Facts
The allottee deposited ₹1,85,000 with the Lucknow Development Authority (LDA) on 31 January 2012 for a flat in Sopan Enclave.
Source reference: p. 1LDA allotted Flat C-401 on 11 July 2014; the scheme was estimated to be completed within 24 months, but the completion certificate was issued only on 17 February 2020.
Source reference: p. 1After LDA’s 2019 demand for pending dues and possession went unanswered, the allottee sought a refund.
Source reference: p. 1The Regulatory Authority dismissed the claim on 24 February 2020.
Source reference: p. 2The Tribunal allowed the allottee’s appeal and directed LDA to refund the booking amount after a 20% deduction, with interest at MCLR + 1% until payment.
Source reference: p. 2LDA appealed, relying on brochure Clause 8.2, which provided for a 20% deduction from the registration amount and refund of the balance without interest.
Source reference: p. 2The High Court also noted that the allotment had not been cancelled and that the allottee’s wife had purchased another LDA flat in 2014.
Source reference: p. 3Issues
1. Whether Clause 8.2, requiring a 20% deduction and excluding interest on the balance refund, could be enforced against the allottee.
Source reference: p. 12. Whether the Tribunal’s refund direction involved an error of law warranting interference in the appeal.
Source reference: p. 12Law Applied
The Court applied the principles of contract law that a court may decline to enforce an unfair or unreasonable contractual term imposed by a party with superior bargaining power, relying on Pioneer Urban Land & Infrastructure Ltd. v. Govindan Raghavan and LIC of India v. Consumer Education & Research Centre.
Source reference: p. 3It also relied on the principle that compensation must be fair and proportionate to the loss and deprivation suffered, as discussed in GDA v. Balbir Singh and Parsvnath Developers Ltd. v. Mohit Khirbat.
Source reference: p. 4The Court referred to the doctrine of unjust enrichment: a person should not retain money or benefits that, in equity and good conscience, belong to another.
Source reference: p. 5Section 18 of the Real Estate (Regulation and Development) Act, 2016 was referred to in the Tribunal’s discussion of relief for delay.
Source reference: p. 2Reasoning
Clause 8.2 was, in the Court’s view, ex facie one-sided, unfair and unreasonable, and LDA therefore could not rely on it to deny interest on the refund.
Source reference: p. 13The project substantially exceeded its estimated 24-month completion period: the booking money was paid in January 2012, while the completion certificate was issued in February 2020.
Source reference: p. 13Further, LDA had not cancelled the allotment, yet retained the booking money.
Source reference: p. 13The Court considered that retention, in these circumstances, unjust enrichment and found no error of law in the Tribunal’s direction to refund 80% of the booking amount with interest.
Source reference: p. 13Holding
The Court held that Clause 8.2 did not entitle LDA to retain 20% of the booking amount without interest, and that no substantial question of law or other error warranted interference with the Tribunal’s order.
The appeal was dismissed, leaving in place the direction to refund the booking amount after a 20% deduction, with interest at MCLR + 1% until payment.
Source reference: p. 14Acts & Sections Cited
2 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.
Central Excise Act, 19441
Customs Act,19621
Original Court PDF
Lucknow Development Authority Thru. Its Authorized Signatory Mr. Rohit SinghvsShivaji Singh
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
