Facts
The petitioner, M/s Pooja Construction, was awarded a Public Works Department contract in 2012 for construction of the Polytechnic College at Geedam, including the administrative and college buildings.
Source reference: no citationAn agreement was executed on 17 April 2012 and the work order was issued on 24 May 2012. The petitioner completed the work within the stipulated period, and a completion certificate was issued on 7 March 2015.
Source reference: para. 5The petitioner claimed release of the balance 50% payment, amounting to ₹13,55,626, along with interest, in respect of the completed contractual work.
Source reference: para. 6Since the two writ petitions involved an identical issue, the High Court heard and decided them together, treating W.P.(C) No. 70 of 2023 as the lead matter.
Source reference: paras. 1–2During hearing, the petitioner limited its prayer to permission to submit a fresh representation before the competent authorities, with a direction for its consideration and decision.
Source reference: para. 7The State expressed no objection to this limited relief.
Source reference: para. 8Issues
Whether the petitioner should be permitted to submit a fresh representation seeking release of the alleged balance contractual payment and other consequential reliefs.
Source reference: paras. 6–7Whether the respondent authorities should be directed to consider and decide such representation within a prescribed period and release any undisputed amount, subject to verification.
Source reference: para. 10Law Applied
The Court exercised its jurisdiction under Article 226 of the Constitution of India.
Source reference: para. 4The applicable principle was that, where the petitioner seeks consideration of a representation concerning payment under a completed government contract and the State has no objection to such limited relief, the Court may direct the competent authorities to consider and decide the representation in accordance with the applicable rules, law and regulations, without adjudicating the disputed contractual claim on merits.
Source reference: paras. 7–10Reasoning
The Court noted that the petitioner had completed the contracted work and possessed a completion certificate, but was seeking a direction for payment of the alleged balance amount and interest.
Source reference: paras. 5–6Since the petitioner did not press for an immediate adjudication of its monetary claim and instead sought liberty to make a fresh representation, and since the State raised no objection, the Court considered it appropriate to adopt the limited procedural course requested.
Source reference: paras. 7–10The authorities were therefore required to examine the representation, relevant documents and the petitioner’s grounds in accordance with law.
Source reference: paras. 7–10Any amount found to be undisputed could be released, but only after verification.
Source reference: para. 10Holding
The writ petitions were disposed of without determining the petitioner’s entitlement to the claimed balance payment or interest.
The petitioner was granted liberty to submit a fresh representation, along with relevant documents and all grounds raised in the writ petitions, before respondent Nos. 1 and 2 within 15 days from receipt of the order.
Source reference: para. 10The concerned respondents were directed to consider and decide the representation in accordance with the applicable law within 60 days from its receipt and, subject to verification, disburse any amount found to be undisputed.
Source reference: para. 10All pending interlocutory applications were also disposed of.
Source reference: paras. 11–12Original Court PDF
M/S POOJA CONSTRUCTIONvsSTATE OF CHHATTISGARH
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
