Bombay High CourtCivil Procedure and EvidenceContract Law

Bombay HC Issues Civil Contempt Notice To PMT Machines, Directors Over Alleged Breach Of Property-Sale Undertaking

Anchor Point Developer Private Limitedv.Pmt Machines Limited

Bombay HC Issues Civil Contempt Notice To PMT Machines, Directors Over Alleged Breach Of Property-Sale Undertaking. Anchor Point Developer Private Limited vs Pmt Machines Limited. Bombay High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the Consent Terms and the order dated 23 April 2025 disclosed a prima facie undertaking to the Court, and whether alleged non-compliance warranted notice for civil contempt.

The court held

The Court found a prima facie case and issued notice under Rule 1035 to Respondent Nos. 1–6 to show cause why action for civil contempt should not be taken under Sections 12 and 2(b) of the Contempt of Courts Act for the alleged wilful breach of the undertakings in the Consent Terms and the order dated 23 April 2025.

It also directed

Notice was made returnable on 4 November 2026, and Respondent Nos. 2–6 were directed to remain present at each hearing unless exempted.

The Court did not finally determine contempt or the validity of the Consent Terms.

01Facts

The parties executed Consent Terms dated 26 December 2024 to settle disputes concerning the proposed sale of properties by Respondent No. 1.

¶ 2–3

By an order dated 23 April 2025, the Bombay High Court disposed of the Section 9 arbitration petition in accordance with the Consent Terms and recorded that the undertakings in them would be treated as undertakings given to the Court.

¶ 2–3

The Consent Terms required Respondent No. 1 to complete the sale by 30 September 2025 and deliver possession within one year of their execution.

¶ 6–9

The Petitioner alleged non-compliance and filed this contempt petition.

The Respondents disputed the authority and legality of the Consent Terms, denied wilful breach, and relied, among other things, on pending execution proceedings.

¶ 18–21, 29–30

02Issues

i.1. Whether the Consent Terms and the order dated 23 April 2025 disclosed a prima facie undertaking to the Court, and whether alleged non-compliance warranted notice for civil contempt.

¶ 1, 10–17, 46–47

ii.2. Whether the Respondents’ challenges to the Consent Terms—including alleged lack of authority, statutory invalidity, and disputed contractual rights—precluded notice at the preliminary stage.

¶ 18–21, 29–33

iii.3. Whether the pending execution proceedings, alleged absence of wilfulness, or limitation under Section 20 barred the contempt petition at this stage.

¶ 30, 34–38, 44–45

iv.4. Whether notice could issue to Respondent Nos. 2–6, and whether their alleged role required consideration at the notice stage.

¶ 39–40, 47–49

03Law Applied

Rule 1035(1) of the Bombay High Court (Original Side) Rules, 1980 permits notice in a contempt petition where a prima facie case is made out; the Court need not finally determine guilt at that stage.

¶ 4–5

Under Sections 2(b) and 12 of the Contempt of Courts Act, 1971, civil contempt includes the wilful breach of an undertaking given to a court, and wilfulness is essential.

¶ 34

Bajranglal Gangadhar Khemka v. Kapurchand Ltd. , 1950 SCC OnLine Bom 12, recognises that an undertaking in consent terms incorporated into a court order may be enforceable as an undertaking to the Court, but breach must be deliberate.

¶ 14–17, 34–35

Kanwar Singh Saini v. High Court of Delhi , (2012) 4 SCC 307, and R.N. Dey v. Bhagyabati Pramanik , (2000) 4 SCC 400, establish that contempt is not a substitute for execution; Abdul Kadar v. Abbasbhai Abdul Quayoom , 1974 SCC OnLine Bom 92, recognises that execution proceedings do not necessarily preclude examination of a separate breach of an undertaking.

¶ 29–31

Dinesh Kumar Gupta v. United India Insurance Co. Ltd. , (2010) 12 SCC 770, and U.N. Bora v. Assam Roller Flour Mills Assn. , (2022) 1 SCC 101, require conscious, wilful disobedience and caution against inferring contempt from speculation.

¶ 38

Section 20 of the Contempt of Courts Act was considered in light of Pallav Sheth v. Custodian , (2001) 7 SCC 549, concerning when contempt proceedings are initiated for limitation purposes.

¶ 44–45

Provisions in the judgment · 5 · Linked ones open on LawLens

Arbitration and Conciliation Act, 1996 Section 9

Companies Act, 2013 Section 180

Contempt of Courts Act, 1971 Section 2Section 18Section 20

04Reasoning

The Court read the order and Consent Terms together: the order expressly treated the Consent Terms’ undertakings as undertakings to the Court, while Clauses 5(a) and 5(b) set out the sale obligations and a fixed completion date.

¶ 10, 13, 17

The allegations of want of authority and breach of Section 180 of the Companies Act, 2013 were not established on the material before the Court, and the underlying order had not been set aside or stayed.

¶ 18–21, 43

Although execution is the proper route to obtain conveyance and possession, it did not, by itself, dispose of the distinct allegation of wilful breach of a court undertaking.

¶ 30–33

Given the alleged non-performance after the specified deadlines and the absence, at this stage, of material explaining non-compliance, the Respondent No. 1 could be required to show cause; wilfulness remained to be determined on the evidence.

¶ 36, 38, 46

The material did not justify rejecting the petition as time-barred at the preliminary stage.

¶ 44–45

05Holding

The Court found a prima facie case and issued notice under Rule 1035 to Respondent Nos. 1–6 to show cause why action for civil contempt should not be taken under Sections 12 and 2(b) of the Contempt of Courts Act for the alleged wilful breach of the undertakings in the Consent Terms and the order dated 23 April 2025.

¶ 47

Notice was made returnable on 4 November 2026, and Respondent Nos. 2–6 were directed to remain present at each hearing unless exempted.

¶ 48–49

The Court did not finally determine contempt or the validity of the Consent Terms.

Bombay High Court

Original Court PDF

Anchor Point Developer Private LimitedvsPmt Machines Limited

Bombay High Court · October 27, 2026