Karnataka High Court

Article 226 jurisdiction is not exercisable to adjudicate contractual disputes involving complex contested questions of fact.

Power Company of Karnataka Limited v. M/s Hassan Thermal Power Private Limited & Anr. [Writ Appeal No. 1969 of 2025]

Karnataka High CourtJUDGMENT: no citation3 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Appellant (PCKL) is the nodal agency for power procurement in Karnataka.

Source reference: no citation

In 1996, the State approved a barge-mounted power project originally for Euro AG, which was later transferred to Respondent No. 1 (HTPPL).

Source reference: para. 6-7

HTPPL deposited ₹1 crore as "Guarantee Money" in 1998.

Source reference: para. 10

Over two decades, the project underwent several Government-approved changes regarding capacity, fuel type, and location.

Source reference: para. 11-16

On 11.04.2016, the State withdrew the project approval, citing that the changes caused the project to lose its "bid route" character and violated the Electricity Act, 2003.

Source reference: para. 18

HTPPL initially sought arbitration before the Permanent Court of Arbitration (PCA), but the Karnataka Electricity Regulatory Commission (KERC) and subsequently the High Court and Supreme Court held that only KERC had jurisdiction under Section 86(1)(f) of the Electricity Act.

Source reference: para. 20-26

HTPPL then filed a Writ Petition seeking refund of the deposit with 12% interest.

Source reference: no citation

The learned Single Judge allowed the petition, treating the retention as "unjust enrichment" and a "continuing wrong" under the Limitation Act.

Source reference: para. 4

PCKL appealed this order.

Source reference: no citation
02

Issues

Whether a writ petition under Article 226 is maintainable for a refund claim involving disputed questions of contractual fact and performance.

Source reference: para. 37-39

Whether the claim for refund of Earnest Money Deposit (EMD) is barred by the law of limitation or if it constitutes a "continuing cause of action."

Source reference: para. 42-45

Whether HTPPL has an efficacious alternative remedy before the KERC under Section 86(1)(f) of the Electricity Act, 2003.

Source reference: para. 38
03

Law Applied

The Court applied Article 226 of the Constitution of India regarding the discretionary jurisdiction of High Courts in contractual matters.

Source reference: para. 37

It primary relied on Section 86(1)(f) of the Electricity Act, 2003, which mandates adjudication of disputes between generating companies and licensees by the State Commission.

Source reference: para. 28

Regarding time-bars, the Court applied Article 113 of the Schedule to the Limitation Act, 1963 (the residuary period of three years).

Source reference: para. 43

The Court also applied Section 14 of the Limitation Act, 1963, which allows for the exclusion of time spent bona fide in a forum lacking jurisdiction.

Source reference: para. 42, 49
04

Reasoning

The Division Bench found that the dispute was fundamentally contractual, involving whether HTPPL performed its obligations or whether the State’s withdrawal was a breach.

Source reference: para. 36-37

Such "disputed questions of fact" are generally not entertained under Article 226.

Source reference: para. 39

The Court disagreed with the Single Judge’s view that the non-refund was a "continuing wrong"; rather, the right to sue accrued when the project was cancelled in 2016.

Source reference: para. 44-45

However, the Bench noted that HTPPL acted bona fide in pursuing arbitration until the Supreme Court finally settled the jurisdictional issue in 2025; thus, that period (2018–2025) is eligible for exclusion under Section 14 of the Limitation Act.

Source reference: para. 49-50

Crucially, the Court held that since the Supreme Court had already relegated the parties to the KERC/APTEL for all disputes, HTPPL possessed an efficacious alternative remedy which it had already begun to invoke.

Source reference: para. 38, 52
05

Holding

The Court allowed the appeal and set aside the Single Judge’s order.

It held that the writ petition was not the appropriate remedy for resolving complex factual and contractual disputes regarding the forfeiture or refund of security deposits.

Source reference: no citation

The Court clarified that HTPPL is at liberty to file a fresh petition before the KERC as per the liberty already granted by that commission on 16.12.2025.

Source reference: para. 53

All rights and contentions regarding the merits of the refund and interest remain open for adjudication by the KERC.

Source reference: para. 54
Karnataka High Court

Original Court PDF

Power Company of Karnataka Limited v. M/s Hassan Thermal Power Private Limited & Anr. [Writ Appeal No. 1969 of 2025]

Karnataka High Court · no citation

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment