Bombay High Court

Arbitration Clause in Main Contract is Not Incorporated into Sub-Contract Without Specific Reference to Arbitration

Apurvakriti Infrastructure Private Limited vs Tata Projects Limited

Bombay High CourtJUDGMENT: June 17, 20262 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Applicant, a sub-contractor, entered into an Agreement-cum-Work Order dated March 2, 2015, with Respondent No. 1 (the main contractor for CIDCO) for track work on the Navi Mumbai Metro project

Source reference: p. 2

Following disputes over unpaid dues, the Applicant invoked arbitration under Clause 31.3 of the Special Conditions of Contract (SCC) and General Conditions of Contract (GCC) executed between Respondent No. 1 and CIDCO

Source reference: p. 3

The Applicant contended that although the Work Order did not contain an independent arbitration clause, the GCC/SCC were incorporated by reference through Annexures attached to the Work Order

Source reference: p. 3, 6

Respondent No. 1 resisted the application, arguing that there was no specific incorporation of the arbitration clause into their bipartite agreement

Source reference: p. 4
02

Issues

1. Whether an arbitration clause contained in a main contract between an employer (CIDCO) and a contractor (Respondent No. 1) is incorporated by general reference into a sub-contract (Work Order) between the contractor and a sub-contractor (Applicant).

Source reference: p. 8 / para. 8

2. Whether the court should refer the issue of the existence of the arbitration agreement to the Arbitral Tribunal under Section 16 of the Arbitration and Conciliation Act, 1996.

Source reference: p. 13 / para. 11
03

Law Applied

Section 7(5) of the Arbitration and Conciliation Act, 1996, which governs incorporation by reference

Source reference: p. 8

M. R. Engineers and Contractors Pvt. Ltd. v. Som Datt Builders Ltd., holding that a general reference to another document is insufficient to incorporate an arbitration clause unless there is a "specific reference" to that clause

Source reference: p. 9, para 8(ii)

Inox Wind Limited v. Thermocables Limited, specifically "Category 3" (two-contract cases), which mandates a stricter rule of construction requiring specific mention of the arbitration clause to bind a sub-contractor

Source reference: p. 11-12
04

Reasoning

The Court examined the Work Order and noted that while Annexures 4 and 5 referred to CIDCO's SCC and GCC, the Work Order itself lacked an independent arbitration provision

Source reference: p. 12

Applying the M.R. Engineers test, the Court found that the reference was general and directed toward technical specifications and performance standards ("back to back" execution) rather than dispute resolution

Source reference: p. 7, 13

The Court distinguished this "two-contract" scenario (Contractor-Subcontractor) from "single-contract" standard form cases, noting that a stricter rule of incorporation applies

Source reference: p. 12

The Court rejected the Applicant's plea to delegate this determination to a Tribunal under Section 16, asserting that the referral court must perform a prima facie determination of the "existence" of the agreement; since the Work Order lacked a specific reference to Clause 31.3, no agreement existed in the eyes of the law

Source reference: p. 14-15
05

Holding

The Court answered the issues in the negative, holding that Clause 31 of the GCC between Respondent No. 1 and CIDCO was not incorporated into the Work Order dated March 2, 2015

In the absence of a valid arbitration agreement between the parties, the Court cannot exercise its powers under Section 11. Consequently, the Commercial Arbitration Application was dismissed

Source reference: p. 15
Bombay High Court

Original Court PDF

Apurvakriti Infrastructure Private LimitedvsTata Projects Limited

Bombay High Court · June 17, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment