Bombay High CourtProperty and Real Estate LawAdministrative and Public Law

Bombay HC Quashes Plan To Acquire 84 Hectares From Tata Power For Private Wellness Project, Citing Ongoing Hydro Use

The Tata Power Company Ltd. And Anrv.The State Of Maharashtra And Ors

Bombay HC Quashes Plan To Acquire 84 Hectares From Tata Power For Private Wellness Project, Citing Ongoing Hydro Use. The Tata Power Company Ltd. And Anr vs The State Of Maharashtra And Ors. Bombay High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the State could use the MID Act to acquire land exclusively for a private company, and whether the acquisition was within the Act’s purposes.

The court held

The Court held that the proposed acquisition was unsustainable: the land remained associated with its original public purpose, the MID Act could not be used to acquire it solely for the benefit of the private respondent, and the acquisition was not shown to serve a primarily public purpose.

It also directed

It allowed the petition, quashed the impugned notifications dated 3 and 4 March 2025 and the show-cause notices dated 7 March 2025, and disposed of the proceedings pending before the SDO.

01Facts

Between 1911 and 1940, land including the disputed 84 hectares was acquired and conveyed to Tata Power’s predecessor for a hydro-electric project, subject to contractual provisions concerning land not used or intended for that project.

¶ 5–6, 69–72

Tata Power maintained that the land remained part of its existing hydro-electric operations and was required for a proposed 1,000 MW pumped-storage project.

¶ 18, 73

The State issued notifications under the Maharashtra Industrial Development Act, 1961 (MID Act), declaring the land an industrial area and initiating acquisition proceedings for the benefit of respondent No. 6, a private company already holding approximately 126 hectares for its proposed project.

¶ 21–26

Tata Power challenged the notifications and show-cause notices under Article 226; the statutory hearing before the Sub-Divisional Officer had concluded, but no decision had been made.

¶ 27–28

02Issues

i.1. Whether the State could use the MID Act to acquire land exclusively for a private company, and whether the acquisition was within the Act’s purposes.

¶ 80, 84–87, 97–100

ii.2. Whether the land could be treated as unutilized and acquired despite its original acquisition for, and alleged continuing use in, hydro-electric projects.

¶ 73–78

iii.3. Whether the proposed acquisition served a public purpose, rather than primarily a private interest, and whether the State’s actions amounted to colourable exercise of power.

¶ 91–100, 109–118

iv.4. Whether the petition was maintainable despite the pending statutory proceedings before the SDO.

¶ 119–124

03Law Applied

Section 1(3) of the MID Act permits Chapter VI to operate in an area, while Sections 32 and 39 concern acquisition and disposal of land for the Act’s purposes; the Act is directed to developing industrial areas or estates, not to acquisition solely for a private company.

¶ 84–86

The Constitution Bench in Shri Ramtanu Co-operative Housing Society Ltd. v. State of Maharashtra held that the MID Act contains no procedure for acquisition for a company, unlike the general land-acquisition law.

¶ 85

Section 39(2)(a) also requires MIDC, before disposing by sale of undeveloped acquired land, to offer it first to the persons from whom it was acquired.

¶ 98

Under the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, acquisition for a private company must meet the statutory public-purpose requirements; the Court found that the Maharashtra exemption in Section 10A did not apply to this project.

¶ 82–83

The power of eminent domain is subject to the requirement of public purpose and lawful procedure; under K. T. Plantation Pvt. Ltd. v. State of Karnataka, the purpose must be primarily public, not primarily private with only incidental public benefit.

¶ 91–96, 115

Article 300-A, as discussed in Kolkata Municipal Corporation v. Bimal Kumar Shah, includes the State’s duty to acquire property only for public purpose.

¶ 91

A show-cause notice issued with a predetermined outcome may be challenged by writ under Siemens Ltd. v. State of Maharashtra.

¶ 120–122

Provisions in the judgment · 17 · Linked ones open on LawLens

Maharashtra Industrial Development Act, 1961. 12 provisionsSection 1Section 2Section 3Section 14Section 32Section 33Section 34Section 36Section 39Section 41Section 43Section 53

Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 Section 2Section 3Section 4Section 10Section 46

04Reasoning

The Court found that the land had been acquired for the hydro-electric project and that Tata Power had shown it remained relevant to that use, including the proposed pumped-storage project. The State had neither identified the land as unutilized in the impugned instruments nor conducted an inquiry into non-utilisation; it could not supply that justification later through affidavits.

¶ 73–78

The acquisition was intended exclusively to benefit respondent No. 6, with compensation to be paid by that company, and the MID Act could not be used as a substitute for the statutory route governing acquisition for a private company.

¶ 87, 97–100

The project’s stated employment and other benefits did not establish that its primary purpose was public: the record showed that the additional land was sought principally for the project’s location and aesthetic features, despite the company already holding about 126 hectares.

¶ 109–118

The sequence of decisions, including the overruling of earlier committee recommendations and the decision to proceed without the landowner’s NOC, supported the finding of colourable exercise of power.

¶ 100–108

The petition was maintainable because the SDO could not determine the constitutional challenges and, in the circumstances, the statutory hearing was found to be a foregone conclusion.

¶ 123–124

05Holding

The Court held that the proposed acquisition was unsustainable: the land remained associated with its original public purpose, the MID Act could not be used to acquire it solely for the benefit of the private respondent, and the acquisition was not shown to serve a primarily public purpose.

¶ 134–135

It allowed the petition, quashed the impugned notifications dated 3 and 4 March 2025 and the show-cause notices dated 7 March 2025, and disposed of the proceedings pending before the SDO.

¶ 135–136
Bombay High Court

Original Court PDF

The Tata Power Company Ltd. And AnrvsThe State Of Maharashtra And Ors

Bombay High Court · November 05, 2026