Facts
Land belonging to Respondent No. 1 was acquired under the National Highways Act, 1956, for widening National Highway No. 200, and a compensation award was passed on 16.04.2018.
Source reference: para. 2Dissatisfied, the respondent sought enhancement under Section 3G(5) of the Act.
Source reference: para. 2The Arbitrator, vide award dated 21.02.2023, remanded the matter to the Competent Authority for Land Acquisition (CALA) for a revised award.
Source reference: para. 2The appellant challenged this under Section 34 of the Arbitration and Conciliation Act, 1996, but the District Court dismissed the application on 27.09.2024, observing the Arbitrator acted beyond the scope of Section 3G(5).
Source reference: para. 2The appellant filed the present appeal under Section 37 on 02.04.2025, with a delay of 101 days beyond the prescribed limitation period.
Source reference: para. 3Issues
Whether the appellant demonstrated "sufficient cause" under Section 5 of the Limitation Act to condone the 101-day delay in filing the arbitration appeal.
Source reference: para. 1, 6Law Applied
The court applied Section 37 of the Arbitration and Conciliation Act, 1996, read with Section 5 of the Limitation Act.
Source reference: para. 1, 4It relied on the precedent set by the Supreme Court in Government of Maharashtra v. Borse Brothers Engineers and Contractors Pvt. Ltd. (2021) 6 SCC 460, which held that for appeals under Section 37, delay beyond the 60/90-day period should be condoned only as an exception and not as a rule, keeping in view the objective of speedy disposal.
Source reference: para. 7It further applied the principle from Ramlal v. Rewa Coalfields Ltd., stating that the proof of "sufficient cause" is a condition precedent to the exercise of discretionary jurisdiction, and even if shown, condonation is not a matter of right.
Source reference: para. 7Reasoning
The court scrutinized the appellant’s explanation for the 101-day delay, which cited administrative exigencies: the time taken for legal opinions, departmental approvals, the superannuation of the officer-in-charge, and the intervening winter vacation.
Source reference: para. 3The court found these explanations to be vague, general, and representative of gross negligence rather than "sufficient cause".
Source reference: para. 4, 6Applying the Borse Brothers standard, the court observed that for arbitration matters, the appellant must act bona fide and with extreme diligence.
Source reference: para. 7It held that the administrative hurdles described did not satisfy the rigorous standard required to overcome the statutory bar of limitation, describing the explanation as "woefully short".
Source reference: para. 6, 8The court noted that identical issues regarding delay by the same department had already been dismissed in previous rulings like Sumitra Bai v. Executive Engineer, PWD.
Source reference: para. 4, 9Holding
The court answered the issue in the negative, holding that the appellant failed to provide a satisfactory explanation for the delay.
I.A. No. 2 of 2025 for condonation of delay was rejected, and consequently, the arbitration appeal was dismissed.
Source reference: para. 9, 10Original Court PDF
Chief Engineer,vsChameli Bai
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in