Facts
The petitioners claimed ownership or joint ownership of lands situated at Villages Kabaripali and Kekrabhat, Tehsil Dabhra, District Sakti, Chhattisgarh. They alleged that portions of their lands had come, or were likely to come, under submergence due to construction of the Ghatoi Dam by the Water Resources Department, affecting their ability to cultivate the lands.
Source reference: para. 3The petitioners submitted representations to the Sub-Divisional Officer (Revenue)-cum-Land Acquisition Officer seeking spot inspection, demarcation, and compensation, but alleged that no inspection or decision had been undertaken.
Source reference: para. 4They also asserted that similarly situated landowners affected by the same project had received compensation after inspection.
Source reference: paras. 4–5Relying on Article 300-A of the Constitution, Sections 80 and 30(3) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 (“2013 Act”), and certain earlier judicial orders, the petitioners sought inspection, acquisition, compensation, interest, and additional compensation.
Source reference: paras. 2, 5The State submitted that the petition could be disposed of with appropriate directions, but contended that the petitioners should first approach the competent authorities with a proper application.
Source reference: para. 6Issues
1. Whether the respondent authorities should be directed to conduct spot inspection and demarcation to determine whether the petitioners’ lands had been submerged or affected by the Ghatoi Dam and, if so, initiate lawful acquisition and compensation proceedings.
Source reference: paras. 2–4, 7–82. Whether the petitioners were entitled to interest under Section 80 and additional compensation under Section 30(3) of the 2013 Act from the alleged date of dispossession.
Source reference: paras. 2, 53. Whether the Court could grant the substantive compensation-related reliefs without first adjudicating the factual question of submergence and completing the statutory determination by the competent authorities.
Source reference: paras. 7–9Law Applied
Article 300-A of the Constitution protects the right to property and prohibits deprivation of property except by authority of law.
Source reference: para. 5Where land is acquired or affected for a public project, compensation must be determined and paid in accordance with the applicable statutory acquisition framework, including the 2013 Act.
Source reference: paras. 2, 5Section 80 of the 2013 Act concerns interest payable on compensation in cases of delayed payment, while Section 30(3) concerns additional compensation as provided by the Act.
Source reference: para. 2The Court also took note of the petitioners’ reliance on Gayabai Digambar Puri (Died) through LRs. v. The Executive Engineer & Others and an earlier order in W.P.(C) No. 1792 of 2026, but did not finally adjudicate the petitioners’ entitlement under those authorities.
Source reference: para. 5Factual determination of submergence, demarcation, and the consequential acquisition and compensation liability was left to the competent authorities in accordance with law.
Source reference: paras. 7–9Reasoning
The Court did not decide whether the petitioners’ lands had in fact been submerged or whether they were entitled to interest or additional compensation.
Source reference: paras. 6–7Since the petitioners’ claim required factual verification through spot inspection and demarcation, and the State accepted that appropriate directions could be issued, the Court considered it appropriate to require the petitioners to submit a fresh application with supporting documents.
Source reference: paras. 6–7The authorities were then directed to conduct inspection and demarcation within the prescribed period.
Source reference: para. 8If the inspection established that the lands were submerged or fell within the affected area of the Ghatoi Dam, the authorities were required to initiate appropriate compensation proceedings under the applicable law.
Source reference: para. 8The Court thereby preserved the petitioners’ statutory claims while avoiding a premature determination of disputed factual and compensation issues.
Source reference: no citationHolding
Without expressing any opinion on the merits, the Court disposed of the petition and granted the petitioners liberty to file a fresh application, along with all necessary documents and a copy of the order, within 15 days.
Upon such filing, the respondent authorities were directed to conduct spot inspection and demarcation within 45 days.
Source reference: para. 8If the lands were found to be submerged or situated within the Dam’s affected area, the authorities were directed to initiate appropriate proceedings for payment of compensation.
Source reference: para. 8The acquisition and compensation proceedings were to be concluded within a further 90 days from the date of demarcation.
Source reference: paras. 8–9No final determination was made regarding entitlement to interest under Section 80 or additional compensation under Section 30(3) of the 2013 Act.
Source reference: no citationActs & Sections Cited
2 provisions across 1 statute referred to in this judgment. Each provision opens on LawLens.
Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 20132
Original Court PDF
MAHIP KUMARvsSTATE OF CHHATTISGARH
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
