01Facts
The appellant awarded KMV Projects Package A-4 for construction of Adarsha Vidyalayas and girls’ hostels in Bidar District under the RMSA scheme.
The contract incorporated a price-adjustment clause under Clause 39 of the Conditions of Contract.
Although the stipulated completion period expired on 16 February 2015, the works were completed later, allegedly due to delays attributable to the appellant, including delay in handing over sites, issuing drawings, approving work slips and releasing payments.
¶ 5–10A supplementary agreement increased the contract value and provided that the applicability of the price-adjustment clause would be decided after a Government enquiry.
¶ 8–9After the Government ultimately permitted price adjustment for the relevant packages, KMV invoked arbitration.
The Sole Arbitrator partly allowed claims for price adjustment, unproductive overhead charges, loss of expected profits and costs, awarding a total of ₹3,80,58,227 with interest.
¶ 16–23The appellant’s petition under Section 34 of the Arbitration and Conciliation Act, 1996 was dismissed by the Commercial Court.
The appellant therefore filed the present appeal under Section 13(1A) of the Commercial Courts Act, 2015 read with Section 37(1)(c) of the Arbitration and Conciliation Act, 1996.
¶ 102Issues
i.Whether the Arbitral Tribunal was justified in treating Clause 39, providing for price adjustment, as part of the parties’ contract.
¶ 24–29ii.Whether the awards under Claim No. 1 for price adjustment, Claim No. 6(a) for unproductive overhead charges, and Claim No. 7 for loss of expected profits were supported by pleadings, evidence and relevant contractual or legal principles.
¶ 29–50iii.Whether the findings and awards under the impugned claims disclosed patent illegality warranting interference under Sections 34 and 37 of the Arbitration and Conciliation Act, 1996.
¶ 37, 43, 50–53iv.Whether the consequential award of interest and litigation costs could survive if the substantive claims were set aside.
¶ 5203Law Applied
The Court applied Sections 34 and 37 of the Arbitration and Conciliation Act, 1996, under which an arbitral award may be set aside for patent illegality, including an award unsupported by evidence or relevant material, while recognising that courts should not ordinarily interfere with an arbitral tribunal’s plausible contractual interpretation.
¶ 28, 37The Court relied on McDermott International Inc. v. Burn Standard Co. Ltd., (2006) 11 SCC 181, concerning the use of the Hudson formula for assessing prolongation-related claims, but held that a formula cannot substitute proof of actual loss.
¶ 39, 46It referred to A.T. Brij Paul Singh v. State of Gujarat, (1984) 4 SCC 59, and MSK Projects India (JV) Ltd. v. State of Rajasthan, (2011) 10 SCC 573, for the proposition that loss of profit may be recoverable where the employer breaches the contract.
¶ 46However, Bharat Coking Coal Ltd. v. L.K. Ahuja, (2004) 5 SCC 109, requires a contractor claiming loss of profit from delayed works to plead and establish that it could have utilised its resources or funds in other profitable business.
¶ 48The Court further applied UNIBROS v. All India Radio, 2023 SCC OnLine SC 1366, which requires proof of delay, absence of contractor responsibility, the contractor’s established status, and credible evidence of actual loss of profitability or missed opportunities; formulae such as Hudson’s are only aids to quantification and cannot independently prove loss.
¶ 49Provisions in the judgment · 5 · Linked ones open on LawLens
Commercial Courts Act, 2015 Section 13
Arbitration and Conciliation Act, 1996 Section 11Section 32Section 34Section 37
04Reasoning
The Court upheld the Tribunal’s interpretation that Clause 39 formed part of the contract because the executed Agreement expressly incorporated the Conditions of Contract and Contract Data, and no exclusion of Clause 39 appeared in the signed documents.
¶ 25–29This was a reasoned interpretation of the contract within the Tribunal’s jurisdiction and did not warrant interference under Sections 34 or 37.
¶ 25–29However, the awards under Claims 1, 6(a) and 7 were unsupported by proof.
For the price-adjustment claim, KMV produced neither a calculation sheet nor documents showing how the claimed amount was derived under the contractual formulae; the Tribunal impermissibly treated the appellant’s failure to respond to a letter mentioning the bill as proof of the claim.
¶ 32–37The overhead claim was based on an assumed 10% rate, although no evidence established that the overheads represented 10% of the contract value.
¶ 38–43A witness’s denial of a suggestion in cross-examination could not amount to an admission by the appellant.
¶ 38–43The loss-of-profit claim likewise lacked supporting pleadings and evidence.
¶ 44–50The Tribunal assumed a 10% profit margin and calculated compensation for the prolonged period, but KMV neither pleaded nor proved any actual loss, alternative projects, or missed business opportunities.
¶ 44–50Applying Bharat Coking Coal and UNIBROS, the Court held that such mathematical assumptions and formulae could not replace proof of injury.
¶ 44–50Since the substantive claims were unsustainable, the related interest and costs awards also could not stand.
¶ 5205Holding
The Court held that the Tribunal’s interpretation incorporating the price-adjustment clause was permissible, but the awards under Claim Nos. 1, 6(a) and 7 were patently illegal because they were not supported by pleadings, evidence or reliable computation.
¶ 52–53The awards of interest on those claims and costs under Claim No. 11 were consequently also set aside.
¶ 52–53The appeal was allowed to that extent, and the arbitral award was set aside insofar as it awarded amounts under Claim Nos. 1, 6(a), 7 and 11.
¶ 52–53Original Court PDF
STATE PROJECTvsM/S KMV PROJECTS
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
