Delhi High Court

Arbitral Award renders unenforceable if claims are not part of a NCLT-approved Resolution Plan.

Mbl Infrastructures Limited vs Ms Pile Foundation Company

Delhi High CourtJUDGMENT: July 01, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner (MBL) was awarded a contract by NHAI for bridge construction in Bihar

Source reference: p. 2

On June 13, 2012, the Petitioner issued a work order to the Respondent for piling work valued at Rs. 4.03 Crores

Source reference: p. 2

Disputes arose regarding mobilization delays and alleged abandonment of work, leading to the appointment of a Sole Arbitrator in May 2014

Source reference: p. 3-4

During the pendency of arbitration, Corporate Insolvency Resolution Process (CIRP) was initiated against the Petitioner on March 30, 2017, by the NCLT, Kolkata

Source reference: p. 6

A Resolution Plan was subsequently approved by the NCLT on April 18, 2018, and upheld by the NCLAT on August 16, 2019

Source reference: p. 6-7

Despite these developments, the Arbitrator proceeded to pass an award on July 26, 2021, reasoning that the Respondent’s claims had not "crystallized" into a debt prior to the IBC proceedings and were thus not extinguished

Source reference: p. 7-8
02

Issues

1. Whether the dues payable to a creditor survive the approval of a Resolution Plan under the Insolvency and Bankruptcy Code (IBC) if such claims were not included in the approved plan

Source reference: p. 9 / para. 4

2. Whether an Arbitral Tribunal retains jurisdiction to adjudicate and award claims against a Corporate Debtor after a Resolution Plan has attained finality

Source reference: p. 9 / para. 3
03

Law Applied

The Court applied Section 31(1) of the Insolvency and Bankruptcy Code, 2016, which mandates that an approved Resolution Plan is binding on the corporate debtor, its employees, members, and creditors

Source reference: p. 9

The Court relied on the principle established in Ghanashyam Mishra & Sons Pvt. Ltd. v. Edelweiss Asset Reconstruction Company Ltd. (2021), which held that once a resolution plan is approved, all claims not part of the plan stand extinguished

Source reference: p. 10-11

It further applied Electrosteel Steel Limited v. Ispat Carrier Private Limited (2025), which clarified that a successful resolution applicant cannot be faced with "undecided claims" (the "hydra head" popping up) and that adjudicatory forums lose jurisdiction over extinguished claims

Source reference: p. 12-13
04

Reasoning

The Court reasoned that the Arbitrator erred in law by holding that the IBC did not apply to "uncrystallized" claims

Source reference: p. 14

Once the NCLT initiated CIRP on March 30, 2017, and issued a public announcement, the Respondent was statutory obligated to lodge its claims with the Resolution Professional

Source reference: p. 13

Since the Resolution Plan attained finality upon approval by the NCLT and NCLAT, any claim not included therein was extinguished by operation of law

Source reference: p. 14

The Court concluded that the IBC overrides inconsistent proceedings and that the Arbitrator’s continuation of the proceedings—and the subsequent issuance of an award for a net sum of Rs. 27,77,438—contravened the "clean slate" principle of the insolvency framework

Source reference: p. 11, 14
05

Holding

The Court answered that no claims survive post-Resolution Plan approval if they are not part of said plan

The Court held that the Arbitrator lacked jurisdiction to pass the impugned Award as the underlying claims stood extinguished by the approved Resolution Plan

Source reference: p. 14

Consequently, the Court set aside the Arbitral Award dated July 26, 2021, and disposed of the petition in favor of the Petitioner

Source reference: p. 14
Delhi High Court

Original Court PDF

Mbl Infrastructures LimitedvsMs Pile Foundation Company

Delhi High Court · July 01, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment