Delhi High Court

Arbitrator’s exclusive domain over evidence quantum and plausible contractual interpretation precludes Section 34 interference.

National Highways And Infrastructure Development Corporation Limited vs Intercontinental Consultants And Technocrats Private Limited In Joint Venture With Anandjiwala Infra Advisory Pvt. Ltd.

Delhi High CourtJUDGMENT: April 20, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Petitioner (NHIDCL) and Respondent entered into a Contract Agreement (CA) on 22.02.2021 for consultancy services regarding the Zojila Tunnel project

Source reference: p. 2, para 2

On 09.04.2021, the Petitioner suspended the Respondent’s services and subsequently issued a Show Cause Notice (SCN) for termination on 07.07.2021, alleging fraudulent practices in the bidding process

Source reference: p. 2, para 2.1

The Respondent challenged these actions in W.P.(C) 10268/2021.

Source reference: p. 2-3, para 2.2

During those proceedings, the Petitioner stated it would revoke the suspension, withdraw the fresh tender, and allow the Respondent to continue the work

Source reference: p. 2-3, para 2.2

Following revocation, the Respondent sought payment for the suspension period (April to August 2021) and withheld bills.

Source reference: p. 3, para 2.3

Upon the Petitioner's failure to pay, arbitration was invoked

Source reference: p. 3, para 2.3

The Arbitrator held the suspension was illegal (not falling under GCC Clause 2.8) and awarded Rs. 5,44,04,340/- for the suspension period, plus litigation costs and interest

Source reference: p. 3, para 2.4; p. 8, para 8

The Petitioner challenged this award under Section 34 of the Arbitration and Conciliation Act, 1996

Source reference: p. 1, para 1
02

Issues

1. Whether the arbitral award was non-speaking or failed to provide adequate reasons as mandated under Section 31(3) regarding the bona fide nature of the suspension

Source reference: p. 3-4, para 3; p. 8, para 10

2. Whether the Arbitrator erred in awarding payments for the suspension period despite alleged demobilization of staff and lack of proof of actual salary payments

Source reference: p. 4, para 3.1; p. 11, para 15

3. Whether the findings of the Arbitrator regarding staff deployment and the illegality of the suspension were "plausible views" immune from interference under Section 34

Source reference: p. 11-12, para 16
03

Law Applied

The court primarily applied Section 31(3) of the Arbitration and Conciliation Act, 1996, which requires a reasoned award, noting that such reasons can be implied from a fair reading of the award and documents

Source reference: p. 8-9

It applied the limited scope of judicial interference under Section 34, emphasizing that the court does not sit in appeal over an arbitrator’s interpretation of a contract or the quantum of evidence

Source reference: p. 12

Furthermore, the court relied on the principle that if a contractual provision is capable of multiple interpretations, the arbitrator’s plausible view must prevail

Source reference: p. 12
04

Reasoning

The court rejected the Petitioner's argument that the award was non-speaking. It held that since the Petitioner had voluntarily revoked the suspension and withdrawn the SCN during writ proceedings, the issue of whether the suspension was bona fide had lost relevance and did not require detailed adjudication by the Arbitrator

Source reference: p. 8-9, para 9, 11

Regarding the award for the suspension period, the court found the Petitioner's claim of "demobilization" factually incorrect, citing Respondent’s letters expressing the need to hold staff

Source reference: p. 9-10, para 12

The court noted that the Respondent had submitted substantial collateral evidence—including attendance registers, hotel occupancy logs for residential offices, and vehicle rent agreements—to prove staff remained deployed at the site

Source reference: p. 10, para 14

Since the Petitioner did not dispute these documents but only challenged the lack of direct salary payment proofs, the court ruled that the Arbitrator’s reliance on this evidence to determine deployment was a "plausible view"

Source reference: p. 11, para 15-16

The court concluded that the determination of the quantum of evidence falls within the exclusive domain of the Arbitrator and cannot be set aside unless there is "no evidence at all"

Source reference: p. 11-12, para 15.1, 16
05

Holding

The Court dismissed the petition, upholding the arbitral award in its entirety.

It held that the Arbitrator’s findings were reasoned, based on available evidence, and represented a plausible interpretation of the facts and contract

Source reference: p. 12-13, para 16, 20

The Court affirmed that the interest granted was consistent with GCC Clause 6.4 and that the litigation costs were within the Arbitrator's discretion under Section 31A(3)

Source reference: p. 13, para 18-19

The award was found not to be vitiated by patent illegality, perversity, or conflict with public policy

Source reference: p. 13, para 20
Delhi High Court

Original Court PDF

National Highways And Infrastructure Development Corporation LimitedvsIntercontinental Consultants And Technocrats Private Limited In Joint Venture With Anandjiwala Infra Advisory Pvt. Ltd.

Delhi High Court · April 20, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment