Bombay High Court

Arbitration clause in a retirement deed extends to a simultaneously executed, interconnected MOU for composite transactions.

Mahindra Mangilalji Jain v. M/s Radha Construction Co and Ors. [2026:BHC-OS:5596]

Bombay High Court3 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Applicant/Petitioner was a partner in Respondent No. 1, a firm developing 'Ventura Commercial Hub'.

Source reference: para. 2

On 16 October 2017, the parties executed four simultaneous documents to facilitate the Petitioner’s exit: a Retirement-cum-Partnership Deed, a Deed of Cancellation, an Allotment Letter for 5,000 sq. ft. of space, and a Memorandum of Understanding (MOU).

Source reference: para. 3, 20

The Retirement Deed contained an arbitration clause (Clause 13), but the MOU, which detailed the payment of ₹17.60 crores as consideration for retirement, did not.

Source reference: para. 21-22

The Respondents defaulted on payment.

Source reference: no citation

The Petitioner sought appointment of an arbitrator under Section 11 and interim measures under Section 9 of the Arbitration Act to secure the 5,000 sq. ft. area.

Source reference: para. 5, 10

Respondents contested the existence of an arbitration agreement for disputes arising from the MOU.

Source reference: para. 14
02

Issues

Whether an arbitration clause contained in a Retirement Deed can be invoked for disputes arising out of a mid-transaction MOU that lacks such a clause but forms part of a composite transaction.

Source reference: para. 23, 31

Whether the "doctrine of election" bars the Petitioner from seeking arbitration when the MOU provides for specific consequences of default, such as reinstatement of partnership.

Source reference: para. 16, 48
03

Law Applied

The Court applied Section 11 and Section 9 of the Arbitration and Conciliation Act, 1996.

Source reference: no citation

It relied on the principle of "composite transactions" established in *Chloro Controls India Pvt. Ltd. v. Severn Trent Water Purification Inc.*, which holds that non-signatories or ancillary agreements can be bound by an arbitration clause in a mother agreement if they are part of a single commercial project.

Source reference: para. 35

This was reinforced by *Ameet Lalchand Shah v. Rishabh Enterprises*, where the Apex Court held that interconnected agreements executed for a common object must be referred to arbitration collectively.

Source reference: para. 35-36

The Court also cited the Constitution Bench in *Cox and Kings Ltd. v. SAP India Pvt. Ltd.*, affirming that in composite transactions involving multiple agreements, the court must assess if the agreements are consequential or follow-ups to the principal agreement.

Source reference: para. 37-38
04

Reasoning

The Court determined that the Retirement Deed was the "principal/mother document" while the MOU and Allotment Letter were ancillary documents executed to give effect to the Petitioner’s exit.

Source reference: para. 33, 36

Since all four documents were executed on the same day for the sole purpose of the Petitioner’s retirement, they constituted a single commercial transaction.

Source reference: para. 33, 39

The Court rejected the Respondents' "entire agreement" argument, noting that the MOU was inseparably intertwined with the Retirement Deed and had no independent legs to stand on.

Source reference: para. 39

Regarding the doctrine of election, the Court held it inapplicable because the Arbitral Tribunal, not the Court at this stage, should decide whether the Petitioner is entitled to monetary consideration or reinstatement.

Source reference: para. 48

The Court found it necessary to preserve the 5,000 sq. ft. area as it forms the subject matter of the dispute and acts as security for the agreed consideration.

Source reference: para. 45
05

Holding

The Court answered Issue 1 in the affirmative, holding that the arbitration clause in the Retirement Deed governs the MOU disputes as they comprise a composite transaction.

It answered Issue 2 in the negative, leaving the choice of relief to the Arbitral Tribunal.

Source reference: para. 48, 55

The Court allowed the Section 11 application, appointing Smt. Justice Sadhana Jadhav (Retd.) as Sole Arbitrator.

Source reference: para. 53

Under Section 9, it directed the Court Receiver to retain physical possession of five specific units (totaling 4,920 sq. ft.) and restrained Respondents from creating third-party rights therein pending the final award.

Source reference: para. 54
Bombay High Court

Original Court PDF

Mahindra Mangilalji Jain v. M/s Radha Construction Co and Ors. [2026:BHC-OS:5596]

Bombay High Court

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment