Delhi High CourtArbitration and MediationCivil Procedure and Evidence

Arbitral Award Based on Expert Testimony and ERP Records Upheld Against Reappreciation of Evidence Under Section 34.

Madhya Bharat Power Corporation Limitedv.Voith Hydro Private Limited

Arbitral Award Based on Expert Testimony and ERP Records Upheld Against Reappreciation of Evidence Under Section 34.. Madhya Bharat Power Corporation Limited vs Voith Hydro Private Limited. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Arbitral Tribunal’s assessment of the engineering component at 6% of the contract value constituted patent illegality or double recovery

The court held

The Court dismissed the Section 34 petition, holding that the Petitioner failed to establish any grounds of patent illegality or perversity

It also directed

The Court affirmed the Tribunal's findings on all claims, including the 12% post-award interest and the cost allocation, stating they were reasoned and within the Tribunal's discretion. The stay on the enforcement of the Award was effectively vacated.

01Facts

Madhya Bharat (Petitioner/Employer) awarded a contract for Electro-Mechanical works for the Rongnichu Hydro Project to Voith Hydro (Respondent/Contractor) in 2011

p. 2

Following a suspension of work in 2013-2014, Voith Hydro invoked arbitration in 2017

pp. 2-3

The Arbitral Tribunal, relying on a Joint Expert Report, passed a unanimous Award on July 31, 2019, awarding Voith Hydro approximately ₹9.03 Crores plus foreign currency components, while rejecting Madhya Bharat's counterclaims

pp. 4-6

Madhya Bharat challenged the Award under Section 34 of the Arbitration and Conciliation Act, 1996, primarily contesting the valuation of engineering works, compensation for manufactured materials, site expenses, and loss of profits

pp. 7-9

02Issues

i.1. Whether the Arbitral Tribunal’s assessment of the engineering component at 6% of the contract value constituted patent illegality or double recovery

pp. 15 / para. 48-52

ii.2. Whether the Award for manufactured materials was unsustainable due to the non-delivery of items to the Employer

pp. 22 / para. 69-70

iii.3. Whether compensation for loss of profits could be awarded without proof of actual loss or tender break-ups

pp. 25 / para. 83-88

iv.4. Whether the grant of post-award interest at 12% and costs was justified

pp. 29 / para. 93-96

03Law Applied

The court applied the limited scope of judicial interference under Section 34 of the Arbitration and Conciliation Act, 1996, as interpreted in Associate Builders v. DDA and Ssangyong Engineering & Construction Co. Ltd. v. NHAI, which prohibits the reappreciation of evidence unless the award is perverse or patently illegal

pp. 12-13

Regarding the quantification of damages/losses, the court relied on McDermott International Inc. v. Burn Standard Co. Ltd., establishing that the choice of methodology and computation falls within the exclusive domain of the arbitrator

p. 14

Section 31A of the Act was applied regarding the Tribunal’s discretion to allocate costs

p. 30

Provisions in the judgment · 3 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 34

Indian Contract Act, 1872 Section 55Section 73

04Reasoning

The Court observed that the Tribunal’s decision on the 6% engineering cost was a fact-based finding derived from Expert testimony and the unique topographical requirements of hydro projects, which does not permit interference

¶ 54-56

On Claim II, the Court upheld the rejection of the Petitioner’s belated demand for delivery of materials, noting that the Petitioner failed to plead this earlier and that the storage/refurbishment costs had already been discounted in the award calculation

¶ 70-71

Regarding Claim IV (Loss of Profit), the Court found that the Tribunal acted reasonably by reducing the claim from 15% to 6%, noting that the Petitioner had already awarded the project to a third party, effectively terminating the contract

¶ 86-89

The Court emphasized that an Arbitrator is the "ultimate master of the quantity and quality of evidence" and held that the reliance on ERP extracts and Expert reports was a "possible view"

¶ 39, 78-79

05Holding

The Court dismissed the Section 34 petition, holding that the Petitioner failed to establish any grounds of patent illegality or perversity

¶ 99-100

The Court affirmed the Tribunal's findings on all claims, including the 12% post-award interest and the cost allocation, stating they were reasoned and within the Tribunal's discretion. The stay on the enforcement of the Award was effectively vacated.

¶ 95-98
Delhi High Court

Original Court PDF

Madhya Bharat Power Corporation LimitedvsVoith Hydro Private Limited

Delhi High Court · May 26, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment