Delhi High Court

Approved Resolution Plan Extinguishes Undecided Claims and Ousts Arbitral Jurisdiction Over Pre-Insolvency Disputes

Mbl Infrastructures Limited vs Pile Foundation Company

Delhi High CourtJUDGMENT: July 01, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner (MBL) was awarded a contract by Haryana PWD for road construction and subsequently issued a work order to the Respondent on November 22, 2012, for piling work

Source reference: p. 2

Disputes arose regarding delays, defective machinery, and slow progress, leading the Petitioner to terminate the contract and award the remaining work to another firm

Source reference: p. 3

The matter was referred to a Sole Arbitrator in 2014

Source reference: p. 4

During the pendency of arbitration, a Corporate Insolvency Resolution Process (CIRP) was initiated against the Petitioner on March 30, 2017

Source reference: p. 6

A Resolution Plan was approved by the NCLT on April 18, 2018, and attained finality via the NCLAT on August 16, 2019

Source reference: p. 7

Despite these developments, the Arbitrator proceeded to pass an Award on July 26, 2021, granting a net sum to the Respondent

Source reference: p. 9

The Petitioner challenged the Award under Section 34 of the Arbitration and Conciliation Act, 1996.

Source reference: no citation
02

Issues

1. Whether the Arbitral Tribunal had the jurisdiction to adjudicate claims and pass an award after a Resolution Plan had been approved under the Insolvency and Bankruptcy Code (IBC), 2016?

Source reference: p. 9, para 3

2. Whether claims that arose prior to the CIRP, but were not part of the approved Resolution Plan, stand extinguished by operation of Section 31 of the IBC?

Source reference: p. 10, para 4-5
03

Law Applied

Section 31(1) of the Insolvency and Bankruptcy Code, 2016, which stipulates that an approved Resolution Plan is binding on the corporate debtor, its employees, members, and all creditors

Source reference: p. 9

Ghanashyam Mishra & Sons Pvt. Ltd. v. Edelweiss Asset Reconstruction Co. Ltd., which established that upon approval of a resolution plan, all claims not included therein stand extinguished and cannot be initiated or continued

Source reference: p. 11, para 102.1

Electrosteel Steel Limited v. Ispat Carrier Private Limited, which held that the expiration of a moratorium does not revive extinguished claims and that adjudicatory forums lose jurisdiction to decide on such claims once the Resolution Plan is approved

Source reference: p. 12-13, para 71-72
04

Reasoning

The Court observed that the Respondent’s claims against the Petitioner existed prior to the commencement of the CIRP in March 2017

Source reference: p. 14, para 9

Under the statutory scheme of the IBC, the Respondent was required to lodge these claims with the Resolution Professional following the public announcement

Source reference: p. 14

The Court rejected the Arbitrator's reasoning that claims "not yet crystallized into a debt" fall outside the ambit of the IBC, labeling this view as contrary to established law

Source reference: p. 14, para 11-12

Once the Adjudicating Authority (NCLT) approved the Resolution Plan, all pre-existing claims not specifically accounted for in that plan were "frozen" and "extinguished"

Source reference: p. 11, 14

Consequently, the continuation of the arbitration and the subsequent rendering of the award violated the "clean slate" principle of the IBC, as the Arbitrator no longer possessed the jurisdiction to adjudicate upon extinguished liabilities

Source reference: p. 13-14
05

Holding

The Court held that the Arbitral Award was passed without jurisdiction as the underlying claims stood extinguished by the approval of the Resolution Plan under the IBC

The direct answer to the issues is that dues not forming part of the Resolution Plan cannot survive its approval, regardless of whether they were "crystallized" or not

Source reference: p. 14

Accordingly, the Court set aside the Impugned Award dated July 26, 2021, and disposed of the petition in favor of the Petitioner

Source reference: p. 15
Delhi High Court

Original Court PDF

Mbl Infrastructures LimitedvsPile Foundation Company

Delhi High Court · July 01, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment