Facts
The petitioner, a Government enterprise, participated in an EPC tender by North Eastern Railway (NER) valued at INR 262.12 Crores.
Source reference: para 4In an earlier round of litigation (Writ C No. 5810 of 2026), the court held that an alleged deficiency in stamp duty on the petitioner’s Bank Guarantee (BG) was a curable defect.
Source reference: para 6Following the court's order dated 29.05.2026, the petitioner submitted an adequately stamped BG.
Source reference: para 7On 08.06.2026, NER rejected the bid via WhatsApp, citing an "incorrect beneficiary name" in the BG.
Source reference: para 2, 7When the petitioner submitted a corrected BG on 19.06.2026, NER rejected it as "belated".
Source reference: para 7The petitioner challenged these rejections as mala fide attempts to eliminate the lowest bidder.
Source reference: para 3, 8Issues
1. Whether the rejection of a technical bid based on an incorrect beneficiary name in a Bank Guarantee constitutes an undue procedural irregularity or a curable defect.
Source reference: para 8, 92. Whether the respondent-authorities acted with mala fides and arbitrariness in violation of Article 14 by adopting inconsistent standards compared to other railway divisions.
Source reference: para 10, 11Law Applied
The court applied the principle of non-arbitrariness and fairness in state action under Article 12 and 14 of the Constitution of India.
Source reference: para 6, 10It relied on Meerut Development Authority v. Assn. of Management Studies (2009) 6 SCC 171, which establishes that while the state is not bound to accept the L1 bidder, its actions must be free from arbitrariness, favoritism, and hidden agendas.
Source reference: para 6The court further applied the doctrine of "curable defects" in tender processes, distinguishing between essential conditions and ancillary procedural requirements.
Source reference: para 6, 8Reasoning
The court observed that the respondent-authorities engaged in "hide and seek" by raising new objections (incorrect beneficiary name) only after the previous objection (stamp duty) was overruled by the court.
Source reference: para 5, 10The court highlighted a systemic inconsistency: another arm of the same organization, "Southern Railway, Chennai," had previously allowed the same petitioner to correct a beneficiary name in a BG after the issuance of a Letter of Award, proving the defect is admittebdly curable.
Source reference: para 9The court reasoned that the failure of NER to point out all defects in the first instance, coupled with the rejection of the corrected BG as "belated," demonstrated a "fixation" or mala fide intent to oust a legitimate L1 bidder.
Source reference: para 8, 10Such "whimsical" and "discriminatory" conduct by a state instrumentality violates the principles of natural justice and the duty to act as a model employer.
Source reference: para 8, 10Holding
The court allowed the writ petition, answering that the defect was curable and the rejection was arbitrary.
The court quashed the impugned letter dated 08.06.2026.
Source reference: para 11The Respondent No. 2 was directed to accept the corrected Bank Guarantee and evaluate the petitioner's financial bid in compliance with the previous order dated 29.05.2026 within three working days.
Source reference: para 11The court concluded that the authorities' actions amounted to impermissible harassment.
Source reference: para 10, 12Original Court PDF
M/S Konkan Railway Corporation Ltd. Thru. Authorised Representative Mr. Om Prakash VermavsUnion Of India, Thru. General Manager, North Eastern Railway U.P. And 5 Others
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in