Facts
The Appellant, TT Energy Private Limited, entered into an Implementation Agreement (IA) on 03.09.2008 with the State of Sikkim for a hydroelectric project
Source reference: p. 3On 08.02.2012, the State issued a notification closing the project, leading the Appellant to invoke an arbitration clause in 2014, though proceedings did not progress
Source reference: p. 3In 2025, Respondent No. 1 issued a new Request for Proposal (RFP) for the same project
Source reference: p. 3The Appellant filed a writ petition (WP(C) No. 68 of 2025) seeking to quash the RFP and enforce the 2008 IA
Source reference: p. 3The Single Judge dismissed the petition as not maintainable, holding that the existence of an arbitration clause in the IA survived for dispute resolution despite questions on the IA's subsistence
Source reference: para. 11, 13Issues
1. Whether the Writ Court was correct in dismissing the petition as non-maintainable due to the existence of an arbitration clause in the Implementation Agreement
Source reference: p. 2-42. Whether Clause 9.2 of the Implementation Agreement, which restricted the Arbitral Tribunal’s power to grant interim relief, is legally enforceable
Source reference: p. 5Law Applied
The court applied the principle of "separability" of arbitration clauses, which ensures that an arbitration agreement remains valid for resolving disputes even if the underlying contract is claimed to be terminated or non-existent
Source reference: para. 11Section 17 of the Arbitration and Conciliation Act, 1996, which empowers Arbitral Tribunals to grant interim measures
Source reference: p. 5-6Statutory powers granted to a tribunal cannot be curtailed by private agreement between parties
Source reference: p. 6Reasoning
The Court observed that the dispute involved significant factual disagreements—specifically regarding the 2012 project closure and the Appellant's alleged abandonment of earlier arbitration—which are better suited for an arbitral tribunal than a Writ Court
Source reference: para. 7The Division Bench concurred with the Single Judge that the writ jurisdiction under Article 226 cannot be used to oust a valid arbitration clause when disputed questions of fact arise from a contract
Source reference: para. 7, 10Regarding Clause 9.2 of the IA, which prohibited the tribunal from granting injunctions, the Court reasoned that such a clause directly contravenes Section 12 and Section 17 of the Arbitration and Conciliation Act, 1996
Source reference: p. 6Since the Respondents agreed not to insist on this clause, the Court found it unenforceable as it attempted to bypass mandatory statutory provisions
Source reference: para. 9-10Holding
The Court upheld the Single Judge's decision that the writ petition was not maintainable due to the alternative remedy of arbitration
Declared Clause 9.2 of the Implementation Agreement unenforceable as it illegally curtailed the tribunal's power to grant interim relief
Source reference: para. 10With the consent of both parties, the Court appointed Mr. Justice Vineet Saran (Retd.) as the Sole Arbitrator. The arbitration is to be conducted in Sikkim per the Fourth Schedule of the Act
Source reference: para. 11-13The writ appeal was disposed of accordingly
Source reference: para. 14Original Court PDF
TT Energy Private LimitedvsPrincipal Chief Engineer cum Secretary, Energy and Power Department, Government of Sikkim and Anr.
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in