01Facts
The petitioner operated a stone-crusher plant supplied through two electricity meters.
p. 2On 18 December 2024, an MSEDCL flying squad alleged that supply to one connection had been diverted so as to bypass the meter.
pp. 2-4MSEDCL raised a theft-of-electricity bill of ₹22,93,410 and a separate compounding charge of ₹7,50,000; following non-payment, supply to both meters was disconnected and a complaint under Section 135 of the Electricity Act, 2003 was lodged.
pp. 2-4In proceedings before the Special Court for determination of civil liability under Section 154(5), a court-appointed Electrical Inspector reported that the theft period could not be established and assessed net consumption of 16,591 units on a six-month basis.
pp. 4-5 · p. 12The petitioner’s applications for interim restoration were rejected.
pp. 5-6In this petition under Article 227, he sought restoration on payment of an amount based on the Inspector’s report; MSEDCL maintained that supply could not be restored without payment of its full demand.
pp. 5-6 · pp. 6-1102Issues
i.Whether, in a case alleging theft of electricity, supply could be restored before final determination of civil liability under Section 154(5), on payment of an amount assessed under the procedure applicable to Section 126.
pp. 23-25 · p. 43ii.Whether the circumstances, including the absence of a Section 126 assessment and the prima facie concern about the 22-month assessment period, justified interim restoration on payment of 50% of the demanded electricity charges.
pp. 45-4903Law Applied
Section 135(1A), third proviso, of the Electricity Act, 2003 requires restoration of supply within 48 hours upon deposit or payment of the assessed amount or electricity charges; Section 126 provides the assessment procedure, including provisional assessment, an opportunity to object, and final assessment, while Section 127 provides an appeal against the final assessment.
pp. 13-24Section 154(5) empowers the Special Court to determine civil liability for theft, and Section 154(6) provides for refund of excess amounts deposited.
p. 21 · p. 24Following West Bengal State Electricity Distribution Co. Ltd. v. Orion Metal Pvt. Ltd., Himadri Steel Pvt. Ltd. v. Jharkhand Urja Vikas Nigam Ltd. and Dakshin Gujarat Vij Co. Ltd. v. Vaibhav Metal Crusher, the Court held that, absent a separate applicable assessment procedure, the “assessed amount” for restoration under Section 135(1A) is determined under Sections 126 and 127; that assessment remains subject to the Special Court’s determination of civil liability.
pp. 29-40The Court also applied the principle in Dakshin Gujarat that, where a provisional assessment is prima facie arbitrary, a constitutional court may, for recorded reasons, order restoration on payment of an amount not less than 50% of the demand.
pp. 41-42Clause 10.1.2 of the Maharashtra Electricity Regulatory Commission (Electric Supply Code and Standards of Performance of Distribution Licensees including Power Quality) Regulations, 2021 provides for assessment at twice the applicable tariff and presumes a 12-month period where the period of theft cannot be ascertained.
pp. 44-45Provisions in the judgment · 20 · Linked ones open on LawLens
Electricity Act, 2003 13 provisions
Section 50Section 126Section 127Section 135Section 136Section 137Section 138Section 139Section 140Section 150Section 153Section 154Section 181Code of Criminal Procedure, 1973 Section 260Section 262Section 263Section 264Section 265Section 307Section 308
04Reasoning
The Court found no material showing that MSEDCL had followed the Section 126 procedure or issued a final assessment after giving the petitioner an opportunity to object.
pp. 45-46Although the Electrical Inspector was not the statutory Assessing Officer, the report could not be treated as valueless at the interim stage, particularly in the absence of a Section 126 assessment.
p. 47The Inspector’s finding that the theft period could not be established also raised a prima facie concern about MSEDCL’s 22-month assessment, given the 12-month default period in the Regulations and the limit specified in Section 154(5) for determining civil liability.
pp. 47-48In light of the prolonged disconnection and the time required for final determination, the Court considered interim restoration appropriate on payment of 50% of the electricity-charge demand.
p. 4805Holding
The Court partly allowed the petition, quashed the District Judge’s order dated 29 January 2026, and directed MSEDCL to restore supply to both meters within three days after the petitioner paid ₹11,46,705—50% of the electricity-charge bill of ₹22,93,410—together with any reconnection charges.
pp. 48-50It clarified that its observations were not to influence the Special Court’s final determination of civil liability under Section 154(5).
p. 50Original Court PDF
Sopan Haribhau AthsherevsThe Superintendent Engineer Msed Company And Ors
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in