01Facts
The respondent company was found technically eligible in the original tender and was declared L-1 after the financial bids were opened.
Following a complaint by an MLA, the Tender Committee disqualified it on the ground that the stamp paper for its affidavit had not been purchased in the deponent’s name, and cancelled the tender.
p. 2 · ¶ 2During the writ proceedings, a fresh tender was issued and the second respondent was awarded the work.
pp. 2–3 · ¶ 3, 9, 14The writ petitioner was permitted to participate in the fresh tender, subject to the outcome of its writ petition, but did not do so.
pp. 2–3 · ¶ 3, 9, 14In a later order, the Single Judge found the original exclusion unsustainable.
pp. 4–5, 7–8 · ¶ 7, 15Given that approximately 80% of the work under the subsequent tender had been completed, the Single Judge did not disturb that work but directed the State to pay the writ petitioner Rs. 5,00,000.
pp. 4–5, 7–8 · ¶ 7, 15The State appealed against that monetary direction.
02Issues
i.Whether the petitioner’s exclusion from the original tender was arbitrary when the NIT contained no requirement that the affidavit’s stamp paper be purchased in the deponent’s name.
p. 7 · ¶ 13ii.Whether the direction to pay Rs. 5,00,000 could be sustained despite the absence of a concluded contract, a work order, or evidence of actual pecuniary loss.
pp. 5–6 · ¶ 8–11 · p. 8 · ¶ 15–1703Law Applied
The Court applied the principle that a tendering authority must assess a bid against the conditions actually stated in the NIT; a bidder cannot be disqualified for failing to meet an unstated requirement.
p. 7 · ¶ 13In exercising writ jurisdiction, the Court may mould relief to account both for an established arbitrary act and for subsequent developments affecting the public interest, including substantial progress of public work.
pp. 7–8 · ¶ 15–17The Court distinguished the Rs. 5,00,000 award from contractual damages, describing it as compensation for the arbitrary exclusion rather than relief under a concluded contract.
p. 8 · ¶ 17The State relied on Rabindra Nath Ghosal v. University of Calcutta, Sube Singh v. State of Haryana, W.B. SEB v. Dilip Kumar Ray and Municipal Corporation of Delhi v. Uphaar Tragedy Victims Association; the Court held those decisions inapplicable to the facts, without setting out or applying their principles in detail.
p. 6, 8 · ¶ 11, 1604Reasoning
The petitioner had been found eligible and declared L-1, while the State conceded that the NIT did not require the affidavit’s stamp paper to be purchased in the deponent’s name.
p. 7 · ¶ 13The Court therefore upheld the finding that the petitioner’s disqualification on that ground was arbitrary.
p. 7 · ¶ 13The subsequent tender did not cure the original illegality, particularly because the petitioner’s challenge was already pending and its participation in the fresh tender had been made subject to the writ petition’s outcome.
pp. 7–8 · ¶ 14However, because the work had substantially progressed, restoring it to the petitioner would have disrupted an ongoing public project.
pp. 7–8 · ¶ 15–17The Court held that the Single Judge had properly balanced those circumstances by leaving the work undisturbed while awarding compensation for the arbitrary exclusion; it did not treat the award as contractual damages.
pp. 7–8 · ¶ 15–1705Holding
The Court answered that the petitioner’s exclusion from the original tender was arbitrary and upheld the Single Judge’s exercise of discretion in moulding relief.
p. 8 · ¶ 17–19It found no ground to interfere with the direction requiring the State to pay Rs. 5,00,000, and dismissed the appeal as devoid of merit.
p. 8 · ¶ 17–19Original Court PDF
The State Of Bihar and OrsvsKamakshi Minakshi Construction Private Limited and Anr
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
