01Facts
The petitioner, Karnataka Neeravari Nigam Ltd. (KNNL), is the beneficiary of a land acquisition for an irrigation project.
p. 1 · p. 3It challenged the judgment and award dated 22.06.2017 in LACA No. 50/2017 passed by the I Additional District Judge, Kalaburagi, seeking a writ of certiorari.
p. 1 · p. 3It was not disputed that KNNL, as beneficiary, was not arrayed as a party before the First Appellate Court.
¶ 2 · p. 3The matter was referred to mediation under retired Justice A.V. Chandrashekar by order dated 07.07.2025.
pp. 4–5The parties executed a Memorandum of Mediation Agreement, approved by the State Government on 25.02.2026.
p. 5Key terms include: market value fixed at Rs. 1,56,621 per acre for dry land.
p. 5, cl. (a)Key terms include: no interest for the delay in filing the appeal.
p. 5, cl. (c)Key terms include: claimants to forgo statutory interest for three years.
p. 5, cl. (d)Key terms include: payment through the P.D. account of KNNL (Head of Account "8443-00-106").
p. 6, cl. (g) · p. 7, cl. (n)Key terms include: withdrawal of pending execution petitions.
p. 6, cl. (k)The Deputy Commissioner, Kalaburagi did not sign the agreement, but the authorised Land Acquisition Officer did.
¶ 6–7 · p. 8Claimants sought an assurance against TDS and Form 16A issuance on the compensation.
¶ 8 · p. 802Issues
i.1. Whether a mediation settlement between the beneficiary of acquisition and the land losers, not signed by the Deputy Commissioner but signed by the authorised Land Acquisition Officer and approved in principle by the State, can be accepted as a lawful compromise.
¶ 6–7 · p. 8ii.2. Whether compensation paid under the mediation agreement is subject to deduction of tax at source.
¶ 8 · pp. 8–9iii.3. Whether the mediated settlement can be given effect under Section 89 CPC read with Order XXIII Rule 3 CPC so as to operate in substitution of the award, judgment, or decree of the Reference and Appellate Courts.
¶ 9 · p. 903Law Applied
The court relied on Section 89 of the Code of Civil Procedure, 1908, read with Order XXIII Rule 3 CPC, under which a lawful settlement may be treated as a compromise that operates in substitution of a decree or award.
¶ 9 · p. 9It also applied the settled principle, drawn from its own earlier order in W.P. No. 102884/2025 dated 20.08.2025, that compensation for compulsory acquisition of land is not subject to tax deduction at source under the Income Tax Act, 1961.
¶ 8 · pp. 8–9The court further referred to the statutory benefits payable under the Land Acquisition Act, which the parties agreed to give or forgo in part; no specific sections are identified in the order.
pp. 5, cl. (b)–(d)The court noted that the dispute was mainly between the beneficiary and the land losers, and that the State had consented in principle to the settlement.
¶ 6 · p. 8Provisions in the judgment · 1 · Linked ones open on LawLens
Code of Civil Procedure, 1908 Section 89
04Reasoning
The court first examined the absence of the Deputy Commissioner's signature. It held that the dispute was essentially between the beneficiary and the land losers, that the State had approved the agreement in principle, and that the authorised Land Acquisition Officer had signed. It therefore dispensed with the Deputy Commissioner's signature and accepted the mediation report.
¶ 6–7 · p. 8On TDS, the court treated the question as settled by its earlier ruling that compulsory acquisition compensation is not liable to TDS. It directed that all payments under the agreement, whether to joint or individual accounts, be made without any deduction.
¶ 8 · pp. 8–9Finally, the court found the agreement to be a lawful settlement within Section 89 CPC read with Order XXIII Rule 3 CPC. Because the agreement was reached after detailed mediation and was voluntary, the court held that it should replace the earlier award and decree.
¶ 9 · p. 9The agreement's clauses, including the exclusion of interest for the appellate delay, the three-year interest waiver, the full-and-final-settlement clause, and the court-fee reimbursement, were recorded as part of the order.
pp. 5–805Holding
The court accepted the Memorandum of Mediation Agreement, found it to be a lawful settlement under Section 89 CPC read with Order XXIII Rule 3 CPC, and held that it operates in substitution of the award, judgment, or decree of the Reference and Appellate Courts.
¶ 6–7, 9 · pp. 8–9It held that compensation under the agreement is not liable to TDS and directed that all payments be made without any deduction at source.
¶ 8 · p. 9It dispensed with the Deputy Commissioner's signature.
¶ 6 · p. 8The court directed the concerned Courts to draw up a decree in terms of the agreement within 60 days of receiving a certified copy of the order.
¶ 9 · p. 9The writ petition was disposed of in terms of the memorandum of settlement.
¶ 10 · p. 10Original Court PDF
KARNATAKA NEERAVARI NIGAM LIMITED BENGALURUvsSYED AHMED HUSSAIN S/O KHAJA PEERA AND ORS
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in