01Facts
The petitioner, the Executive Engineer of KNNL (BNT Division), was the beneficiary of a land acquisition.
The petitioner challenged an order dated 31.10.2017 passed by the Special Land Acquisition Officer (Respondent No. 1) under Section 28-A of the Land Acquisition Act, 1894.
¶ 3 · prayer (a)The petitioner sought (a) certiorari quashing that order and (b) mandamus directing the SLAO not to award interest under Section 34 of the Act.
prayer (a)–(b)The petitioner's principal ground was that the Land Acquisition Officer passed the award belatedly, and the beneficiary therefore cannot be saddled with liability to pay interest for that delay.
¶ 3Respondent Nos. 4–27 are the landowners/claimants, represented separately.
¶ 2The Court noted that two coordinate bench decisions had already considered a similar issue and dismissed the writ petitions: Karnataka Road Development Corporation Ltd. v. Smt. Putalabai & Ors., WP No. 200652/2023 (dated 05.06.2024), and The Executive Engineer v. The SLAO & Ors., WP No. 202440/2023 (dated 03.03.2026).
¶ 3 and fn. 1–202Issues
i.1. Whether the beneficiary of an acquisition can be relieved from liability to pay interest under Section 34 of the Land Acquisition Act, 1894, on the ground that the Land Acquisition Officer passed the award belatedly.
¶ 3ii.2. Whether the present writ petition, raising a question already decided by coordinate benches of the same Court, warrants a different outcome.
¶ 3–403Law Applied
The Court relied on the Land Acquisition Act, 1894, specifically Section 28-A (re-determination of award) and Section 34 (payment of interest on enhanced compensation), although the order does not reproduce or interpret their text.
¶ 3 · prayer (a)–(b)The Court principally applied the doctrine of judicial discipline and consistency, following the coordinate bench rulings in Karnataka Road Development Corporation Ltd. v. Smt. Putalabai (WP No. 200652/2023, dated 05.06.2024) and The Executive Engineer v. SLAO (WP No. 202440/2023, dated 03.03.2026), which held that the same issue (liability for interest where the award was delayed) does not relieve the beneficiary of interest liability and dismissed the writs.
¶ 3 and fn. 1–2The reasoning of these precedents is not set out in the present order.
Provisions in the judgment · 2
Land Acquisition Act, 1897 Section 34
Land Acquisition Act, 1894 Section 28
04Reasoning
The petitioner's sole contention was that delay by the Land Acquisition Officer in passing the award should not expose the beneficiary to interest liability.
¶ 3The Court observed that a coordinate bench had already examined this identical question in two earlier writ petitions and had dismissed them.
¶ 3Applying that reasoning to the present case, the Court held that the petitioner's challenge to the 31.10.2017 order and the mandamus sought against the imposition of interest raised nothing distinct, and dismissed the petition.
¶ 4The order does not independently analyze the statutory scheme or the facts of delay; it proceeds wholly by adopting the reasoning of the earlier decisions.
¶ 4The petition's prayers refer to Section 34, while para. 3 describes the impugned award as passed under Section 28-A; the order does not reconcile this discrepancy.
¶ 3 · prayer (a)–(b)05Holding
The Court answered the issues against the petitioner: the beneficiary cannot escape interest liability under Section 34 merely because the award was passed belatedly, following the coordinate bench rulings.
¶ 3–4The writ petition is dismissed in its entirety, and the SLAO's order dated 31.10.2017 is left intact, including the direction on interest.
¶ 4 · prayer (a)–(b)Original Court PDF