01Facts
The Appellant (PCKL) is the nodal agency for power procurement in Karnataka.
In 1996, the State approved a barge-mounted power project originally for Euro AG, which was later transferred to Respondent No. 1 (HTPPL).
¶ 6-7HTPPL deposited ₹1 crore as "Guarantee Money" in 1998.
¶ 10Over two decades, the project underwent several Government-approved changes regarding capacity, fuel type, and location.
¶ 11-16On 11.04.2016, the State withdrew the project approval, citing that the changes caused the project to lose its "bid route" character and violated the Electricity Act, 2003.
¶ 18HTPPL initially sought arbitration before the Permanent Court of Arbitration (PCA), but the Karnataka Electricity Regulatory Commission (KERC) and subsequently the High Court and Supreme Court held that only KERC had jurisdiction under Section 86(1)(f) of the Electricity Act.
¶ 20-26HTPPL then filed a Writ Petition seeking refund of the deposit with 12% interest.
The learned Single Judge allowed the petition, treating the retention as "unjust enrichment" and a "continuing wrong" under the Limitation Act.
¶ 4PCKL appealed this order.
02Issues
i.Whether a writ petition under Article 226 is maintainable for a refund claim involving disputed questions of contractual fact and performance.
¶ 37-39ii.Whether the claim for refund of Earnest Money Deposit (EMD) is barred by the law of limitation or if it constitutes a "continuing cause of action."
¶ 42-45iii.Whether HTPPL has an efficacious alternative remedy before the KERC under Section 86(1)(f) of the Electricity Act, 2003.
¶ 3803Law Applied
The Court applied Article 226 of the Constitution of India regarding the discretionary jurisdiction of High Courts in contractual matters.
¶ 37It primary relied on Section 86(1)(f) of the Electricity Act, 2003, which mandates adjudication of disputes between generating companies and licensees by the State Commission.
¶ 28Regarding time-bars, the Court applied Article 113 of the Schedule to the Limitation Act, 1963 (the residuary period of three years).
¶ 43The Court also applied Section 14 of the Limitation Act, 1963, which allows for the exclusion of time spent bona fide in a forum lacking jurisdiction.
¶ 42, 49Provisions in the judgment · 4 · Linked ones open on LawLens
Limitation Act, 1963 Section 22Section 14
Electricity Act, 2003 Section 86
KARNATAKA HIGH COURT ACT, 1961 Section 4
04Reasoning
The Division Bench found that the dispute was fundamentally contractual, involving whether HTPPL performed its obligations or whether the State’s withdrawal was a breach.
¶ 36-37Such "disputed questions of fact" are generally not entertained under Article 226.
¶ 39The Court disagreed with the Single Judge’s view that the non-refund was a "continuing wrong"; rather, the right to sue accrued when the project was cancelled in 2016.
¶ 44-45However, the Bench noted that HTPPL acted bona fide in pursuing arbitration until the Supreme Court finally settled the jurisdictional issue in 2025; thus, that period (2018–2025) is eligible for exclusion under Section 14 of the Limitation Act.
¶ 49-50Crucially, the Court held that since the Supreme Court had already relegated the parties to the KERC/APTEL for all disputes, HTPPL possessed an efficacious alternative remedy which it had already begun to invoke.
¶ 38, 5205Holding
The Court allowed the appeal and set aside the Single Judge’s order.
¶ 54It held that the writ petition was not the appropriate remedy for resolving complex factual and contractual disputes regarding the forfeiture or refund of security deposits.
The Court clarified that HTPPL is at liberty to file a fresh petition before the KERC as per the liberty already granted by that commission on 16.12.2025.
¶ 53All rights and contentions regarding the merits of the refund and interest remain open for adjudication by the KERC.
¶ 54Original Court PDF
Power Company of Karnataka Limited v. M/s Hassan Thermal Power Private Limited & Anr. [Writ Appeal No. 1969 of 2025]
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
![Article 226 jurisdiction is not exercisable to adjudicate contractual disputes involving complex contested questions of fact.. Power Company of Karnataka Limited v. M/s Hassan Thermal Power Private Limited & Anr. [Writ Appeal No. 1969 of 2025]. Karnataka High Court. LawLens](/stories/thumbnails/article-226-jurisdiction-is-not-exercisable-to-adjudicate-contractual-disputes-involving-c-10836df0445a48e291a650b8c42936f0.webp)