Karnataka High CourtCivil Procedure and EvidenceArbitration and Mediation

Brother's Plea to Undo 2006 Lok Adalat Partition Compromise Fails Over Delay, Missing Fraud Details

ABDUL REHAMAN S/O KASHIMSA BAGWANv.HUSSAINBASHYA S/O KASHIMS BAGWAN AND ORS

Brother's Plea to Undo 2006 Lok Adalat Partition Compromise Fails Over Delay, Missing Fraud Details. ABDUL REHAMAN S/O KASHIMSA BAGWAN vs HUSSAINBASHYA S/O KASHIMS BAGWAN AND ORS. Karnataka High Court. LawLens
The LawLens card for this judgmentXLinkedInWhatsApp

In brief

The question

1. Whether the petitioner's challenge to the Lok Adalat compromise decree dated 08.11.2006 is barred by delay and laches, given the petitioner raised no objection until 2014.

The court held

The writ petition challenging the compromise decree dated 08.11.2006 in O.S. No. 173/2006 is liable to be dismissed on the grounds of delay and laches, because the petitioner did not object until 2014.

It also directed

The fraud allegation was not supported by pleaded particulars of date and items as required by Order VI Rule 4 CPC, and no merit was found on the substance.

The writ petition is dismissed, and the Lok Adalat compromise decree stands.

01Facts

Respondent No. 1 filed O.S. No. 173 of 2006 on 11.10.2006 seeking partition and separate possession of a 1/4th share in the suit properties.

p. 3 · ¶ 2

The first hearing was fixed for 13.10.2006, notice was ordered, and the matter was posted to 14.11.2006.

p. 3 · ¶ 2

The petitioner alleges that the respondents misled him and filed a compromise petition under which he and the respondents were to take a 1/4th share in Sy. No. 180/1/D, Bidarkundi village.

p. 3 · ¶ 2

The matter was referred to the Lok Adalat, Muddebihal, and a compromise decree was drawn on 08.11.2006.

pp. 3–4 · ¶ 2 · p. 8 · ¶ 7

The petitioner contends that the respondents obtained his signature under the guise of an application in another suit (O.S. No. 2 of 2001) and that the decree was not acted upon until 2014.

p. 5 · ¶ 4

He further contends that the hearing date was advanced to 08.11.2006 and the reference to Lok Adalat made the same day, which he says was arbitrary.

p. 5 · ¶ 4 · p. 7 · ¶ 7

The respondents state that the petitioner appeared through counsel, signed the compromise after its contents were explained, that the parties acted on the decree, and that revenue records were changed.

p. 6 · ¶ 5

The petitioner filed C.M.P. No. 3 of 2014 to set aside the decree; it was dismissed on 23.10.2020 on the ground that a Lok Adalat decree is challenged by writ petition, not by miscellaneous petition.

pp. 3–4 · ¶ 2 · p. 8 · ¶ 7

The present writ petition under Article 227 of the Constitution was filed in February 2021.

p. 6 · ¶ 5 · p. 1

02Issues

i.1. Whether the petitioner's challenge to the Lok Adalat compromise decree dated 08.11.2006 is barred by delay and laches, given the petitioner raised no objection until 2014.

pp. 8–9 · ¶ 7

ii.2. Whether the petitioner's allegation of fraud is maintainable where the writ petition fails to plead the particulars of the alleged fraud, including dates and items, as required by Order VI Rule 4 CPC.

pp. 9–10 · ¶ 8–9

03Law Applied

The Court applied Article 227 of the Constitution as the procedural vehicle for challenging the Lok Adalat decree.

p. 1 · p. 3 · ¶ 2

Order VI Rule 4 of the Code of Civil Procedure requires that particulars (with dates and items, where necessary) be stated in pleadings where a party relies on misrepresentation, fraud, breach of trust, wilful default, or undue influence.

p. 10 · ¶ 8

Unexplained delay and laches in challenging a decree disentitle a party to relief in writ jurisdiction.

pp. 9–10 · ¶ 9

No precedents were cited in the judgment.

04Reasoning

It is undisputed that the matter was referred to Lok Adalat on the parties' submissions, that the petitioner appeared through counsel, and that the compromise bore his signature and counsel's identification after its contents were read out.

pp. 7–8 · ¶ 7

Although the petitioner raised no objection from 09.11.2006 and approached the Court only in 2014, the Court treated the eight-year delay as a basis for holding the challenge belated.

pp. 8–9 · ¶ 7

On fraud, the Court noted that the writ petition did not particularise the events constituting the alleged fraud.

p. 9 · ¶ 7

Applying Order VI Rule 4 CPC, the Court held that the absence of dates and items in the pleadings was fatal to the fraud plea.

p. 10 · ¶ 9

The judgment does not separately address the petitioner's contention that advancing the hearing date was arbitrary.

p. 5 · ¶ 4 · no further discussion

05Holding

The writ petition challenging the compromise decree dated 08.11.2006 in O.S. No. 173/2006 is liable to be dismissed on the grounds of delay and laches, because the petitioner did not object until 2014.

p. 9 · ¶ 7 · p. 10 · ¶ 9

The fraud allegation was not supported by pleaded particulars of date and items as required by Order VI Rule 4 CPC, and no merit was found on the substance.

p. 10 · ¶ 8–9

The writ petition is dismissed, and the Lok Adalat compromise decree stands.

p. 10, order
Karnataka High Court

Original Court PDF

ABDUL REHAMAN S/O KASHIMSA BAGWANvsHUSSAINBASHYA S/O KASHIMS BAGWAN AND ORS