01Facts
The petitioners, whose lands in Hiremagaluru Village were acquired for a broad-gauge railway line following notifications issued in 2015, challenged the compensation fixed by the Land Acquisition Officer.
pp. 6–9After the award notice dated 26 December 2015, they sought enhanced compensation and requested, by applications dated 16 January 2016, that their claims be referred under Section 64 of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (“2013 Act”).
pp. 6–9The Officer had not acted on those applications.
pp. 6–9The petitioners sought mandamus requiring a reference; the State submitted that they had approached belatedly but stated that the Officer would take steps to make the references.
pp. 6–902Issues
i.1. Whether the Land Acquisition Officer was required to consider the petitioners’ applications seeking reference under Section 64 of the 2013 Act.
pp. 9–10ii.2. Whether the Officer should be directed to consider those applications and, if warranted, refer the claims to the appropriate authority notwithstanding the time that had elapsed.
pp. 9–1003Law Applied
Section 64 of the 2013 Act provides for reference of a landowner’s claim concerning compensation to the appropriate authority.
pp. 9–10The Court treated the Collector’s consideration of a request for such a reference as a statutory duty and observed that the reference procedure should be approached liberally to enable adjudication of a land loser’s compensation claim.
pp. 9–10The Court also proceeded under its writ jurisdiction under Articles 226 and 227 of the Constitution.
pp. 2–3Provisions in the judgment · 1 · Linked ones open on LawLens
Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 Section 64
04Reasoning
The petitioners had promptly sought enhanced compensation and a Section 64 reference after the award notice, but the Officer had taken no action since 2016.
pp. 9–10The Court considered that inaction unjustified and emphasized that the Officer had a duty to consider the applications.
pp. 9–10Although the petitioners could also make representations before the appropriate authority, that did not discharge the Officer’s obligation to consider their requests.
pp. 9–10The Court therefore directed consideration of the applications and left open the question of whether interest could be awarded for the period beyond sixty days from the date the reference was sought.
pp. 9–1005Holding
The writ petitions were disposed of with a direction to the Land Acquisition Officer to consider the petitioners’ applications for enhanced compensation and, if warranted, refer the claims to the appropriate authority under Section 64 of the 2013 Act within three months of receiving the order.
pp. 10–11The question of interest beyond sixty days was left to the appropriate authority.
pp. 10–11The Court further stated that failure to take proactive steps to make the references would be treated as grave misconduct, warranting disciplinary action by the Officer’s superior.
pp. 10–11Original Court PDF