
03

Law Applied

The petitioner invoked Section 24(2) of the 2013 Act, concerning lapse of acquisition in specified circumstances, and Section 27 of the BDA Act, concerning the consequence of failure to execute an approved scheme within the prescribed period.

Source reference: pp. 3–6

The Court applied the Division Bench’s decision in W.A. No. 1783/2014 and connected appeals, which upheld the acquisition but permitted landowners to seek exclusion of their lands on the grounds identified in that decision.

Source reference: pp. 6–8

The Court reasoned that where the acquisition’s validity attained finality only in 2024, the authority could not be expected to form the layout while the challenge to the acquisition remained pending.

Source reference: p. 7
04

Reasoning

The Court noted that the acquisition had been challenged and that the Division Bench ultimately upheld it, while providing a route for landowners to seek exclusion of their lands.

Source reference: pp. 6–7

Since the acquisition’s validity attained finality only in 2024, the Court rejected the petitioner’s contention that the acquisition had lapsed under Section 27 of the BDA Act or Section 24(2) of the 2013 Act, reasoning that the BDA could not have been expected to implement the layout during the pendency of the challenge.

Source reference: p. 7

The Court therefore directed the petitioner to use the representation procedure made available by the Division Bench.

Source reference: pp. 7–8
05

Holding

The petition was disposed of, and the final notification dated 18 February 2010 was upheld.

The petitioner was permitted to apply within one month of receiving the order for exclusion of his land on grounds recognised by the Division Bench; the BDA was directed to decide the representation within three months of receiving it.

Source reference: p. 8

Pending that decision, the respondents were restrained from taking precipitative steps to vandalise, damage, or destroy standing trees or buildings on the property.

Source reference: pp. 8–9

The petitioner was restrained from constructing, reconstructing, modifying, or altering any building there until the representation was decided; any construction made in breach of the order could be removed after notice.

Source reference: pp. 8–9
06

Acts & Sections Cited

1 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 20131

Karnataka High Court

Original Court PDF

SRI CHANNAPPAvsSTATE OF KARNATAKA

Karnataka High Court · August 18, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment