01Facts
The petitioner entered into a Contract Agreement on October 4, 2023, with the respondent for the maintenance of an optical fiber cable network for a three-year term
pp. 1-2Due to alleged frequent cable damages in late 2024, the respondent terminated the contract and blacklisted the petitioner for three years via a Letter dated November 24, 2025
p. 2The respondent justified the lack of a prior show-cause notice by arguing that blacklisting was part of the termination clause (Clause 29) under the Special Conditions of Contract
pp. 2-3The petitioner moved the High Court under Section 9 of the Arbitration and Conciliation Act, 1996, seeking interim protection against the blacklisting order on the grounds of violation of natural justice
pp. 1-202Issues
i.Whether the respondent could validly blacklist the petitioner without issuing a specific prior show-cause notice, even if such power is stipulated within a contract termination clause
p. 3 / para. 8ii.Whether the petitioner is entitled to interim protection (stay) against the blacklisting order pending arbitration
p. 6 / para. 1403Law Applied
Principles of Natural Justice, specifically the doctrine of audi alteram partem, holding that a show-cause notice is a sine qua non for the proper exercise of authority
p. 4 / para. 11Reliance on A.K.G. Construction and Developers Pvt. Ltd. v. State of Jharkhand, which establishes that the decision to blacklist is independent of termination and requires a separate application of mind and notice
p. 4 / para. 12Application of UMC Technologies Private Limited v. Food Corporation of India, which mandates that a show-cause notice must clearly spell out the intention to blacklist to allow an "informed and meaningful opportunity" to respond
p. 5 / para. 13Provisions in the judgment · 4 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 9Section 11Section 12Section 21
04Reasoning
The Court observed that the respondent admitted to not issuing a specific notice regarding the proposed blacklisting
p. 3 / para. 8The Court rejected the respondent's contention that the existence of a contractual clause (Clause 29) authorizing blacklisting obviated the need for a notice
p. 6 / para. 13Applying the UMC Technologies precedent, the Court reasoned that the mere existence of a clause in a bid or contract document does not satisfy the mandatory requirement of a clear proposed action in a show-cause notice
p. 6 / para. 13Since the petitioner had a 21-year relationship with the respondent and held various other contracts, the Court found that the blacklisting order without due process would cause irreparable damage, establishing a prima facie case and balance of convenience in favor of the petitioner
pp. 6-7 / para. 1405Holding
The Court held that the blacklisting order was procedurally infirm for lack of a show-cause notice and stayed the Letter dated November 24, 2025, to the extent of the blacklisting
p. 7 / para. 15Upon the parties' mutual agreement, the Court waived the statutory requirements of Section 21 and Section 11 of the Arbitration Act and referred the dispute to a Sole Arbitrator under the aegis of the Delhi International Arbitration Centre (DIAC)
pp. 8 / para. 18-21The petition was disposed of with directions for the arbitrator to adjudicate all claims and counter-claims on merits
pp. 9 / para. 21-23Original Court PDF
S P TelecomvsRailtel Corporation Of India Limited
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
