Delhi High CourtInsolvency and Bankruptcy LawArbitration and Mediation

Arbitral Award renders unenforceable if claims are not part of a NCLT-approved Resolution Plan.

Mbl Infrastructures Limitedv.Ms Pile Foundation Company

Arbitral Award renders unenforceable if claims are not part of a NCLT-approved Resolution Plan.. Mbl Infrastructures Limited vs Ms Pile Foundation Company. Delhi High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the dues payable to a creditor survive the approval of a Resolution Plan under the Insolvency and Bankruptcy Code (IBC) if such claims were not included in the approved plan

The court held

The Court answered that no claims survive post-Resolution Plan approval if they are not part of said plan

It also directed

The Court held that the Arbitrator lacked jurisdiction to pass the impugned Award as the underlying claims stood extinguished by the approved Resolution Plan

Consequently, the Court set aside the Arbitral Award dated July 26, 2021, and disposed of the petition in favor of the Petitioner

01Facts

The Petitioner (MBL) was awarded a contract by NHAI for bridge construction in Bihar

p. 2

On June 13, 2012, the Petitioner issued a work order to the Respondent for piling work valued at Rs. 4.03 Crores

p. 2

Disputes arose regarding mobilization delays and alleged abandonment of work, leading to the appointment of a Sole Arbitrator in May 2014

pp. 3-4

During the pendency of arbitration, Corporate Insolvency Resolution Process (CIRP) was initiated against the Petitioner on March 30, 2017, by the NCLT, Kolkata

p. 6

A Resolution Plan was subsequently approved by the NCLT on April 18, 2018, and upheld by the NCLAT on August 16, 2019

pp. 6-7

Despite these developments, the Arbitrator proceeded to pass an award on July 26, 2021, reasoning that the Respondent’s claims had not "crystallized" into a debt prior to the IBC proceedings and were thus not extinguished

pp. 7-8

02Issues

i.1. Whether the dues payable to a creditor survive the approval of a Resolution Plan under the Insolvency and Bankruptcy Code (IBC) if such claims were not included in the approved plan

p. 9 / para. 4

ii.2. Whether an Arbitral Tribunal retains jurisdiction to adjudicate and award claims against a Corporate Debtor after a Resolution Plan has attained finality

p. 9 / para. 3

03Law Applied

The Court applied Section 31(1) of the Insolvency and Bankruptcy Code, 2016, which mandates that an approved Resolution Plan is binding on the corporate debtor, its employees, members, and creditors

p. 9

The Court relied on the principle established in Ghanashyam Mishra & Sons Pvt. Ltd. v. Edelweiss Asset Reconstruction Company Ltd. (2021), which held that once a resolution plan is approved, all claims not part of the plan stand extinguished

pp. 10-11

It further applied Electrosteel Steel Limited v. Ispat Carrier Private Limited (2025), which clarified that a successful resolution applicant cannot be faced with "undecided claims" (the "hydra head" popping up) and that adjudicatory forums lose jurisdiction over extinguished claims

pp. 12-13

Provisions in the judgment · 6 · Linked ones open on LawLens

Insolvency and Bankruptcy Code, 2016. Section 7Section 13Section 14Section 31

Code of Civil Procedure, 1908 Section 47

Arbitration and Conciliation Act, 1996 Section 34

04Reasoning

The Court reasoned that the Arbitrator erred in law by holding that the IBC did not apply to "uncrystallized" claims

p. 14

Once the NCLT initiated CIRP on March 30, 2017, and issued a public announcement, the Respondent was statutory obligated to lodge its claims with the Resolution Professional

p. 13

Since the Resolution Plan attained finality upon approval by the NCLT and NCLAT, any claim not included therein was extinguished by operation of law

p. 14

The Court concluded that the IBC overrides inconsistent proceedings and that the Arbitrator’s continuation of the proceedings—and the subsequent issuance of an award for a net sum of Rs. 27,77,438—contravened the "clean slate" principle of the insolvency framework

p. 11, 14

05Holding

The Court answered that no claims survive post-Resolution Plan approval if they are not part of said plan

¶ 10

The Court held that the Arbitrator lacked jurisdiction to pass the impugned Award as the underlying claims stood extinguished by the approved Resolution Plan

p. 14

Consequently, the Court set aside the Arbitral Award dated July 26, 2021, and disposed of the petition in favor of the Petitioner

p. 14
Delhi High Court

Original Court PDF

Mbl Infrastructures LimitedvsMs Pile Foundation Company

Delhi High Court · July 01, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment