Facts
The appellants were successful bidders for stone-mining blocks at Rajouli, Nawadah, and entered into lease arrangements after obtaining mining-plan approval and environmental clearance.
Source reference: para. 3–11They did not pay the second instalments by the dates demanded; the Department later sought the instalments and interest.
Source reference: para. 3–11In earlier writ proceedings, the appellants paid the principal and two months’ interest, while being given liberty to contest the remaining interest. After the competent authority rejected their representations and issued further demands, the appellants’ subsequent writ petitions were dismissed. They appealed, challenging the demand for interest beyond two months under Rule 52(5) of the Bihar Minor Mineral Concession Rules, 1972.
Source reference: para. 3–11Issues
Whether Rule 52(5) authorises the Department to charge interest beyond two months for default in payment of an instalment
Source reference: para. 12, 21–24Whether the earlier orders directing payment of two months’ interest and permitting representations on the balance finally determined the appellants’ liability for interest beyond that period
Source reference: para. 30–33Law Applied
Rule 52(5) of the Bihar Minor Mineral Concession Rules, 1972 provides for simple interest at 24 per cent up to two months after an instalment default and states that thereafter action for cancellation shall be taken.
Source reference: para. 22The Court applied the principle that a statutory authority must act within the powers and limits prescribed by statute; where legislation prescribes how an act is to be done, the authority must follow that prescription, as reiterated in State of Jharkhand v. Ambay Cements.
Source reference: para. 26It also relied on Tata Chemicals Ltd. v. Commissioner of Customs (Preventive), Jamnagar for the principle that statutory power must be exercised according to law and cannot be enlarged by estoppel, and Shridhar C. Shetty (Dead) through Legal Representatives v. Additional Collector and Competent Authority for the principle that a statutory authority cannot act beyond its statutory jurisdiction.
Source reference: para. 27–28Reasoning
The Court distinguished the appellants’ admitted default from the separate question of the monetary consequences that Rule 52(5) permits. Reading the two parts of the Rule together, it held that the two-month limit on interest has operative effect and that the prescribed consequence thereafter is action for cancellation—not indefinite continuation of interest.
Source reference: para. 21–25, 37–39The agreements and the obligation to pay the instalments could not enlarge that statutory consequence.
Source reference: para. 21–25, 37–39The earlier orders had not finally decided that interest beyond two months was recoverable; they preserved the appellants’ ability to contest the remaining interest, so the statutory question remained open.
Source reference: para. 30–33The Court did not decide the separate arguments concerning commencement of the lease, Rule 25(2), permissions, or force majeure.
Source reference: para. 34–36Holding
The Court held that interest under Rule 52(5) could not continue beyond two months solely because the instalment remained unpaid.
It allowed all three appeals, set aside the Single Judge’s judgments, and quashed the orders dated 14 September 2023 and consequential demands insofar as they sought interest beyond that period.
Source reference: para. 41–44The principal instalment liabilities and amounts already deposited, including two months’ interest, remained undisturbed; there was no order as to costs.
Source reference: para. 45–46Acts & Sections Cited
2 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.
Transfer of Property Act, 18821
Maharashtra Land Revenue Code, 19661
Original Court PDF
M/s Mahadev Enclave Pvt. Ltd.,vsThe State of Bihar
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
