Facts
The Respondent issued a tender for the ‘Up-gradation, Operation & Maintenance of Inspection & Certification Centre’ at Jhuljhuli, Delhi
Source reference: para 2.1The Petitioner Consortium was declared the successful L1 bidder on 27.03.2025, and a Letter of Acceptance (LoA) was issued on 26.08.2025
Source reference: para 2.2On 18.11.2025, the Respondent issued a Show Cause Notice (SCN) alleging concealment of an FIR dated 13.05.2025 registered against a consortium member, M/s Naman Electronics, in Gujarat
Source reference: para 2.3Subsequent fact-finding revealed that M/s Naman Electronics’ license for a similar project in Mehsana, Gujarat, had been suspended on 21.02.2024 and cancelled/surrendered on 16.11.2024 following an investigation into the fraudulent issuance of fitness certificates
Source reference: para 8Consequently, the Respondent cancelled the tender and the LoA on 04.02.2026
Source reference: para 10The Petitioner challenged these orders, arguing that the FIR was a post-bid development and did not fall under the disclosure mandate of the tender
Source reference: para 3Issues
1. Whether the Petitioner’s failure to disclose the prior investigation and cancellation of its license in Gujarat constituted a violation of the disclosure requirements under Clause 3 of the tender
Source reference: para 13, 142. Whether the cancellation of the tender and LoA by the Respondent was arbitrary or illegal
Source reference: para 18Law Applied
The court primarily applied Clause 3 of the Tender Document ("Instructions to Bidders"), which mandates an undertaking that no consortium member is under investigation, charge-sheeted, convicted, or blacklisted regarding any similar project
Source reference: para 10, 13It also considered the principle from Siemens Ltd v. State of Maharashtra, which defines exceptions to the non-maintainability of writ petitions against show-cause notices when the authority acts with a pre-determined mind
Source reference: para 3.2, 17the court relied on the administrative law principle that non-disclosure of material facts vitiates the award of a contract and that authorities may act to preserve the sanctity of the procurement process
Source reference: para 15, 18Reasoning
The court rejected the Petitioner’s contention that the FIR (registered on 13.05.2025) was the only relevant event
Source reference: para 12, 14It noted that Clause 3 required disclosure of "investigations" in similar projects
Source reference: para 13Since the investigation into malpractices in Gujarat led to a license suspension in February 2024 and cancellation in November 2024—both occurring prior to the bid submission in February 2025—these were material facts that the Petitioner was obligated to disclose
Source reference: para 14, 16The court observed that the scope of work in the Mehsana project was identical to the subject tender, qualifying it as a "similar project"
Source reference: para 15The court reasoned that had these facts been disclosed, the Respondent would likely not have issued the LoA
Source reference: para 16It further held that the Siemens Ltd. precedent was inapplicable as the record clearly established a breach of tender conditions
Source reference: para 17Holding
The High Court dismissed the petition, holding that the Respondent's decision to cancel the tender and LoA was a legitimate exercise to preserve the sanctity of the procurement process
The court found no arbitrariness in the impugned orders dated 04.02.2026 and 18.02.2026, as the Petitioner had suppressed material facts regarding its disqualification in a similar project
Source reference: para 15, 18No costs were awarded
Source reference: para 19Original Court PDF
Consortium Of M/S Naman Electronics M/S Likhma Ram Bhambhu And M/S Shiv KumarvsGovernment Of Nct Of Delhi
Click to open original judgment
Original judgment, available to read, download and summarize on LawLens.in