Facts
The Petitioner (MBL) was awarded a contract by NHAI for bridge construction in Bihar
Source reference: p. 2On June 13, 2012, the Petitioner issued a work order to the Respondent for piling work valued at Rs. 4.03 Crores
Source reference: p. 2Disputes arose regarding mobilization delays and alleged abandonment of work, leading to the appointment of a Sole Arbitrator in May 2014
Source reference: p. 3-4During the pendency of arbitration, Corporate Insolvency Resolution Process (CIRP) was initiated against the Petitioner on March 30, 2017, by the NCLT, Kolkata
Source reference: p. 6A Resolution Plan was subsequently approved by the NCLT on April 18, 2018, and upheld by the NCLAT on August 16, 2019
Source reference: p. 6-7Despite these developments, the Arbitrator proceeded to pass an award on July 26, 2021, reasoning that the Respondent’s claims had not "crystallized" into a debt prior to the IBC proceedings and were thus not extinguished
Source reference: p. 7-8Issues
1. Whether the dues payable to a creditor survive the approval of a Resolution Plan under the Insolvency and Bankruptcy Code (IBC) if such claims were not included in the approved plan
Source reference: p. 9 / para. 42. Whether an Arbitral Tribunal retains jurisdiction to adjudicate and award claims against a Corporate Debtor after a Resolution Plan has attained finality
Source reference: p. 9 / para. 3Law Applied
The Court applied Section 31(1) of the Insolvency and Bankruptcy Code, 2016, which mandates that an approved Resolution Plan is binding on the corporate debtor, its employees, members, and creditors
Source reference: p. 9The Court relied on the principle established in Ghanashyam Mishra & Sons Pvt. Ltd. v. Edelweiss Asset Reconstruction Company Ltd. (2021), which held that once a resolution plan is approved, all claims not part of the plan stand extinguished
Source reference: p. 10-11It further applied Electrosteel Steel Limited v. Ispat Carrier Private Limited (2025), which clarified that a successful resolution applicant cannot be faced with "undecided claims" (the "hydra head" popping up) and that adjudicatory forums lose jurisdiction over extinguished claims
Source reference: p. 12-13Reasoning
The Court reasoned that the Arbitrator erred in law by holding that the IBC did not apply to "uncrystallized" claims
Source reference: p. 14Once the NCLT initiated CIRP on March 30, 2017, and issued a public announcement, the Respondent was statutory obligated to lodge its claims with the Resolution Professional
Source reference: p. 13Since the Resolution Plan attained finality upon approval by the NCLT and NCLAT, any claim not included therein was extinguished by operation of law
Source reference: p. 14The Court concluded that the IBC overrides inconsistent proceedings and that the Arbitrator’s continuation of the proceedings—and the subsequent issuance of an award for a net sum of Rs. 27,77,438—contravened the "clean slate" principle of the insolvency framework
Source reference: p. 11, 14Holding
The Court answered that no claims survive post-Resolution Plan approval if they are not part of said plan
The Court held that the Arbitrator lacked jurisdiction to pass the impugned Award as the underlying claims stood extinguished by the approved Resolution Plan
Source reference: p. 14Consequently, the Court set aside the Arbitral Award dated July 26, 2021, and disposed of the petition in favor of the Petitioner
Source reference: p. 14Original Court PDF
Mbl Infrastructures LimitedvsMs Pile Foundation Company
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in