01Facts
The parties entered into a construction contract on December 4, 2013, for a commercial complex.
¶ 2Work commenced on February 12, 2014, although a formal "notice to commence" was not issued and the sanctioned building plan was only obtained on January 19, 2016.
¶ 4, 33The respondent granted four extensions of time without levying liquidated damages, but eventually terminated the contract on May 17, 2017, alleging slow progress (approx. 60-62% completion).
¶ 9, 23An Arbitral Tribunal ruled the termination illegal, finding the respondent in material breach due to the delay in obtaining the sanctioned plan and the fact that extensions were granted without damages.
¶ 3, 10A Single Judge of the High Court set aside the award under Section 34 of the Arbitration and Conciliation Act, 1996, prompting this appeal.
¶ 1, 2902Issues
i.1. Whether the Arbitral Tribunal’s finding that the contract could only legally commence upon the Sanctioned Building Plan was perverse and contrary to the evidence on record.
¶ 34ii.2. Whether the grant of extensions "without prejudice" by the respondent constituted a waiver of the right to claim liquidated damages or blame the appellant for delay.
¶ 35-36iii.3. Whether the Single Judge correctly exercised jurisdiction under Section 34 to set aside the award on the grounds of patent illegality.
¶ 3703Law Applied
The Court applied Section 34 of the Arbitration and Conciliation Act, 1996, which permits setting aside an award for "patent illegality" appearing on the face of the award.
¶ 37It further relied on the principles of Section 37 regarding the limited scope of appellate interference, citing *Somdatt Builders-NCC-NEC(JV) vs. National Highways Authority of India*, which mandates that an appellate court must only ensure the Section 34 court acted within its limited power.
¶ 15, 30The court also considered Section 28(3), requiring the Tribunal to take into account the terms of the contract and trade usages.
¶ 16Provisions in the judgment · 11
the contract Section 27.2Section 28.5
the Act of 1996 Section 28Section 34Section 37
General Condition of Contracts Section 15Section 16Section 19Section 27.1Section 28Section 32
04Reasoning
The Division Bench found that the Arbitral Tribunal committed a fundamental error by ignoring the conduct of the parties.
Both parties had accepted February 12, 2014, as the commencement date in their pleadings and had proceeded with work and payments long before the building plan was sanctioned.
¶ 31, 33Consequently, the Tribunal’s finding that there was "no legal commencement" until 2016 was deemed perverse as no reasonable person could reach that conclusion given the evidence.
¶ 34Regarding the extensions, the Court noted the Tribunal failed to adjudicate the impact of the "without prejudice" caveat attached to the extensions granted by the respondent.
¶ 35The Court held that the Tribunal’s failure to differentiate between legal and actual commencement and its misinterpretation of the extension letters placed the award on a "wrong pedestal," justifying the Single Judge's intervention.
¶ 12, 3605Holding
The Court dismissed the appeal, upholding the Single Judge's order to set aside the arbitral award.
¶ 38The Court held that an award is vitiated by patent illegality if it draws inferences that no reasonable person could draw from the record or ignores vital evidence regarding the parties' ad idem commencement of work.
¶ 34, 37The stay on the judgment was refused.
¶ 39Original Court PDF
MBL Infrastructure Limitedvs.Hooghly River Bridges Commissioners [AO-COM/26/2025; 2026:CHC-OS:86-DB]
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
![Arbitral award based on perverse findings regarding contract commencement and unconditional extensions constitutes patent illegality.. MBL Infrastructure Limited vs. Hooghly River Bridges Commissioners [AO-COM/26/2025; 2026:CHC-OS:86-DB]. Calcutta High Court. LawLens](/stories/thumbnails/arbitral-award-based-on-perverse-findings-regarding-contract-commencement-and-unconditiona-a1e7d64270d1411ca0237bc8827664c9.webp)