Madhya Pradesh High CourtAdministrative and Public LawContract Law

Bidder who participates with full knowledge of tender conditions cannot later challenge them.

M/S Ekta Parivahan Sahkari Samiti Maryadit Tikamgarhv.The State Of Madhya Pradesh

Bidder who participates with full knowledge of tender conditions cannot later challenge them.. M/S Ekta Parivahan Sahkari Samiti Maryadit Tikamgarh vs The State Of Madhya Pradesh. Madhya Pradesh High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether a bidder who participated in a tender with knowledge of its terms can challenge those terms after being declared the successful (L-1) bidder.

The court held

A bidder who participates with knowledge of tender conditions cannot challenge them after being declared successful, and forfeiture of EMD and debarment for refusing to execute the agreement were validly imposed under the tender document after due notice.

It also directed

The petition was found to be without merit and was dismissed; no relief was granted to the petitioner, and the orders dated 22.01.2026 and 02.04.2026 stand.

01Facts

The petitioner, a cooperative society, participated in a tender of the respondent Corporation. Due to negligence and improper study of the tender conditions by the society's Manager, it quoted low rates.

¶ 2

On 10.10.2025, the petitioner submitted a representation seeking cancellation and re-tender under Clauses 25/26 of the tender conditions.

¶ 2

The head office approved the quoted rates on 09.01.2026, and the petitioner was asked to execute the agreement by memorandum of the same date.

¶ 2

By letter dated 13.01.2026, the petitioner expressed unwillingness to execute the agreement because it could not match 100% of the quoted rates.

¶ 2

On 22.01.2026, the respondents forfeited the petitioner's Earnest Money Deposit (EMD) and debarred it from tenders for two forthcoming tender years.

¶ 2

A show cause notice dated 24.03.2026 had asked why debarment should not follow.

¶ 6

The impugned order dated 02.04.2026 by respondent No. 4 forfeited the EMD and debarred the petitioner from the Corporation's tenders for 2025–2027 and forthcoming tenders up to 2027.

¶ 1

The petitioner contended that Clause 19 of the tender conditions, which provides for forfeiture and debarment, cannot override Article 14 of the Constitution.

¶ 2

02Issues

i.1. Whether a bidder who participated in a tender with knowledge of its terms can challenge those terms after being declared the successful (L-1) bidder.

¶ 3 · ¶ 6

ii.2. Whether the forfeiture of EMD and debarment of the petitioner under Clause 19 of the tender conditions, which the petitioner alleges is violative of Article 14, is sustainable.

¶ 2 · ¶ 6 · ¶ 11

03Law Applied

Courts must exercise restraint in contractual and commercial matters, interfering only on clear arbitrariness, mala fides, bias, or irrationality, and must give "fair play in the joints" to the State (Tata Motors Ltd. v. BEST, 2023 SCC OnLine SC 671).

¶ 4

The award of contracts is a commercial transaction; the State may fix its own tender terms, which are not open to judicial scrutiny, but it must adhere to its own norms and act fairly (Air India Ltd. v. Cochin International Airport Ltd., (2000) 2 SCC 617).

¶ 5

Bids cannot be rewritten, and judicial review is confined to arbitrariness or irrationality (Siemens Public Communication Networks Pvt. Ltd. v. Union of India, (2008) 16 SCC 215).

¶ 7

A party that participates in a tender with full knowledge of its conditions cannot later challenge them (National High Speed Rail Corporation v. Montecarlo Ltd., (2022) 6 SCC 401).

¶ 8

Judicial review does not allow the Court to act as a "superboard" or substitute its judgment for that of the administrator, and the State may reject any tender (Tata Cellular v. Union of India, (1994) 6 SCC 651).

¶ 9

Courts defer to the employer's interpretation of tender conditions unless it is mala fide or perverse (Shrishti Infrastructure Development Corporation Ltd. v. State of M.P., 2021 (4) M.P.L.J. 428).

¶ 10

Provisions in the judgment · 1

ITB (alias, unresolved) Section 1

04Reasoning

The petitioner, having participated with full awareness of the tender conditions and having been declared L-1, could not challenge those conditions.

¶ 3

The Court treated the petitioner's own quotation as its responsibility, stating that a representation about the Manager's negligence was no excuse once the petitioner became the successful bidder.

¶ 6

Because the petitioner expressed unwillingness to execute the agreement, the authorities were entitled under the tender document to forfeit the EMD and debar it.

¶ 6

The Court found that a show cause notice had been issued, which gave the petitioner notice of the proposed debarment.

¶ 6

The Court concluded that the respondents followed all required parameters before passing the debarment order and that no mala fides or arbitrariness had been established warranting interference under the limited scope of judicial review.

¶ 4, 9, 11

The judgment does not quote or analyse the text of Clause 19 or separately examine the Article 14 challenge to it beyond these general principles.

¶ 2 · ¶ 11

05Holding

A bidder who participates with knowledge of tender conditions cannot challenge them after being declared successful, and forfeiture of EMD and debarment for refusing to execute the agreement were validly imposed under the tender document after due notice.

¶ 3, 6, 11

The petition was found to be without merit and was dismissed; no relief was granted to the petitioner, and the orders dated 22.01.2026 and 02.04.2026 stand.

¶ 11, 12
Madhya Pradesh High Court

Original Court PDF

M/S Ekta Parivahan Sahkari Samiti Maryadit TikamgarhvsThe State Of Madhya Pradesh

Madhya Pradesh High Court · November 16, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment