Facts
The Appellant (Union of India/CPWD) awarded a contract to the Respondent for the construction of an Administrative Building at NEIAH, Shillong, valued at ₹23.60 crores
Source reference: para. 1-2Under the NIT, the Respondent was required to submit a Trading Licence from the KHADC within one month
Source reference: para. 3Due to the Model Code of Conduct, the Respondent failed to obtain the license, which consequently delayed procurement and GST registration
Source reference: para. 4-5On 24.06.2024, the Appellant determined the contract and forfeited the Performance Guarantee (PG) of ₹1.18 crores, purportedly invoking Clause 5 of the Agreement
Source reference: para. 6, 12The Sole Arbitrator set aside the termination and ordered the release of the PG and litigation costs
Source reference: para. 8The Commercial Court at Shillong dismissed the Appellant's Section 34 challenge on 03.02.2026
Source reference: para. 10The Appellant then approached the High Court under Section 37
Source reference: para. 11Issues
1. Whether the Appellant’s invocation of Clause 5 of the GCC to determine the contract was legally valid under the terms of the agreement.
Source reference: para. 18, 232. Whether the High Court, exercising jurisdiction under Section 37 of the Arbitration Act, can interfere with concurrent findings of fact regarding the interpretation of contract clauses.
Source reference: para. 24, 27Law Applied
The court applied the restrictive principles of judicial interference under Section 34 and Section 37 of the Arbitration and Conciliation Act, 1996.
Source reference: para. 20, 25Section 37 courts cannot undertake an independent assessment of merits and must be "extremely cautious" in disturbing concurrent findings (MMTC Limited v. M/s Vedanta Limited (2019)).
Source reference: para. 25An award can only be set aside if it is contrary to fundamental policy, public interest, justice/morality, or is patently illegal (Haryana Tourism Limited v. Kandhari Beverages Limited (2022)).
Source reference: para. 26The appellate court does not sit in appeal to find if an award is right or wrong upon reappraisal of evidence (Punjab State Civil Supplies Corp. Ltd. v. Sanman Rice Mills (2024)).
Source reference: para. 27Reasoning
The Court observed that the Appellant's primary contention—that an amended Clause 5 allowed forfeiture followed by termination—was never presented before the Arbitrator
Source reference: para. 15-16Upon reviewing the GCC, the Court noted that Clause 3 specifically governs the determination of a contract for failure to proceed with work, whereas Clause 5 pertains to "Time and extension for delay"
Source reference: para. 18, 24The Arbitrator found that the Engineering-in-Charge invoked the wrong provision (Clause 5) to terminate the contract, rendering the action without jurisdiction
Source reference: para. 23-24The High Court reasoned that since the Commercial Court had already concurred with the Arbitrator’s factual interpretation of these clauses, it could not re-examine the merits or substitute its own view for that of the Arbitral Tribunal under the narrow window of Section 37
Source reference: para. 24, 27-28Holding
The High Court held that the Arbitrator’s finding regarding the invalidity of the termination under Clause 5 was a finding of fact that does not warrant interference
The High Court dismissed the appeal and upheld the judgment of the Commercial Court, directing the Appellant to satisfy the award, specifically releasing the Performance Guarantee (Claim 2) and paying the awarded expenses (Claim 6) within four weeks
Source reference: para. 28, 29, 30Original Court PDF
UNION OF INDIAvsM/S. RAJNISH INFRATECH OPC PVT. LTD.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in