Bengaluru HC Quashes BBMP Building Order After No Effective Hearing, Orders Fresh Decision on Claim of No Construction in 30 Years

MR. S. CHINNAPPA RAJU,v.THE ASST.EXECUTIVE ENGINEER,

Bengaluru HC Quashes BBMP Building Order After No Effective Hearing, Orders Fresh Decision on Claim of No Construction in 30 Years. MR. S. CHINNAPPA RAJU, vs THE ASST.EXECUTIVE ENGINEER,. Karnataka High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the confirmation order could stand when the petitioner was allegedly not afforded an effective personal hearing as contemplated by the proviso to Section 243(3)(d) of the GBG Act.

The court held

The petition was allowed in part.

It also directed

The confirmation order dated 10 July 2026 was quashed, and the proceedings were restored for reconsideration.

The second respondent was directed to provide the petitioner a reasonable personal hearing under the proviso to Section 243(3)(d), consider his claim that no construction had been undertaken in the preceding three decades, and pass a reasoned order.

The petitioner was directed to file a certified copy of the order with the second respondent within one week of receiving it.

01Facts

The petitioner asserted ownership of property No. 9, Sy. No. 38, Site No. 3, 13th A Cross, Manorayanapalya, Bengaluru.

p. 3

He challenged the second respondent’s confirmation order dated 10 July 2026, made under Section 243 of the Greater Bengaluru Governance Act, 2024 (“GBG Act”), confirming a provisional order dated 13 March 2026.

pp. 3, 5–6

The petitioner alleged that, although informed a provisional hearing would take place, he was told on appearing that it had been postponed; the confirmation order was later passed without further notice or hearing.

pp. 3–4

He also maintained that he had purchased the property under a sale deed dated 16 June 2003 and that the construction was approximately 36 years old, with no recent construction undertaken.

pp. 3–4

Despite the alternative remedy under Section 250 of the GBG Act, he sought relief under Articles 226 and 227 of the Constitution.

p. 3

02Issues

i.1. Whether the confirmation order could stand when the petitioner was allegedly not afforded an effective personal hearing as contemplated by the proviso to Section 243(3)(d) of the GBG Act.

pp. 3–5

ii.2. Whether the Court should intervene notwithstanding the alternative remedy under Section 250 of the GBG Act, in view of the alleged failure to provide that hearing.

p. 3, 5

03Law Applied

The proviso to Section 243(3)(d) of the GBG Act requires an effective personal hearing before the relevant proceedings are concluded.

p. 3, 6

Section 250 provides an alternative remedy, but the Court considered the petitioner’s allegation of non-compliance with the statutory hearing requirement when deciding whether to intervene.

p. 3

No precedent was cited.

Provisions in the judgment · 2

Greater Bengaluru Governance Act, 2024 Section 243Section 250

04Reasoning

The Court accepted that if the proceedings had been completed without an opportunity to be heard, despite the petitioner having been informed that a hearing would take place, there would be a failure to comply with the statutory requirement of an effective personal hearing.

p. 5

That procedural concern persuaded the Court to quash the confirmation order and restore the matter for reconsideration.

pp. 5–6

The Court further directed that any confirmation of the provisional order address the petitioner’s specific case that no construction had been undertaken in recent decades.

pp. 5–6

05Holding

The petition was allowed in part.

p. 6

The confirmation order dated 10 July 2026 was quashed, and the proceedings were restored for reconsideration.

p. 6

The second respondent was directed to provide the petitioner a reasonable personal hearing under the proviso to Section 243(3)(d), consider his claim that no construction had been undertaken in the preceding three decades, and pass a reasoned order.

pp. 6–7

The petitioner was directed to file a certified copy of the order with the second respondent within one week of receiving it.

pp. 6–7
Karnataka High Court

Original Court PDF

MR. S. CHINNAPPA RAJU,vsTHE ASST.EXECUTIVE ENGINEER,

Karnataka High Court · September 28, 2026