Facts
The parties entered into a construction contract on December 4, 2013, for a commercial complex.
Source reference: para. 2Work commenced on February 12, 2014, although a formal "notice to commence" was not issued and the sanctioned building plan was only obtained on January 19, 2016.
Source reference: para. 4, 33The respondent granted four extensions of time without levying liquidated damages, but eventually terminated the contract on May 17, 2017, alleging slow progress (approx. 60-62% completion).
Source reference: para. 9, 23An Arbitral Tribunal ruled the termination illegal, finding the respondent in material breach due to the delay in obtaining the sanctioned plan and the fact that extensions were granted without damages.
Source reference: para. 3, 10A Single Judge of the High Court set aside the award under Section 34 of the Arbitration and Conciliation Act, 1996, prompting this appeal.
Source reference: para. 1, 29Issues
1. Whether the Arbitral Tribunal’s finding that the contract could only legally commence upon the Sanctioned Building Plan was perverse and contrary to the evidence on record.
Source reference: para. 342. Whether the grant of extensions "without prejudice" by the respondent constituted a waiver of the right to claim liquidated damages or blame the appellant for delay.
Source reference: para. 35-363. Whether the Single Judge correctly exercised jurisdiction under Section 34 to set aside the award on the grounds of patent illegality.
Source reference: para. 37Law Applied
The Court applied Section 34 of the Arbitration and Conciliation Act, 1996, which permits setting aside an award for "patent illegality" appearing on the face of the award.
Source reference: para. 37It further relied on the principles of Section 37 regarding the limited scope of appellate interference, citing *Somdatt Builders-NCC-NEC(JV) vs. National Highways Authority of India*, which mandates that an appellate court must only ensure the Section 34 court acted within its limited power.
Source reference: para. 15, 30The court also considered Section 28(3), requiring the Tribunal to take into account the terms of the contract and trade usages.
Source reference: para. 16Reasoning
The Division Bench found that the Arbitral Tribunal committed a fundamental error by ignoring the conduct of the parties.
Source reference: no citationBoth parties had accepted February 12, 2014, as the commencement date in their pleadings and had proceeded with work and payments long before the building plan was sanctioned.
Source reference: para. 31, 33Consequently, the Tribunal’s finding that there was "no legal commencement" until 2016 was deemed perverse as no reasonable person could reach that conclusion given the evidence.
Source reference: para. 34Regarding the extensions, the Court noted the Tribunal failed to adjudicate the impact of the "without prejudice" caveat attached to the extensions granted by the respondent.
Source reference: para. 35The Court held that the Tribunal’s failure to differentiate between legal and actual commencement and its misinterpretation of the extension letters placed the award on a "wrong pedestal," justifying the Single Judge's intervention.
Source reference: para. 12, 36Holding
The Court dismissed the appeal, upholding the Single Judge's order to set aside the arbitral award.
The Court held that an award is vitiated by patent illegality if it draws inferences that no reasonable person could draw from the record or ignores vital evidence regarding the parties' ad idem commencement of work.
Source reference: para. 34, 37The stay on the judgment was refused.
Source reference: para. 39Original Court PDF
MBL Infrastructure Limitedvs.Hooghly River Bridges Commissioners [AO-COM/26/2025; 2026:CHC-OS:86-DB]
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in