Facts
The Appellants (APSPDCL and others) challenged an order dated 05.07.2021 passed by the Andhra Pradesh Electricity Regulatory Commission (APERC).
Source reference: p. 2Respondent No. 2, M/s Chaitanya Projects Ltd., commissioned a 0.8 MW wind project on 29.03.2017 and executed a Power Purchase Agreement (PPA) with Appellant No. 1 on 30.03.2017.
Source reference: p. 3While the State Commission declared the PPA invalid for lacking mandatory statutory approval under Section 86(1)(b) of the Electricity Act, 2003, it invoked Section 70 of the Contract Act, 1872, to direct the Appellants to compensate Respondent No. 2 for energy injected into the grid from 2017 until disconnection in 2020 at a rate of ₹2.93 per unit.
Source reference: p. 2-3The Appellants appealed against this specific direction for compensation.
Source reference: p. 3Issues
1. Whether a power generator can be awarded compensation under Section 70 of the Indian Contract Act, 1872, for energy injected into a grid system under the aegis of an unapproved and legally unenforceable PPA?
Source reference: p. 4, para. 102. Whether the appellate court should exercise discretionary powers under Order XLI Rule 33 of the CPC to modify the rate of compensation in the absence of a cross-appeal by the Respondent?
Source reference: p. 5, para. 15Law Applied
The court applied Section 86(1)(b) of the Electricity Act, 2003, regarding the necessity of Commission approval for power purchase costs.
Source reference: p. 2-3It primarily relied on Section 70 of the Indian Contract Act, 1872, which creates an obligation for a person enjoying the benefit of a non-gratuitous act to compensate the provider.
Source reference: p. 3Procedurally, the court invoked Order XLI Rule 33 of the Code of Civil Procedure (CPC), 1908, which grants appellate courts the power to pass any decree to do complete justice, as interpreted in Choudhary Sahu v. State of Bihar and K. Muthuswami Gounder v. N. Palaniappa Gounder, emphasizing that this power is discretionary and must be exercised with caution.
Source reference: p. 5-6Reasoning
The Tribunal noted that the factual and legal matrix was identical to a previous judgment (Appeal Nos. 11 and 468 of 2022) involving Vibrant Greentech India Private Limited (VGIPL), where the Tribunal had upheld the applicability of Section 70 of the Contract Act for energy injected without a valid PPA.
Source reference: p. 4-5Although the Tribunal had remanded the VGIPL case for a fresh determination of the compensation rate (due to a cross-appeal by the generator), it distinguished the present case.
Source reference: p. 5Here, Respondent No. 2 failed to appear or file any submissions or cross-appeal.
Source reference: p. 5While Order XLI Rule 33 of the CPC allows the court to grant relief to a non-appealing party in exceptional cases to avoid inconsistent decrees, the Tribunal determined that such discretionary power should be used sparingly.
Source reference: p. 6Since Respondent No. 2 showed no interest in the proceedings, the Tribunal declined to remand the matter for a higher rate of compensation.
Source reference: p. 6Holding
The Tribunal answered the first issue in the affirmative, upholding the State Commission's decision to award compensation under Section 70 of the Contract Act despite the invalidity of the PPA.
Regarding the second issue, the Tribunal declined to modify the rate of ₹2.93 per unit or remand the matter, citing the Respondent's absence and lack of cross-appeal.
Source reference: p. 6, para. 16The Appeal No. 456 of 2022 was dismissed, and the State Commission's order was upheld.
Source reference: p. 6Original Court PDF
Southern Power Distribution Company & OrsvsAndhra Pradesh Electricity Regulatory Commission & Anr
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in