Facts
The appellant, a consumer in Uttar Pradesh, challenged the Uttar Pradesh Electricity Regulatory Commission’s order dated 27.01.2022 rejecting his petition for review of the Commission’s tariff order dated 07.10.2008.
Source reference: para. 1; p. 3Respondent No. 2, Jaiprakash Power Ventures Limited (JPVL), had developed a 400 MW run-of-the-river hydroelectric project in Uttarakhand and entered into a Power Purchase Agreement dated 16.01.2007 with Uttar Pradesh Power Corporation Limited (UPPCL).
Source reference: para. 2; p. 3The Commission had approved the project’s capital cost and tariff through orders dated 05.04.2007, 12.04.2007 and 07.10.2008.
Source reference: paras. 2–3; pp. 3–4In 2021, the appellant filed Petition No. 1702/2021 under Section 94(1)(f) of the Electricity Act, 2003 read with Regulation 51 of the UPERC Conduct of Business Regulations, 2019, seeking review of the 07.10.2008 tariff order.
Source reference: para. 4; p. 4Issues
1. Whether the appellant’s petition before the Commission was a petition for revision or fresh determination of tariff, rather than a petition for review of the tariff order dated 07.10.2008.
Source reference: paras. 6–12; pp. 5–102. Whether an appeal lies against the Commission’s order rejecting the review petition, or whether such an appeal is barred under Order XLVII Rule 7 of the Code of Civil Procedure, 1908.
Source reference: para. 15; p. 11Law Applied
Section 94(1)(f) of the Electricity Act, 2003 empowers a State Electricity Regulatory Commission to review its decisions, directions and orders.
Source reference: para. 9; p. 6Regulation 51(a) of the UPERC Conduct of Business Regulations, 2019 permits an aggrieved person to seek review of a Commission’s direction, decision or order, subject to the Code of Civil Procedure, 1908.
Source reference: para. 11; pp. 8–9The power of review under Section 94(1)(f) is analogous to the civil court’s review jurisdiction under Order XLVII Rule 1 CPC and is confined to the grounds recognised for review.
Source reference: para. 9; p. 6Under Order XLVII Rule 7 CPC, an appeal is not maintainable against an order rejecting a review petition.
Source reference: para. 15; p. 11Although the appellant relied on the Commission’s tariff-determination powers under Sections 62(1)(a) and 86(1)(a)–(b) of the Electricity Act, those provisions did not alter the character of the petition actually filed.
Source reference: para. 6; pp. 5–6Reasoning
The Tribunal examined the petition’s title, statutory basis and prayers.
Source reference: no citationThe petition expressly sought review under Section 94(1)(f) and Regulation 51, and its principal prayers requested review of the 07.10.2008 order on the ground that it violated the Commission’s regulations.
Source reference: paras. 8–9; pp. 6–7The requests for fresh tariff scrutiny, refund of alleged excess recoveries and filing of a fresh tariff application were ancillary and would arise only if the review were first allowed.
Source reference: para. 10; p. 8The appellant had also argued before the Commission that the tariff order contained an error apparent on the face of the record, and the Commission had framed issues concerning limitation and the existence of such an error.
Source reference: para. 11; pp. 8–9Since the appellant did not dispute the Commission’s description of the proceedings or object to the issues framed, the Tribunal held that the petition was unequivocally a review petition, not an independent tariff-revision proceeding.
Source reference: para. 12; p. 10Consequently, the Commission’s order was an order rejecting review, against which an appeal was barred by Order XLVII Rule 7 CPC.
Source reference: para. 15; p. 11Holding
The Tribunal held that the appellant had filed a review petition challenging the tariff order dated 07.10.2008, and not a petition for independent revision or redetermination of tariff.
Since the Commission had rejected that review petition on 27.01.2022, the appeal against the rejection order was not maintainable under Order XLVII Rule 7 CPC.
Source reference: para. 16; p. 11The appeal was accordingly dismissed as not maintainable, and all pending applications were disposed of.
Source reference: para. 16; p. 11Acts & Sections Cited
3 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Electricity Act, 20033
Original Court PDF
Rama Shanker AwasthivsUttar Pradesh State Electricity Regulatory Commission & Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
