01Facts
The appellants challenged the judgment and award dated 21 April 2023 in LAC No. 662/2021, passed by the I Additional District Judge and Land Acquisition, Rehabilitation and Resettlement Authority, Vijayapura.
p. 2The appeal under Section 74(1) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, was filed on 19 June 2025 with a stated delay of 672 days.
pp. 2–3The appellants sought condonation of delay by I.A. No. 01/2026, relying principally on administrative reasons and the movement of files.
pp. 2–3The High Court found the supporting affidavit bald and lacking relevant dates.
p. 3, 1302Issues
i.Whether the appellants demonstrated sufficient, reasonable, and bona fide cause to condone the 672-day delay in filing the appeal.
pp. 3, 13–14ii.Whether the appeal could proceed when the application for condonation of delay was liable to be rejected.
p. 1403Law Applied
Section 74(1) of the 2013 Act provides for an appeal from the relevant award or decision.
p. 2An application to condone delay requires a reasonable and satisfactory explanation that covers the period of delay; governmental authorities receive no automatic or special exemption from limitation requirements.
pp. 3–4, 13In Shivamma v. Karnataka Housing Board, 2025 SCC OnLine SC 1969, the Supreme Court reiterated that public interest is served by timely and accountable governmental action, and that administrative lethargy or laxity does not, by itself, constitute sufficient cause.
pp. 4–10The Court also relied on State of Odisha v. Managing Committee of Namatara Girls High School, 2026 SCC OnLine SC 191, which distinguished a genuine explanation from a mere excuse and affirmed that condonation is discretionary, not a matter of right.
pp. 11–12The judgment further cited the principle in Basawaraj that limitation must be applied as prescribed and cannot be extended on equitable grounds.
pp. 6–7Provisions in the judgment · 4 · Linked ones open on LawLens
Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 Section 74
Limitation Act, 1963 Section 5Section 3
Code of Civil Procedure, 1908 Section 100
04Reasoning
The appellants’ affidavit relied largely on file movement and administrative approvals, but supplied no relevant dates or specific account of what prevented timely filing.
pp. 3, 13–14It therefore neither explained the entire period of delay nor established bona fide diligence.
pp. 3, 13–14Applying the cited Supreme Court authorities, the Court held that administrative delay and inter-departmental correspondence were insufficient, and that the State and its instrumentalities must meet the same limitation requirements as other litigants.
p. 4, 13As no satisfactory cause was shown, the Court rejected the condonation application without proceeding to the merits of the appeal.
p. 1405Holding
The High Court held that the appellants had not established sufficient, reasonable, or bona fide cause for the 672-day delay.
p. 14It dismissed I.A. No. 01/2026 and, consequently, dismissed the appeal; pending applications, if any, were also disposed of.
p. 14Original Court PDF