Supreme CourtInsolvency and Bankruptcy LawBanking and Finance Law

Adjustment of security deposits against pre-CIRP dues after insolvency commencement violates the Section 14 moratorium.

Central Transmission Utility Of India Limitedv.Sumit Binani

Adjustment of security deposits against pre-CIRP dues after insolvency commencement violates the Section 14 moratorium.. Central Transmission Utility Of India Limited vs Sumit Binani. Supreme Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

Whether a creditor can adjust or set off a cash security deposit against pre-CIRP dues after the Insolvency Commencement Date in light of the Section 14 moratorium

The court held

The Supreme Court affirmed the orders of the NCLT and NCLAT, holding that the appropriation of ₹85.13 crores toward pre-CIRP dues was illegal and in derogation of the Section 14 moratorium

It also directed

The Court directed that the deposit should instead be adjusted against post-CIRP dues to maintain the CD as a going concern, while the pre-CIRP dues must be settled according to the claim process and the approved Resolution Plan

The appeals were rejected

01Facts

The Corporate Debtor (CD), KSK Mahanadi Power Company Limited (KMPCL), entered into a Transmission Service Agreement (TSA) with the Appellant’s predecessor, PGCIL

p. 1

Per the orders of the Central Electricity Regulatory Commission (CERC), the CD deposited ₹108.44 crores in cash as a Payment Security Mechanism (PSM) in lieu of a Letter of Credit (LoC)

p. 3, 12

On 03.10.2019, the NCLT admitted the CD into the Corporate Insolvency Resolution Process (CIRP), triggering a moratorium under Section 14 of the IBC

p. 2

The Appellant, an operational creditor, filed a claim in Form B for outstanding dues, of which the Resolution Professional (RP) admitted only a portion

p. 9, 20

On 28.03.2020—after the commencement of CIRP—the Appellant adjusted the ₹108.44 crore deposit against outstanding bills, including ₹85.13 crores for pre-CIRP dues

p. 2, 14

Both the NCLT and NCLAT held that the adjustment of pre-CIRP dues post-insolvency commencement violated the moratorium

pp. 4-5

02Issues

i.Whether a creditor can adjust or set off a cash security deposit against pre-CIRP dues after the Insolvency Commencement Date in light of the Section 14 moratorium

p. 3 / para 3

ii.Whether a cash deposit made in lieu of a Letter of Credit can be treated as a third-party guarantee or a security interest enforceable during the CIRP

p. 7 / para 6

03Law Applied

Section 14 of the IBC, which imposes a moratorium on the recovery or enforcement of any security interest against the Corporate Debtor upon the commencement of CIRP

p. 4, 22

Bharti Airtel Ltd. v. Aircel Ltd. (2024) 4 SCC 668, which established that "insolvency set-off" is not recognized during the CIRP stage and that pre-CIRP dues cannot be adjusted from amounts payable to the CD post-commencement

pp. 18 / para 16-17

Section 238 of the IBC, the provisions of the Code override any other inconsistent instruments or laws

p. 4 / para 4

Provisions in the judgment · 10 · Linked ones open on LawLens

Insolvency and Bankruptcy Code, 2016. 10 provisionsSection 3Section 5Section 14Section 29Section 30Section 36Section 52Section 53Section 62Section 238

04Reasoning

The Court reasoned that the cash deposit remained the property of the CD until a valid adjustment was made. Since the Appellant attempted to apportion these funds on 28.03.2020 (post-CIRP commencement), the act was a clear violation of the Section 14 moratorium

p. 25 / para 24

The Court distinguished between "contractual set-off" (permissible only if completed prior to CIRP) and the present case, where the adjustment was made during the moratorium

p. 18 / para 16

Regarding the nature of the deposit, the Court held that a cash deposit is not equivalent to a Bank Guarantee or LoC; even if it were, Section 14(3)(b) protects guarantees to the CD, not enforcement of the CD's own assets held by a creditor

pp. 22-23 / para 20-22

The Appellant had already submitted to the CIRP process by filing Form B for the same dues; having failed to challenge the RP’s limited admission of those claims, the Appellant could not unilaterally "self-satisfy" the debt by appropriating the CD’s asset

pp. 21-22 / para 18-19

05Holding

The Supreme Court affirmed the orders of the NCLT and NCLAT, holding that the appropriation of ₹85.13 crores toward pre-CIRP dues was illegal and in derogation of the Section 14 moratorium

pp. 26 / para 25-26

The Court directed that the deposit should instead be adjusted against post-CIRP dues to maintain the CD as a going concern, while the pre-CIRP dues must be settled according to the claim process and the approved Resolution Plan

pp. 26-27 / para 25

The appeals were rejected

p. 27 / para 26
Supreme Court

Original Court PDF

Central Transmission Utility Of India LimitedvsSumit Binani

Supreme Court · March 23, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment