01Facts
The complainant initiated civil contempt proceedings alleging wilful disobedience of the High Court’s order dated 25 April 2025 in R.P. No. 109/2025.
p. 2That review petition had been dismissed after the Supreme Court had also dismissed the special leave petition challenging the earlier proceedings concerning unauthorised construction.
pp. 3–5In the contempt proceedings, the Assistant Engineer filed an affidavit stating that the unauthorised fourth floor had been demolished, but construction within the setback area remained because its removal was said to risk structural instability and public safety.
pp. 5–8The affidavit also stated that a setback deviation of 11.70% had been recorded.
pp. 5–802Issues
i.Whether the accused had wilfully disobeyed the High Court’s order dated 25 April 2025.
p. 2ii.Whether the remaining setback deviation required further action by the authorities, including consideration under Section 249 of the Greater Bengaluru Governance Act, 2024.
p. 703Law Applied
The petition was brought under Sections 11 and 12 of the Contempt of Courts Act, 1971, read with Article 215 of the Constitution of India.
p. 2The Court also referred to Section 249(1)(a) of the Greater Bengaluru Governance Act, 2024, which the accused’s counsel relied on in submitting that certain deviations in residential buildings may be regularised; the Court left the application of that provision to the competent authorities.
p. 7Provisions in the judgment · 2 · Linked ones open on LawLens
Contempt of Courts Act, 1971 Section 11Section 12
04Reasoning
The Court considered the compliance affidavit, which reported demolition of the unauthorised fourth floor and attributed the remaining setback violation to asserted structural and safety risks.
pp. 5–7It also noted the reported 11.70% deviation and counsel’s submission concerning possible regularisation under Section 249.
p. 7Rather than determine whether the remaining construction was regularisable or make an express finding on wilful disobedience, the Court left the matter for the authorities to consider and take appropriate steps under the Act.
p. 705Holding
The Court observed that the authorities under the Greater Bengaluru Governance Act, 2024, should consider and take appropriate steps under Section 249.
p. 8It made that observation and consigned the contempt petition; it did not expressly find the accused guilty of contempt or direct that the setback deviation be regularised.
p. 8Original Court PDF