01Facts
The Applicant, a sub-contractor, entered into an Agreement-cum-Work Order dated March 2, 2015, with Respondent No. 1 (the main contractor for CIDCO) for track work on the Navi Mumbai Metro project
p. 2Following disputes over unpaid dues, the Applicant invoked arbitration under Clause 31.3 of the Special Conditions of Contract (SCC) and General Conditions of Contract (GCC) executed between Respondent No. 1 and CIDCO
p. 3The Applicant contended that although the Work Order did not contain an independent arbitration clause, the GCC/SCC were incorporated by reference through Annexures attached to the Work Order
p. 3, 6Respondent No. 1 resisted the application, arguing that there was no specific incorporation of the arbitration clause into their bipartite agreement
p. 402Issues
i.1. Whether an arbitration clause contained in a main contract between an employer (CIDCO) and a contractor (Respondent No. 1) is incorporated by general reference into a sub-contract (Work Order) between the contractor and a sub-contractor (Applicant).
p. 8 / para. 8ii.2. Whether the court should refer the issue of the existence of the arbitration agreement to the Arbitral Tribunal under Section 16 of the Arbitration and Conciliation Act, 1996.
p. 13 / para. 1103Law Applied
Section 7(5) of the Arbitration and Conciliation Act, 1996, which governs incorporation by reference
p. 8M. R. Engineers and Contractors Pvt. Ltd. v. Som Datt Builders Ltd., holding that a general reference to another document is insufficient to incorporate an arbitration clause unless there is a "specific reference" to that clause
p. 9, para 8(ii)Inox Wind Limited v. Thermocables Limited, specifically "Category 3" (two-contract cases), which mandates a stricter rule of construction requiring specific mention of the arbitration clause to bind a sub-contractor
pp. 11-12Provisions in the judgment · 4 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 7Section 11Section 16Section 21
04Reasoning
The Court examined the Work Order and noted that while Annexures 4 and 5 referred to CIDCO's SCC and GCC, the Work Order itself lacked an independent arbitration provision
p. 12Applying the M.R. Engineers test, the Court found that the reference was general and directed toward technical specifications and performance standards ("back to back" execution) rather than dispute resolution
p. 7, 13The Court distinguished this "two-contract" scenario (Contractor-Subcontractor) from "single-contract" standard form cases, noting that a stricter rule of incorporation applies
p. 12The Court rejected the Applicant's plea to delegate this determination to a Tribunal under Section 16, asserting that the referral court must perform a prima facie determination of the "existence" of the agreement; since the Work Order lacked a specific reference to Clause 31.3, no agreement existed in the eyes of the law
pp. 14-1505Holding
The Court answered the issues in the negative, holding that Clause 31 of the GCC between Respondent No. 1 and CIDCO was not incorporated into the Work Order dated March 2, 2015
p. 15In the absence of a valid arbitration agreement between the parties, the Court cannot exercise its powers under Section 11. Consequently, the Commercial Arbitration Application was dismissed
p. 15Original Court PDF
Apurvakriti Infrastructure Private LimitedvsTata Projects Limited
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
