Facts
The North Eastern Railway (NER) floated a tender for civil engineering and electrification works via EPC mode
Source reference: p. 1-2The Petitioner (Sannverse) and Respondent (Konkan Railway) entered into a Memorandum of Understanding (MOU) dated 29.10.2025 to jointly participate in the tender
Source reference: p. 2Pursuant to the MOU, the Petitioner provided a Bank Guarantee of Rs. 2 Crores as bid security
Source reference: p. 2The Respondent was awarded the work and subsequently issued a letter to the Petitioner on 01.04.2026 for back-to-back performance
Source reference: p. 2Disputes arose regarding delays in submitting performance securities, leading the Petitioner to file this petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking to restrain the Respondent from encashing the Bank Guarantee and taking coercive actions
Source reference: p. 1-2The court raised a preliminary objection regarding the maintainability of the petition due to the absence of an arbitration clause in the MOU
Source reference: p. 3Issues
1. Whether a Section 9 petition is maintainable in the absence of an express arbitration agreement between the parties
Source reference: p. 62. Whether an arbitration clause from a principal contract (NER and Respondent) can be incorporated by reference into a subcontract (Respondent and Petitioner) without specific mention
Source reference: p. 4-5Law Applied
The court applied Section 9 of the Arbitration and Conciliation Act, 1996, which requires the existence of an arbitration agreement as a prerequisite for interim relief
Source reference: p. 6It relied heavily on the precedent set in NBCC (India) Limited v. Zillion Infrastructure Pvt. Ltd., which established that a general reference to a principal contract in a secondary contract does not ipso facto incorporate an arbitration clause unless there is a specific mention
Source reference: p. 3-4The court also distinguished State of U.P. v. Combined Chemicals Company Pvt. Ltd. regarding the binding nature of tender documents between the same parties and emphasized that party autonomy is the "hallmark of arbitration"
Source reference: p. 4, 6Reasoning
The Court examined the MOU dated 29.10.2025 and found that Clause 5 only provided for dispute resolution through "mutual discussion or negotiations," with no mention of arbitration
Source reference: p. 4The Petitioner argued that because the MOU was an outcome of the NER tender (which contained an arbitration clause), that clause should be "borrowed" into the MOU
Source reference: p. 4The Court rejected this, noting that the Petitioner failed to show any term in the MOU that specifically incorporated the RFP/Tender's arbitration clause by reference
Source reference: p. 5Following the NBCC ruling, the Court held that since the MOU was a subcontract between different parties than the principal contract, a literal or implied "transplanting" of the arbitration clause could not be assumed
Source reference: p. 5Without evidence that the parties were ad idem (in agreement) regarding arbitration at the time of execution, the Court cannot "stitch" such a clause into the agreement
Source reference: p. 6Holding
The Court held that the petition under Section 9 is not maintainable because no arbitration agreement exists between the Petitioner and the Respondent
The Court dismissed the petition and all pending applications, vacated any existing interim orders, and granted the Petitioner liberty to pursue other legal remedies
Source reference: p. 6-7Original Court PDF
Sannverse Railtech Private LimitedvsKonkan Railway Corporation Limited
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in