01Facts
The petitioner is a registered flat owners’ association representing residents of a project developed by the third respondent-builder.
p. 3Following complaints about incomplete works, TNRERA directed the builder to register the project, complete pending works, hand over maintenance of common areas, and furnish a Completion Certificate; the builder’s appeal was dismissed.
p. 3In execution proceedings, TNRERA imposed penalties and directed their recovery by the District Collector. It forwarded a recovery warrant to the Collector on 23 May 2024 under Section 40(1) of the Real Estate (Regulation and Development) Act, 2016, read with Rule 26 of the Tamil Nadu Rules, but the Collector had not initiated recovery proceedings despite the petitioner’s representations.
pp. 3–5The Association therefore sought a mandamus directing execution of the warrant and recovery of the sums as arrears of land revenue.
pp. 1–202Issues
i.1. Whether the District Collector’s failure to act on TNRERA’s recovery warrant warranted a mandamus directing recovery of the sums as arrears of land revenue.
pp. 5–6ii.2. Whether the recovery was to be completed within a time fixed by the Court.
p. 603Law Applied
Article 226 of the Constitution empowers the High Court to issue a writ of mandamus to require a public authority to perform a legally required duty.
pp. 1–2, 4–6Section 40(1) of the Real Estate (Regulation and Development) Act, 2016, read with Rule 26 of the Tamil Nadu Real Estate (Regulation and Development) Rules, 2017, was the stated basis for forwarding the recovery warrant for execution.
pp. 1–2, 4–6The order directed recovery of the sums as arrears of land revenue under the Tamil Nadu Revenue Recovery Act, 1864.
pp. 1–2, 4–6Provisions in the judgment · 3 · Linked ones open on LawLens
Real Estate (Regulation and Development) Act, 2016. Section 40Section 17Section 63
04Reasoning
TNRERA had issued and forwarded the recovery warrant in 2024, directing the Collector to recover the penalty from the builder as arrears of land revenue.
p. 4The Court noted that, despite receipt of the warrant, the Collector had taken no steps to commence recovery proceedings.
p. 5In light of that inaction and the recovery direction, the Court considered a mandamus appropriate and required the Collector to execute the warrant.
p. 605Holding
The Court allowed the writ petition and issued a mandamus directing the District Collector to execute TNRERA’s recovery order/warrant and recover the sums directed from the builder as arrears of land revenue under the Tamil Nadu Revenue Recovery Act, 1864, within three weeks of receiving a copy of the order.
p. 6No costs were awarded.
p. 6Original Court PDF
SSM NAGAR FLAT OWNERS ASSOCIATIONvsTHE DISTRICT COLLECTOR