The question

1. Whether the compromise, which reduces the acquired extent from 827.91 sq. mtrs. to 321.01 sq. mtrs., quashes the preliminary and final notifications and the award insofar as they relate to 506.90 sq. mtrs., and is lawful and just so as to be recorded.

The court held

The court held the compromise lawful and just and accepted it.

It also directed

The court disposed of the writ petition in terms of the compromise.

The preliminary notification dated 10.08.2021, final notification dated 21.01.2022 and award dated 08.12.2022 are quashed insofar as they cover 506.90 sq. mtrs., and the petitioners are absolute owners of that extent.

The petitioners will hand over 321.01 sq. mtrs. as per the annexed sketch, with compensation of Rs. 3,21,35,348 plus accrued interest.

The petitioners are to seek release of the amount from LAC No. 13/2023 within seven days.

Respondent No. 3 must protect, restore and reconstruct the affected amenities and boundary wall.

The parties and the authorised officer of Respondent No. 3 are directed to sign the order sheet in acceptance.

01Facts

The four petitioners, heirs of late T. Chinnaswamy Reddy, challenged acquisition of land in Sy. No. 52/1, Nagavara Village, Kasaba Hobli, Bengaluru North Taluk, for the Bangalore Suburban Rail (BSR) Project.

¶ 1

The land is Item No. 2 of the writ schedule.

¶ 1

The State issued a Preliminary Notification dated 10.08.2021 and a Final Notification dated 21.01.2022 under Section 28(4) of the KIAD Act, covering 827.91 sq. mtrs.

¶ 2 of compromise

The KIADB-KRIDE Special Land Acquisition Officer-2 passed an award dated 08.12.2022, followed by an award notice dated 21.02.2023.

¶ 1

The petitioners sought a declaration of entitlement to compensation under the RFCTLARR Act, 2013, and certiorari quashing the notifications and award insofar as they affected 506.90 sq. mtrs.

¶ 1

While the petition was pending, Respondent No. 3 (KRIDE) modified the rail alignment.

¶ 2 of compromise, cl. 3

A survey showed only 321.01 sq. mtrs. was required for the project, and 506.90 sq. mtrs. could be excluded.

¶ 2 of compromise, cl. 3

The parties then entered a compromise under Order XXIII Rule 3 CPC, read with Section 151 CPC and Article 226.

¶ 2

02Issues

i.1. Whether the compromise, which reduces the acquired extent from 827.91 sq. mtrs. to 321.01 sq. mtrs., quashes the preliminary and final notifications and the award insofar as they relate to 506.90 sq. mtrs., and is lawful and just so as to be recorded.

¶ 2 of compromise, cl. (a) · ¶ 3

ii.2. Whether the writ petition may be disposed of in terms of the compromise, including the compensation, interest, restoration and boundary-wall terms.

¶ 4 · ¶ 2 of compromise, cl. (b)–(l)

03Law Applied

The court relied on Order XXIII Rule 3 CPC, read with Section 151 CPC and Article 226 of the Constitution, as the procedural basis for recording a compromise in a writ proceeding.

¶ 2

The court examined the compromise for lawfulness and justness before accepting it.

¶ 3

The substantive framework is the Land Acquisition Act, 1894, as invoked through Section 28(4) of the KIAD Act, 1966, which governed the preliminary notification, final notification and award.

¶ 2 of compromise, cl. 2

The petitioners' claim rests on the RFCTLARR Act, 2013, which provides the compensation framework and was pleaded in the prayer.

¶ 1

No precedent was cited in the order.

Provisions in the judgment · 2 · Linked ones open on LawLens

Code of Civil Procedure, 1908 Section 151

KARNATAKA INDUSTRIAL AREAS DEVELOPMENT ACT, 1966 Section 28

04Reasoning

The court accepted the compromise after perusing its terms and finding them "just and lawful."

¶ 3

The petitioners, appearing in person and identified by counsel, confirmed their assent, and Respondent No. 3 agreed to the terms.

¶ 3

The survey showed that only 321.01 sq. mtrs. was needed for the BSR alignment. Excluding the balance of 506.90 sq. mtrs. therefore removed the basis for acquiring that portion.

¶ 2 of compromise, cl. 3

The compromise accordingly provides for quashing the notifications and award for that extent, with the petitioners regaining absolute ownership.

¶ 2 of compromise, cl. (a)

The compensation for the 321.01 sq. mtrs. is fixed at Rs. 1,00,107 per sq. mtr., inclusive of statutory benefits, with accrued interest, and is to be adjusted against the deposit in LAC No. 13/2023.

¶ 2 of compromise, cl. (b)–(c)

The Respondent is restricted to interest on Rs. 3,21,35,348 and is not to claim interest on the entire deposit of Rs. 5,86,28,425.

¶ 2 of compromise, cl. (d)

Because the basketball and football courts and the school amenities fall within the excluded area, Respondent No. 3 must protect and restore them and reconstruct the compound wall at its own cost, using a temporary barricade during the works.

¶ 2 of compromise, cl. (e)–(f)

The compromise is expressly confined to these facts and is not to serve as precedent, and it is without admission of liability.

¶ 2 of compromise, cl. (j)

05Holding

The court held the compromise lawful and just and accepted it.

¶ 3

The court disposed of the writ petition in terms of the compromise.

¶ 4

The preliminary notification dated 10.08.2021, final notification dated 21.01.2022 and award dated 08.12.2022 are quashed insofar as they cover 506.90 sq. mtrs., and the petitioners are absolute owners of that extent.

¶ 2 of compromise, cl. (a)

The petitioners will hand over 321.01 sq. mtrs. as per the annexed sketch, with compensation of Rs. 3,21,35,348 plus accrued interest.

¶ 2 of compromise, cl. (b), (d), (h)

The petitioners are to seek release of the amount from LAC No. 13/2023 within seven days.

¶ 2 of compromise, cl. (c)

Respondent No. 3 must protect, restore and reconstruct the affected amenities and boundary wall.

¶ 2 of compromise, cl. (e)–(g)

The parties and the authorised officer of Respondent No. 3 are directed to sign the order sheet in acceptance.

¶ 4
Karnataka High Court

Original Court PDF

SMT JETHRUTHA CvsSTATE OF KARNATAKA

Karnataka High Court · November 11, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment