Allahabad High Court

Compliance With Integrated Township Policy 80% Threshold Is Assessed Against Entire Project Area, Not Individual Villages.

Sidharth vs State Of U.P. And 4 Others

Allahabad High CourtJUDGMENT: May 29, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

The Ghaziabad Development Authority (GDA) initiated land acquisition for an "Integrated Township Project" (Park Town) in Village Mahrauli under the U.P. Township Policy, 2023

Source reference: para 3.1, 4.1

This followed earlier lapsed proceedings from 2013-2014 under the old 1894 Act

Source reference: para 3.3

A preliminary notification under Section 11(1) of the 2013 Act was issued on 07.03.2025 for 2.86844 hectares of land

Source reference: para 3.4

Petitioners filed objections under Section 15, which were rejected by the Collector; subsequently, a declaration under Section 19 and a notice under Section 21 were issued in 2026

Source reference: para 2, 3.8

Petitioners challenged the notifications primarily on grounds of non-compliance with the 80% prior-purchase rule of the 2023 Policy, lack of a valid R&R scheme, and mechanical rejection of objections

Source reference: para 2, 4.1-4.3
02

Issues

1. Whether the acquisition was vitiated by the failure to purchase/obtain consent for 80% of the land prior to notification as per the 2023 Policy

Source reference: para 6.9

2. Whether the rejection of Section 15 objections via an undated order constituted a violation of natural justice or non-application of mind

Source reference: para 6.5.2

3. Whether fresh proceedings under the 2013 Act are barred if earlier proceedings under the 1894 Act had lapsed

Source reference: para 6.2

4. Whether the acquisition complied with the procedural safeguards under Article 300-A of the Constitution

Source reference: para 6.11
03

Law Applied

Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013, specifically Section 11 (Notifications), Section 15 (Objections), Section 19 (Declaration), Section 21 (Notice), and Section 24(2) (Lapse of earlier proceedings)

Source reference: paras 6.2, 6.3, 6.5, 6.7

U.P. Township Policy, 2023, regarding the 20% acquisition limit

Source reference: para 3.1, 6.9

Precedent: Kolkata Municipal Corporation v. Bimal Kumar Shah regarding the seven sub-rights under Article 300-A

Source reference: para 6.11

Precedent: Ramniklal N. Bhutta v. State of Maharashtra on balancing public versus private interest

Source reference: para 6.1, 6.13.2

Precedent: Vijay Pal Singh v. State of U.P. regarding the calculation of consent thresholds and SIA compliance

Source reference: para 6.14
04

Reasoning

The Court found that Section 24(2) of the 2013 Act expressly permits fresh acquisition after the lapse of 1894 Act proceedings

Source reference: para 6.2

Regarding the 80% purchase/consent threshold, the Court held that the calculation must be based on the entire project area (46.5212 hectares) and not village-wise; since the developer purchased/consented to ~80% of the total project land, acquiring the remaining ~20% (including Mahrauli) was valid

Source reference: para 3.9, 6.9.2, 6.9.4

The Court dismissed the challenge to the undated Section 15 order, noting that since a Section 19 declaration was subsequently issued, the Government must have considered the report, and a mere lack of date is a curable irregularity, not an illegality

Source reference: para 6.5.4, 6.5.5

The SIA process was found compliant as hearings were held and reports approved by the Government

Source reference: para 6.4.3

The Court ruled that since the Act provides a complete mechanism for notice, hearing, and compensation, the sub-rights of Article 300-A were satisfied

Source reference: para 6.11.1
05

Holding

The Court dismissed all six writ petitions, holding that the acquisition proceedings were conducted in strict conformity with the 2013 Act and the 2023 Policy

It held that the 80% threshold is project-wide and not village-specific

Source reference: para 7(iii)

The Court directed the Collector to conclude the award inquiry under Sections 22 and 23, pass a Rehabilitation and Resettlement Award under Section 31, and ensure possession is taken only after full payment of compensation as per Section 38. Petitioners were granted liberty to approach the Section 64 Reference Authority for disputes regarding compensation or measurement

Source reference: para 8.1, 8.1(d)
Allahabad High Court

Original Court PDF

SidharthvsState Of U.P. And 4 Others

Allahabad High Court · May 29, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment