01Facts
The petitioners challenged notifications issued under Sections 28(1) and 28(4) of the Karnataka Industrial Areas Development Act, 1966 (“KIAD Act”), proposing and finalising acquisition of their 6 acres and 23 guntas in Gowdanahalli Village for an industrial area
¶ 1–2After receiving a notice under Section 28(2), they objected to the acquisition only on the basis that they would consent if paid ₹1 crore per acre; they later contended that the land was garden land and that compensation had not been paid promptly
¶ 2, 10The State and KIADB opposed the petition, relying on the petitioners’ delay, their participation in compensation proceedings, deposit of compensation before the Reference Court, and subsequent allotment and possession of the acquired land
¶ 4–8The Court rejected the challenge to the acquisition but considered whether the delay in determining and depositing compensation required a fresh award
¶ 12–1602Issues
i.1. Whether the petitioners could belatedly challenge the acquisition notifications on the grounds that the land was garden land and that the State’s policy was not to acquire such land
¶ 10–12ii.2. Whether the delay in determining and depositing compensation justified directing a fresh award using a later date for determining compensation
¶ 13–1603Law Applied
Sections 28(1)–(4) of the KIAD Act govern the preliminary notification, objections, consideration of objections and final notification for acquisition; Sections 29(2) and 29(3) provide for determination of compensation by consent or otherwise
¶ 1, 13Under Ram Chand v. Union of India, (1994) 1 SCC 44, delay in challenging acquisition must be considered alongside the authorities’ inaction; where acquisition has progressed and public interest has intervened, quashing may be inappropriate, although the authorities may remain answerable for failing to act within a reasonable time
¶ 11Under Bernard Francis Joseph Vaz v. Government of Karnataka, (2025) 7 SCC 580, compensation must be determined and disbursed promptly, and prolonged deprivation of compensation may warrant relief recognising the loss in value of money over time
¶ 14Article 300-A protects the constitutional right to property and requires adequate compensation in accordance with law
¶ 14Provisions in the judgment · 2 · Linked ones open on LawLens
KARNATAKA INDUSTRIAL AREAS DEVELOPMENT ACT, 1966 Section 28Section 29
04Reasoning
The Court held that the petitioners had not raised the garden-land ground in their objections and had waited years to challenge the notifications; meanwhile, the acquisition had progressed, compensation had been deposited, and the land had been allotted and taken into possession for industrial use. In those circumstances, setting aside the acquisition was no longer appropriate
¶ 10–12However, the acquisition began in 2010 and compensation was deposited only in 2025. The Court found that the delay was not justified by the partition proceedings and that the compensation could not be regarded as just and reasonable without accounting for the passage of time and diminished value of money. Applying Bernard Francis Joseph Vaz, it directed a fresh award using a 2025 valuation date
¶ 13–1605Holding
The petition was allowed in part: the challenge to the acquisition was dismissed, but respondent No. 3 was directed to pass a fresh award, with the operative order specifying 23 January 2025 as the relevant date for determining compensation; the petitioners may seek a reference if dissatisfied or pursue a consent award based on the market value prevalent in 2025.
¶ 17Compliance was directed within three months of receipt of a certified copy
¶ 17The judgment contains an apparent date inconsistency: paragraph 16 refers to 21 March 2025, the date compensation was deposited, whereas the operative order specifies 23 January 2025
¶ 16–17Original Court PDF
NAGARAJAIAHvsSTATE OF KARNATAKA
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
