01Facts
In 2011, the respondent awarded the petitioner a contract for the construction of a memorial in Punjab
¶ 2The respondent unilaterally appointed a sole arbitrator in 2019, whose award was subsequently set aside by the High Court in a Section 37 appeal on 02.04.2025 for violating Section 12(5) of the Arbitration and Conciliation Act, 1996
¶ 2.1, 2.2Following a Section 21 notice, the petitioner filed the present petition under Section 11(6) for the appointment of an independent arbitrator
¶ 1, 2.2The respondent contested the petition based on Clause 48 of the contract, which stipulated that arbitration must be conducted by the respondent’s Managing Director/Chief Engineer or their nominee; further, the clause stated that if such an appointment was not possible, the matter should not be referred to arbitration at all
¶ 302Issues
i.1. Whether a contractual clause that forecloses the right to arbitration if the contractee’s designated official cannot act as an arbitrator is valid and enforceable under the Act
¶ 3, 6.1ii.2. Whether the court can invoke Section 11(6) to appoint an independent arbitrator by severing the unilateral appointment mechanism from the arbitration agreement
¶ 6.1, 703Law Applied
The court applied Section 11(6) and Section 18 of the Arbitration and Conciliation Act, 1996, the latter of which mandates equal treatment of parties
¶ 1, 6.1It relied extensively on the Supreme Court precedent in Hindustan Construction Company Ltd. v. Bihar Rajya Pul Nirman Nigam Limited (2025 SCC OnLine SC 2578), which held that clauses granting a party an "absolute veto" over arbitration violate Article 14 of the Constitution (principles of fairness and non-arbitrariness) and Section 18 of the Act
¶ 4, 6.1The court also applied the doctrine of severability to ensure that the substantive intent to arbitrate survives the striking down of an unenforceable appointment mechanism
¶ 6.1Provisions in the judgment · 7 · Linked ones open on LawLens
Arbitration and Conciliation Act, 1996 Section 7Section 11Section 12Section 18Section 21Section 34Section 37
04Reasoning
The court observed that the restrictive portion of the arbitration clause—providing that the matter "shall not be referred to arbitration at all" if the respondent's nominee cannot act—is "vague, uncertain, and arbitrary"
¶ 6.1Applying the Hindustan Construction ruling, the court held that in public-private contracts involving Public Sector Undertakings (PSUs), such clauses fail the test of constitutional scrutiny under Article 14
¶ 6.1The court rejected the respondent's argument that the absence of "consent" at the Section 11 stage distinguished this case from precedent, clarifying that the valid arbitration agreement is derived from the surviving portion of the clause after severing the illegal unilateral mechanism
¶ 7, 8The court concluded that the intention to arbitrate remained intact, empowering the court to "cure the defect" by appointing an independent arbitrator
¶ 6.1, 805Holding
The court allowed the petition, holding that a valid and subsisting arbitration agreement exists between the parties despite the restrictive language of Clause 48
¶ 7, 8The court appointed Justice Mr. Krishna Kumar Lahoti (Retd.) as the sole arbitrator
¶ 9It directed that the arbitrator’s fees be governed by Schedule IV of the Act and required a Section 12 disclosure before entering upon the reference
¶ 10All rival claims and counterclaims were left open for adjudication by the learned arbitrator
¶ 11Original Court PDF
Salil KumarvsIndia Tourism Development Corporation Limited
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in
