Chhattisgarh High Court
Construction LawAdministrative and Public Law

Authorities must decide the contractor’s representation for unpaid dues within the prescribed time.

M/S POOJA CONSTRUCTION vs STATE OF CHHATTISGARH

Chhattisgarh High CourtJUDGMENT: September 01, 20262 MIN READSOURCE JUDGMENT
Authorities must decide the contractor’s representation for unpaid dues within the prescribed time.. M/S POOJA CONSTRUCTION vs STATE OF CHHATTISGARH. Chhattisgarh High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The petitioner, M/s Pooja Construction, was awarded a Public Works Department contract in 2012 for construction of the Polytechnic College at Geedam, including the administrative and college buildings.

Source reference: no citation

An agreement was executed on 17 April 2012 and the work order was issued on 24 May 2012. The petitioner completed the work within the stipulated period, and a completion certificate was issued on 7 March 2015.

Source reference: para. 5

The petitioner claimed release of the balance 50% payment, amounting to ₹13,55,626, along with interest, in respect of the completed contractual work.

Source reference: para. 6

Since the two writ petitions involved an identical issue, the High Court heard and decided them together, treating W.P.(C) No. 70 of 2023 as the lead matter.

Source reference: paras. 1–2

During hearing, the petitioner limited its prayer to permission to submit a fresh representation before the competent authorities, with a direction for its consideration and decision.

Source reference: para. 7

The State expressed no objection to this limited relief.

Source reference: para. 8
02

Issues

Whether the petitioner should be permitted to submit a fresh representation seeking release of the alleged balance contractual payment and other consequential reliefs.

Source reference: paras. 6–7

Whether the respondent authorities should be directed to consider and decide such representation within a prescribed period and release any undisputed amount, subject to verification.

Source reference: para. 10
03

Law Applied

The Court exercised its jurisdiction under Article 226 of the Constitution of India.

Source reference: para. 4

The applicable principle was that, where the petitioner seeks consideration of a representation concerning payment under a completed government contract and the State has no objection to such limited relief, the Court may direct the competent authorities to consider and decide the representation in accordance with the applicable rules, law and regulations, without adjudicating the disputed contractual claim on merits.

Source reference: paras. 7–10
04

Reasoning

The Court noted that the petitioner had completed the contracted work and possessed a completion certificate, but was seeking a direction for payment of the alleged balance amount and interest.

Source reference: paras. 5–6

Since the petitioner did not press for an immediate adjudication of its monetary claim and instead sought liberty to make a fresh representation, and since the State raised no objection, the Court considered it appropriate to adopt the limited procedural course requested.

Source reference: paras. 7–10

The authorities were therefore required to examine the representation, relevant documents and the petitioner’s grounds in accordance with law.

Source reference: paras. 7–10

Any amount found to be undisputed could be released, but only after verification.

Source reference: para. 10
05

Holding

The writ petitions were disposed of without determining the petitioner’s entitlement to the claimed balance payment or interest.

The petitioner was granted liberty to submit a fresh representation, along with relevant documents and all grounds raised in the writ petitions, before respondent Nos. 1 and 2 within 15 days from receipt of the order.

Source reference: para. 10

The concerned respondents were directed to consider and decide the representation in accordance with the applicable law within 60 days from its receipt and, subject to verification, disburse any amount found to be undisputed.

Source reference: para. 10

All pending interlocutory applications were also disposed of.

Source reference: paras. 11–12
Chhattisgarh High Court

Original Court PDF

M/S POOJA CONSTRUCTIONvsSTATE OF CHHATTISGARH

Chhattisgarh High Court · September 01, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment