Karnataka High CourtProperty and Real Estate LawAdministrative and Public Law

After 27 Years Without Final Notification, Karnataka HC Quashes 1999 Bengaluru-Mysuru Corridor Preliminary Notice, Lets Owner Use His Land

SRI. MADHURAGHAVENDRAv.STATE OF KARNATAKA

After 27 Years Without Final Notification, Karnataka HC Quashes 1999 Bengaluru-Mysuru Corridor Preliminary Notice, Lets Owner Use His Land. SRI. MADHURAGHAVENDRA vs STATE OF KARNATAKA. Karnataka High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the acquisition proposal concerning the petitioner’s lands could remain pending after the 1999 preliminary notification, in the absence of a final notification under Section 28(4) of the KIAD Act

The court held

The petition was allowed.

It also directed

The Court quashed the preliminary notification insofar as it related to the specified lands and declared that the proposal to acquire those lands had lapsed.

It directed that any revenue entry in the name of Respondent Nos. 1 or 2 be deleted and the petitioner’s name restored forthwith.

Respondent No. 5 was granted liberty to proceed against Respondent Nos. 1 and 2 for their failure to take the necessary steps to conclude the acquisition.

01Facts

The petitioner claimed ownership and possession of specified lands in Hebbadi Village, Mandya District, which were included in a preliminary acquisition notification dated 3 July 1999 issued under Section 28(1) of the Karnataka Industrial Areas Development Act, 1966 (KIAD Act), for the Bengaluru–Mysuru Infrastructure Corridor Project.

pp. 3–5

No final notification under Section 28(4) had been issued.

pp. 3–5

The petitioner sought to quash the preliminary notification insofar as it concerned his lands and to have the acquisition declared lapsed.

pp. 3–5

The State and KIADB respondents did not dispute that no steps had been taken to issue a final notification and acknowledged that the same preliminary notification had been quashed in earlier proceedings concerning similarly placed landowners.

pp. 3–5

02Issues

i.1. Whether the acquisition proposal concerning the petitioner’s lands could remain pending after the 1999 preliminary notification, in the absence of a final notification under Section 28(4) of the KIAD Act

pp. 3–5, 7

ii.2. Whether the preliminary notification should be quashed and the petitioner’s right to use the lands, including restoration of the revenue entries, recognised

pp. 5–7

03Law Applied

The Court considered Sections 28(1) and 28(4) of the KIAD Act, under which a preliminary notification initiates the acquisition process and a final notification is a subsequent step in that process.

pp. 3–5

The Court applied the principle that a landowner cannot be kept indefinitely awaiting completion of an acquisition proposal where no final notification has been issued; in those circumstances, the proposal remains uncompleted and the owner is entitled to use the land.

p. 6

No separate precedent or additional statutory doctrine was cited in the order.

Provisions in the judgment · 1 · Linked ones open on LawLens

KARNATAKA INDUSTRIAL AREAS DEVELOPMENT ACT, 1966 Section 28

04Reasoning

The preliminary notification had been issued in 1999, but the respondents confirmed that no steps had been taken to issue a final notification.

pp. 5–6

The Court reasoned that, after such an extended period without completion of the acquisition process, the petitioner could not be kept waiting or deprived of the use of his land.

pp. 5–6

It therefore treated the acquisition as an uncompleted proposal and held that the petitioner was entitled to utilise the land as desired.

pp. 5–6

05Holding

The petition was allowed.

pp. 6–7

The Court quashed the preliminary notification insofar as it related to the specified lands and declared that the proposal to acquire those lands had lapsed.

pp. 6–7

It directed that any revenue entry in the name of Respondent Nos. 1 or 2 be deleted and the petitioner’s name restored forthwith.

pp. 6–7

Respondent No. 5 was granted liberty to proceed against Respondent Nos. 1 and 2 for their failure to take the necessary steps to conclude the acquisition.

pp. 6–7
Karnataka High Court

Original Court PDF

SRI. MADHURAGHAVENDRAvsSTATE OF KARNATAKA

Karnataka High Court · October 29, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment