Facts
The petitioner, a registered contractor, entered into an agreement with the erstwhile Patna Regional Development Authority (PRDA) on 2 September 2008 for construction of a PCC road and underground drainage from Hanuman Nagar to Sector-K.
Source reference: paras. 2–3He claimed to have completed the work in 2011 under departmental supervision and that the final bill for Rs. 2,10,663 had been prepared, but the amount remained unpaid.
Source reference: paras. 2–3Despite representations to the State authorities, payment was not released.
Source reference: para. 4The Executive Engineer informed him that payment required approval from the Urban Development Department.
Source reference: para. 4The State contended that, following the merger of PRDA with the Patna Municipal Corporation (PMC), PMC was the competent authority to examine the claim.
Source reference: paras. 7–9PMC did not dispute the allotment or execution of the work, but attributed the non-payment to administrative and financial difficulties concerning the erstwhile PRDA accounts and the absence of governmental sanction.
Source reference: paras. 10–13Issues
Whether the respondents could withhold the petitioner’s admitted contractual dues merely because of inter-departmental administrative difficulties and the absence of approval following the merger of PRDA with PMC?
Source reference: paras. 15–19Whether the petitioner was entitled to 12% compound interest on the delayed payment?
Source reference: paras. 20–21Law Applied
The Court applied the principle that a public authority cannot deny payment for work duly completed under a valid agreement merely on the ground of inter-departmental correspondence, procedural delay, or administrative difficulties.
Source reference: para. 18State instrumentalities are required to act fairly, reasonably, and without arbitrariness, and must take an expeditious decision regarding admitted contractual dues.
Source reference: para. 19The Court further held that compound interest cannot be granted in the absence of a statutory or contractual provision authorising it; any legally available entitlement to interest must be considered by the competent authority in accordance with law.
Source reference: para. 21Reasoning
The Court found that the petitioner’s work had been awarded and executed, and that the respondents had not specifically disputed preparation of the final bill.
Source reference: para. 15PMC’s own pleadings demonstrated that the claim had not been rejected on merits; payment was withheld only because of unresolved administrative issues concerning PRDA’s accounts and the requirement of approval from the Urban Development Department.
Source reference: paras. 16–17Applying the principle that internal governmental difficulties cannot defeat a contractor’s lawful claim after performance of the contractual obligation, the Court held that prolonged withholding of the admitted dues was arbitrary and legally unsustainable.
Source reference: paras. 18–19However, because no statutory or contractual basis for compound interest was shown, the Court declined to grant that relief.
Source reference: para. 21Holding
The writ petition was allowed.
The Urban Development and Housing Department and PMC were directed to process and release the admissible amount payable to the petitioner, if not already paid, within three months from receipt or production of the order.
Source reference: para. 20If any part of the claim was found not payable, the respondents were required to pass and communicate a reasoned and speaking order within the same period.
Source reference: para. 20The claim for 12% compound interest was rejected; nevertheless, any interest legally payable under a statutory or contractual provision was directed to be considered by the competent authority.
Source reference: para. 21Original Court PDF
Sanjay Kumar VermavsThe State Of Bihar and Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
