01Facts
The petitioner, Karnataka Neeravari Nigama Ltd. (KNNL), the beneficiary of a land acquisition, challenged the judgment and award dated 23.08.2018 in LACA No. 807/2017 passed by the I Addl. District and Sessions Judge, Kalaburagi.
¶ 1 · ¶ 2It was undisputed that KNNL had not been impleaded as a party before the First Appellate Court.
¶ 2The matter was referred to mediation before Justice A.V. Chandrashekar (Retd.) under the Court's order dated 07.07.2025.
¶ 3The mediation produced a Memorandum of Settlement, approved by the State Government on 25.02.2026, fixing the market value at ₹1,28,400 per acre for dry land, with statutory benefits payable except for the period of delay in filing the appeal, and no interest for the delay period.
¶ 4, clauses (a), (b), (c)Under the settlement, the claimants agreed to forgo statutory interest for three years, with the interest waiver forfeited if payment is not made within four months, and payment to be made through the P.D. Account of the Chief Accounts Officer, KNNL, Dharwad (Head of Account 8443-00-106).
¶ 4, clauses (d), (f), (g), (n)The settlement was recorded as a full and final settlement, with KNNL to pay costs equal to the court fee paid by the claimants.
¶ 4, clauses (h), (j), (m)The Deputy Commissioner, Kalaburagi did not sign the agreement, but the Land Acquisition Officer, authorised for the purpose, did.
¶ 6 · ¶ 7The claimants raised apprehension regarding deduction of tax at source (TDS) and issuance of Form 16A on compensation.
¶ 802Issues
i.1. Whether the Mediation Agreement, signed by the Land Acquisition Officer and approved in principle by the State but not signed by the Deputy Commissioner, may be accepted as a lawful settlement capable of substituting the award, judgment, or decree of the Reference and Appellate Courts.
¶ 6 · ¶ 7 · ¶ 9ii.2. Whether compensation paid pursuant to the settlement is subject to deduction of tax at source under the Income Tax Act.
¶ 8iii.3. Whether, given the admitted non-impleadment of KNNL before the First Appellate Court, the writ petition could be disposed of by recording the settlement.
¶ 2 · ¶ 1003Law Applied
Section 89 of the Code of Civil Procedure, 1908, read with Order XXIII Rule 3 CPC, under which a settlement arrived at through mediation may be recognised as a lawful compromise that operates in substitution of a decree or award.
¶ 9The Court's power to refer the matter to mediation and to record the settlement arises from its jurisdiction under Articles 226 and 227 of the Constitution, invoked in the petition.
¶ 1 · prayer clause (A)The earlier ruling in W.P. No. 102884/2025 (order dated 20.08.2025) held that compensation for compulsory acquisition of land is not subject to TDS under the Income Tax Act.
¶ 8A settlement by the authorised representatives of the acquiring authority, with the State's consent in principle, is sufficient where the dispute lies mainly between the beneficiary and the land loser.
¶ 6 · ¶ 7The Land Acquisition Act framework for statutory benefits and the State's G.O. No. AE 13 TAR 2023 dated 27.09.2024 for the payment mechanism.
¶ 4, clauses (b), (g), (n)Provisions in the judgment · 1 · Linked ones open on LawLens
Code of Civil Procedure, 1908 Section 89
04Reasoning
Since the dispute was principally between the beneficiary (KNNL) and the land loser, and the State had consented in principle, the Deputy Commissioner's signature could be dispensed with. The authorised signature of the Land Acquisition Officer was treated as sufficient, and the mediation report was accepted.
¶ 6 · ¶ 7The Court did not re-examine tax law. It followed its earlier determination in W.P. No. 102884/2025 that acquisition compensation is not subject to TDS, and directed that all payments under the settlement, whether to joint or individual accounts, be made without deduction.
¶ 8The Court treated the settlement as a lawful compromise under Section 89 CPC read with Order XXIII Rule 3, so that it would replace the award, judgment, or decree below and require the trial and appellate courts to draw up a decree within 60 days.
¶ 9The order does not separately discuss the effect of KNNL's non-impleadment before the First Appellate Court. It records the non-joinder as undisputed and proceeds on the settlement, which KNNL itself signed through its representatives.
¶ 2 · ¶ 405Holding
The Mediation Agreement, although not signed by the Deputy Commissioner, is a lawful settlement under Section 89 CPC read with Order XXIII Rule 3 CPC, and operates in substitution of the impugned award and the decrees of the lower courts.
¶ 6 · ¶ 7 · ¶ 9Compensation under the settlement is not subject to TDS, and all payments are to be made without any deduction at source. The writ petition is disposed of in terms of the memorandum of settlement. Under clause (o), the settlement is not a precedent or policy decision binding on KNNL in other cases.