Allahabad High Court

Administrative Arbitrariness in Rejecting Curable Defects in Bank Guarantees Hits Article 14 and Principles of Natural Justice

M/S Konkan Railway Corporation Ltd. Thru. Authorised Representative Mr. Om Prakash Verma vs Union Of India, Thru. General Manager, North Eastern Railway U.P. And 5 Others

Allahabad High CourtJUDGMENT: July 08, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner, a Government enterprise, participated in an EPC tender by North Eastern Railway (NER) valued at INR 262.12 Crores.

Source reference: para 4

In an earlier round of litigation (Writ C No. 5810 of 2026), the court held that an alleged deficiency in stamp duty on the petitioner’s Bank Guarantee (BG) was a curable defect.

Source reference: para 6

Following the court's order dated 29.05.2026, the petitioner submitted an adequately stamped BG.

Source reference: para 7

On 08.06.2026, NER rejected the bid via WhatsApp, citing an "incorrect beneficiary name" in the BG.

Source reference: para 2, 7

When the petitioner submitted a corrected BG on 19.06.2026, NER rejected it as "belated".

Source reference: para 7

The petitioner challenged these rejections as mala fide attempts to eliminate the lowest bidder.

Source reference: para 3, 8
02

Issues

1. Whether the rejection of a technical bid based on an incorrect beneficiary name in a Bank Guarantee constitutes an undue procedural irregularity or a curable defect.

Source reference: para 8, 9

2. Whether the respondent-authorities acted with mala fides and arbitrariness in violation of Article 14 by adopting inconsistent standards compared to other railway divisions.

Source reference: para 10, 11
03

Law Applied

The court applied the principle of non-arbitrariness and fairness in state action under Article 12 and 14 of the Constitution of India.

Source reference: para 6, 10

It relied on Meerut Development Authority v. Assn. of Management Studies (2009) 6 SCC 171, which establishes that while the state is not bound to accept the L1 bidder, its actions must be free from arbitrariness, favoritism, and hidden agendas.

Source reference: para 6

The court further applied the doctrine of "curable defects" in tender processes, distinguishing between essential conditions and ancillary procedural requirements.

Source reference: para 6, 8
04

Reasoning

The court observed that the respondent-authorities engaged in "hide and seek" by raising new objections (incorrect beneficiary name) only after the previous objection (stamp duty) was overruled by the court.

Source reference: para 5, 10

The court highlighted a systemic inconsistency: another arm of the same organization, "Southern Railway, Chennai," had previously allowed the same petitioner to correct a beneficiary name in a BG after the issuance of a Letter of Award, proving the defect is admittebdly curable.

Source reference: para 9

The court reasoned that the failure of NER to point out all defects in the first instance, coupled with the rejection of the corrected BG as "belated," demonstrated a "fixation" or mala fide intent to oust a legitimate L1 bidder.

Source reference: para 8, 10

Such "whimsical" and "discriminatory" conduct by a state instrumentality violates the principles of natural justice and the duty to act as a model employer.

Source reference: para 8, 10
05

Holding

The court allowed the writ petition, answering that the defect was curable and the rejection was arbitrary.

The court quashed the impugned letter dated 08.06.2026.

Source reference: para 11

The Respondent No. 2 was directed to accept the corrected Bank Guarantee and evaluate the petitioner's financial bid in compliance with the previous order dated 29.05.2026 within three working days.

Source reference: para 11

The court concluded that the authorities' actions amounted to impermissible harassment.

Source reference: para 10, 12
Allahabad High Court

Original Court PDF

M/S Konkan Railway Corporation Ltd. Thru. Authorised Representative Mr. Om Prakash VermavsUnion Of India, Thru. General Manager, North Eastern Railway U.P. And 5 Others

Allahabad High Court · July 08, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment