Delhi High Court
Arbitration and MediationConstruction Law

Clause 5.2 hindrance extensions count when determining entitlement to an early-completion bonus.

Union Of India vs Swadeshi Civil Infrastructure Pvt. Ltd.

Delhi High CourtJUDGMENT: October 12, 20263 MIN READSOURCE JUDGMENT
Clause 5.2 hindrance extensions count when determining entitlement to an early-completion bonus.. Union Of India vs Swadeshi Civil Infrastructure  Pvt. Ltd.. Delhi High Court. LawLens
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The dispute arose from a 30 July 2018 agreement for construction of 76 multi-storeyed flats at Dr. B.D. Marg, New Delhi.

Source reference: p. 1–2, para. 4–5

The parties agreed that the arbitral claims and counterclaims would be decided on the pleadings and documents, without oral evidence.

Source reference: p. 1–2, para. 4–5

The contractor was awarded ₹7,46,53,850 as an early-completion bonus under Claim 1.

Source reference: p. 2, para. 8

The Tribunal included 138 days of hindrance allowed under clause 5.2 when determining entitlement to the bonus, in addition to other justified extensions.

Source reference: p. 2, p. 4, para. 8, 15–17

The Union’s Section 34 petition challenged Claims 1, 4 and 7.

Source reference: p. 1, para. 3

The Court also found that, under Claim 4, the Tribunal had awarded interest on Claim 2 despite the contractor not having sought such interest.

Source reference: p. 1, p. 9, para. 3, 28–29
02

Issues

Whether hindrance days allowed under clause 5.2 could be counted in determining the contractor’s entitlement to an early-completion bonus under clause 2A, despite clause 2A expressly referring to extensions under clauses 5.3, 12 and 15.

Source reference: p. 3–4, p. 6–7, para. 11, 19, 22–25

Whether the Tribunal’s award of interest on Claim 2, when no such interest had been sought, was beyond the scope of the arbitration and could be set aside as a severable part of the award.

Source reference: p. 9, para. 28–30

Whether the direction to reimburse GST, where payable on the awarded amount, warranted interference under Section 34.

Source reference: p. 9–10, para. 31–34
03

Law Applied

Section 34 of the Arbitration and Conciliation Act, 1996 permits only limited judicial review of an arbitral award; the court is not an appellate forum and may not reappraise the merits merely because another interpretation is possible.

Source reference: p. 8, para. 24–25

Contractual interpretation lies primarily within the arbitral tribunal’s domain, subject to the award not being wholly unreasonable or contrary to the agreement (Ssangyong Engineering & Construction Co. Ltd. v. NHAI, (2019) 15 SCC 131).

Source reference: p. 8, para. 24–25

Under clause 2A of the agreement, a bonus is payable for completion ahead of the stipulated or justified extended completion date; clause 5.2 bars claims for damages arising from specified delays but does not expressly bar a bonus.

Source reference: p. 2, p. 5–6, para. 9, 19, 22–23

Under the majority decision in Gayatri Balasamy v. ISG Novasoft Technologies Ltd., 2025 SCC OnLine SC 986, a court’s limited power to modify an award includes severing an invalid portion where it is separable.

Source reference: p. 9, para. 30

The Court also noted that GST treatment may differ according to the nature of each component of an award, including whether it represents consideration for a supply or compensation for breach or loss.

Source reference: p. 10, para. 32–33
04

Reasoning

The Court held that the Tribunal’s interpretation of clause 2A was a permissible construction of the contract.

Source reference: p. 6–8, para. 22–27

Although clause 2A specifically referred to extensions under clauses 5.3, 12 and 15, clause 5.2 did not prohibit a bonus; it only precluded damages for the specified delays.

Source reference: p. 6–8, para. 22–27

The Tribunal could therefore take the 138 days allowed under clause 5.2 into account in assessing whether the contractor completed the work ahead of the applicable completion date, and the Court found no ground under Section 34 to disturb that interpretation.

Source reference: p. 6–8, para. 22–27

By contrast, interest on Claim 2 had not been claimed, so the Tribunal exceeded the scope of the proceedings in awarding it.

Source reference: p. 9, para. 29–30, 35

Since that interest component was separable, it could be set aside without disturbing the rest of the award.

Source reference: p. 9, para. 29–30, 35

The GST direction required reimbursement only where GST was actually payable and did not warrant interference.

Source reference: p. 9–10, para. 31–34
05

Holding

The petition was allowed in part.

The Court declined to interfere with the bonus awarded under Claim 1 or the GST direction under Claim 7.

Source reference: p. 10, para. 34–37

It set aside only the award of interest on Claim 2, as that relief had not been sought and was severable from the remainder of the award.

Source reference: p. 10, para. 34–37

Pending applications were also disposed of.

Source reference: p. 11, para. 37
06

Acts & Sections Cited

4 provisions across 2 statutes referred to in this judgment. Each provision opens on LawLens.

Arbitration and Conciliation Act, 19962

Indian Contract Act, 18722

Delhi High Court

Original Court PDF

Union Of IndiavsSwadeshi Civil Infrastructure Pvt. Ltd.

Delhi High Court · October 12, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment