Bombay High Court
Arbitration and MediationCivil Procedure and Evidence

An unsuccessful amicable-settlement attempt satisfies a pre-arbitration requirement to resolve disputes amicably.

Girish Narang vs Virendra Arora

Bombay High CourtJUDGMENT: September 29, 20263 MIN READSOURCE JUDGMENT
An unsuccessful amicable-settlement attempt satisfies a pre-arbitration requirement to resolve disputes amicably.. Girish Narang vs Virendra Arora. Bombay High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Applicant and Respondents executed a Deed of Partnership dated 1 April 2025 for the production and commercial exploitation of the film JATADHARA.

Source reference: para. 2

Clause 11 provided for amicable resolution of disputes and, if unresolved, arbitration.

Source reference: paras. 9–10

Following the film’s release, the Applicant sought disclosure of the Partnership’s financial records and reconciliation of accounts, including outstanding receipts and liabilities. He alleged that the records supplied were incomplete.

Source reference: paras. 2–3, 14–15

After discussions and notices—including a Section 21 notice dated 15 December 2025—the parties did not resolve the disputes or mutually appoint an arbitrator. The Applicant applied under Section 11 of the Arbitration and Conciliation Act, 1996.

Source reference: paras. 3, 24, 27
02

Issues

1. Whether a valid arbitration agreement existed and the disputes raised fell within its scope.

Source reference: paras. 8–12, 17–18

2. Whether the parties’ amicable-settlement process and agreed procedure for appointing an arbitrator had been exhausted or had failed.

Source reference: paras. 14–16, 24

3. Whether the Respondents’ objections concerning unverified accounts, proof of claims, liability periods, and appointment of an auditor justified refusing appointment of an arbitrator.

Source reference: paras. 19–24
03

Law Applied

Section 11 of the Arbitration and Conciliation Act, 1996 empowers the Court to secure constitution of an arbitral tribunal where the agreed appointment procedure fails; Section 11(6) applies where a party fails to act as required under that procedure.

Source reference: para. 24

Section 21 concerns commencement of arbitral proceedings and limitation, but claims may be raised before the tribunal if they fall within the arbitration agreement.

Source reference: para. 18

Section 16 recognises the tribunal’s competence to rule on its own jurisdiction, supporting restraint by the referral court from determining disputed merits at the appointment stage.

Source reference: para. 25

The Court relied on Jagdish Chander v. Ramesh Chander, (2007) 5 SCC 719, on whether contractual language constitutes an agreement to arbitrate; Powertech World Wide Ltd. v. Delvin International General Trading LLC, (2012) 1 SCC 361, on amicable-settlement steps and arbitration clauses; Adavya Projects Pvt. Ltd. v. M/s Vishal Structurals Pvt. Ltd. & Ors., 2025 INSC 507, on the limited referral-stage inquiry and Section 21 notices; and ASF Buildtech Pvt. Ltd. v. Shapoorji Pallonji and Company Pvt. Ltd., 2025 INSC 616, on avoiding a merits inquiry at the referral stage.

Source reference: paras. 12–13, 18, 20, 24–25
04

Reasoning

Clause 11 stated that unresolved disputes “shall be referred to arbitration” and provided for appointment under the Act if the parties failed to agree within 30 days; unlike the clause in Jagdish Chander, it did not require fresh consent to arbitrate.

Source reference: paras. 9–12

The record of meetings, correspondence, assurances, partial disclosure, and the Final Notice showed an attempt at amicable resolution, which had failed; the clause prescribed no particular settlement process.

Source reference: paras. 14–16

The accounting, disclosure, liability, and statutory-compliance disputes arose from the Partnership and fell within the clause. Whether the Applicant’s figures were proved, which Respondent was liable for particular periods, or whether an auditor should be appointed were matters for the tribunal, not grounds to refuse referral.

Source reference: paras. 18–23

As the parties had not mutually appointed an arbitrator despite the notices and opportunities given, the agreed appointment procedure had failed.

Source reference: para. 24
05

Holding

The Court allowed the Section 11 application and appointed Mr. Harsh Moorjani as Sole Arbitrator to adjudicate disputes arising out of and in terms of Clause 11 of the Deed of Partnership dated 1 April 2025.

It directed the parties to bear the tribunal’s fees and costs equally in the first instance, subject to the final award, and expressly left all issues on the merits open.

Source reference: paras. 28(F), 29
06

Acts & Sections Cited

4 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19964

Bombay High Court

Original Court PDF

Girish NarangvsVirendra Arora

Bombay High Court · September 29, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment