In brief

The question

Whether the petitioner, as a subsequent purchaser of land notified for acquisition, could challenge the acquisition notifications and obtain a declaration that the acquisition had lapsed under Section 24(2) of the 2013 Act.

The court held

The Court rejected the challenge to the acquisition notifications and the request for a declaration of lapse under Section 24(2).

It also directed

It permitted the petitioner to apply to the BDA under Section 38D within one month of receiving the order, with supporting documents.

The BDA was directed to inspect the property and consider the request in accordance with Section 38D, including the relevant questions concerning the construction and the petitioner’s eligibility; the order contemplated a decision within three months thereafter.

Until then, the respondents were directed not to take precipitative action against the construction, if any, put up by the petitioner or his vendor.

01Facts

The petitioner purchased the schedule property in Sy. No. 75, Kadugondanahalli, in 2014, through successive conveyances.

pp. 3–7

The land had been notified for acquisition by the Bangalore Development Authority (BDA) in 1978, with a final notification issued in 1985.

pp. 3–7

The petitioner claimed that he remained in possession, that compensation had not been paid, and that the acquisition had lapsed under Section 24(2) of the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.

pp. 3–7

The BDA maintained that an award had been passed and possession taken.

pp. 3–7

The petitioner sought a declaration that the acquisition had lapsed; the matter came before the High Court under Articles 226 and 227 of the Constitution.

pp. 3–7

02Issues

i.Whether the petitioner, as a subsequent purchaser of land notified for acquisition, could challenge the acquisition notifications and obtain a declaration that the acquisition had lapsed under Section 24(2) of the 2013 Act.

pp. 6–8

ii.Whether the petitioner was entitled to relief concerning his claimed possession and construction on the acquired land, including consideration under Section 38D of the Bangalore Development Authority Act, 1976.

pp. 8–10

03Law Applied

The Court referred to Section 24(2) of the 2013 Act in considering the claim that the acquisition had lapsed for non-payment of compensation and failure to take possession.

pp. 3, 6–8

It relied on Shivkumar v. Union of India, (2019) 10 SCC 229, for the principle that a purchaser who acquires land after it has been notified for acquisition cannot challenge the acquisition, as the purchaser’s rights are subordinate to the State’s interest.

p. 8

It also relied on Indore Development Authority v. Manoharlal, (2020) 8 SCC 129, for the proposition that a person claiming possession of land that has vested following acquisition may be treated as an unauthorised occupant and summarily evicted.

p. 8

The Court directed the petitioner to seek consideration under Section 38D of the BDA Act, subject to establishing the relevant facts, including possession from 2008 and the existence and location of the construction.

pp. 9–10

Provisions in the judgment · 1 · Linked ones open on LawLens

Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 Section 24

04Reasoning

The petitioner acquired the property in 2014, long after the 1978 preliminary notification and 1985 final notification.

pp. 8–10

Applying Shivkumar, the Court held that his status as a subsequent purchaser prevented him from assailing the acquisition.

pp. 8–10

His claim that a structure existed on the property and that he remained in possession did not undermine the acquisition notifications.

pp. 8–10

In light of Indore Development Authority, claimed possession of vested acquired land did not entitle him to the declaration sought.

pp. 8–10

The Court nevertheless allowed him to apply under Section 38D, leaving the BDA to inspect the property and determine whether the construction was within Sy. No. 75, whether it existed before 2008, and whether the petitioner qualified for the statutory benefit.

pp. 8–10

05Holding

The Court rejected the challenge to the acquisition notifications and the request for a declaration of lapse under Section 24(2).

p. 9

It permitted the petitioner to apply to the BDA under Section 38D within one month of receiving the order, with supporting documents.

pp. 9–10

The BDA was directed to inspect the property and consider the request in accordance with Section 38D, including the relevant questions concerning the construction and the petitioner’s eligibility; the order contemplated a decision within three months thereafter.

pp. 9–10

Until then, the respondents were directed not to take precipitative action against the construction, if any, put up by the petitioner or his vendor.

p. 10
Karnataka High Court

Original Court PDF

MR. FAYAZ AHMEDvsTHE STATE OF KARNATAKA

Karnataka High Court · September 28, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment