Madhya Pradesh High CourtArbitration and MediationCivil Procedure and Evidence

An arbitral award cannot be set aside under Section 34 absent a statutory ground; merits review is impermissible.

Union Of Indiav.Manav Bhanot

An arbitral award cannot be set aside under Section 34 absent a statutory ground; merits review is impermissible.. Union Of India vs Manav Bhanot. Madhya Pradesh High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

Whether the arbitral award was liable to be set aside under Section 34(2)(b) of the Arbitration and Conciliation Act, 1996, on the ground that it conflicted with the public policy of India.

The court held

The Court answered the issues against the Union of India.

It also directed

It held that none of the grounds under Section 34(2)(b)(i) or (ii), including conflict with the public policy of India, had been made out, and that the alleged lack of reasoning concerning the idling claims did not warrant interference.

The arbitration appeal under Section 37 was accordingly dismissed, and the order dated 14 December 2016 upholding the arbitral award was affirmed.

01Facts

The respondent-contractor was awarded a Railway contract for constructing 24 houses at Jabalpur, originally scheduled for completion within 11 months.

¶ 2 · p. 1

The work was completed after approximately 27 months, with delay attributable to both parties.

¶ 2 · p. 1

The contractor raised several claims, including claims relating to penalty, waterproofing, doors and windows, material-price differences, pipes, and idling charges for labour, machinery, a graduate engineer, a supervisor, and a watchman.

¶ 2 · p. 1

A three-member arbitral tribunal, comprising senior Railway officers, passed an award dated 28 August 2014 allowing various claims, including Claims Nos. 11, 12 and 13 concerning idling of the graduate engineer, supervisor and watchman.

¶ 1 · p. 1 · ¶ 11 · p. 4

The Union of India challenged the award under Section 34 of the Arbitration and Conciliation Act, 1996. The Additional District Judge, Jabalpur, rejected the challenge on 14 December 2016 and upheld the award, leading to the present appeal under Section 37.

¶ 1 · p. 1

02Issues

i.Whether the arbitral award was liable to be set aside under Section 34(2)(b) of the Arbitration and Conciliation Act, 1996, on the ground that it conflicted with the public policy of India.

¶ 5, 7–10 · pp. 2–3

ii.Whether the alleged absence of detailed reasons for allowing the claims relating to idling of the graduate engineer, supervisor and watchman justified interference with the award under Section 37.

¶ 3–4 · pp. 1–2

iii.Whether the matter ought to be remanded to the arbitral tribunal for passing a fresh award.

¶ 5 · p. 2

03Law Applied

The Court applied Section 34(2)(b) of the Arbitration and Conciliation Act, 1996, under which an arbitral award may be set aside where the subject matter is not arbitrable or where the award conflicts with the public policy of India.

¶ 7 · p. 2

Explanation 1 limits conflict with public policy to cases involving fraud or corruption, violation of Sections 75 or 81, contravention of the fundamental policy of Indian law, or conflict with the most basic notions of morality or justice.

¶ 7 · pp. 2–3

Explanation 2 provides that determining whether there is a contravention of the fundamental policy of Indian law does not permit a review of the merits of the dispute.

¶ 7 · p. 3

The Court also considered the appellant’s reliance on Indian Oil Corporation v. M/s Metro Builders (Orissa) Pvt. Ltd., where absence of discernible reasoning was treated as a fundamental infirmity, but held that the statutory grounds for interference were not established in the present case.

¶ 4 · p. 2

Provisions in the judgment · 4 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 37Section 34Section 75Section 81

04Reasoning

The Union of India contended that the tribunal had given no adequate reasoning for allowing the three idling-related claims and relied on the Delhi High Court decision concerning absence of discernible reasoning.

¶ 3–4 · pp. 1–2

The High Court, however, held that the appellant had neither pleaded nor established fraud, corruption, violation of Sections 75 or 81, contravention of the fundamental policy of Indian law, or conflict with the basic notions of morality or justice.

¶ 8–9 · p. 3

It further emphasized that Explanation 2 barred a merits review of the dispute under the guise of examining public policy.

¶ 10 · p. 3

The award recorded that the contractor had produced documentary evidence supporting Claims Nos. 11, 12 and 13, and the appellant could not demonstrate any basis for taking a different view.

¶ 11 · p. 4

The Court also observed that the Union of India’s failure to properly contest the claims before the arbitral tribunal did not justify a subsequent appeal on what it considered frivolous grounds.

¶ 11 · p. 4

05Holding

The Court answered the issues against the Union of India.

¶ 10–11 · pp. 3–4

It held that none of the grounds under Section 34(2)(b)(i) or (ii), including conflict with the public policy of India, had been made out, and that the alleged lack of reasoning concerning the idling claims did not warrant interference.

¶ 10–11 · pp. 3–4

The arbitration appeal under Section 37 was accordingly dismissed, and the order dated 14 December 2016 upholding the arbitral award was affirmed.

¶ 12 · p. 5
Madhya Pradesh High Court

Original Court PDF

Union Of IndiavsManav Bhanot

Madhya Pradesh High Court · September 22, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment