Delhi High Court

Concession Agreement terms incorporated into Escrow and Substitution Agreements are binding and enforceable by lenders.

National Highways Authority Of India Nhai vs South Indian Bank Ltd And Union Bank Of India Ltd (Throuh South Indian Bank Limited) & Anr.

Delhi High CourtJUDGMENT: July 09, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

NHAI (Appellant) entered into Concession Agreements (CAs) with Respondent No. 2 for road projects

Source reference: para 3

Consequently, Escrow Agreements (EAs) and Substitution Agreements (SAs) were executed as tripartite contracts involving Respondent No. 1 (Lenders)

Source reference: para 5, 7

Following project delays, the Independent Engineer (IE) issued a Provisional Completion Certificate (PCC) on Dec 8, 2016, but purportedly kept it in "abeyance" via a letter dated Dec 17, 2016, citing incomplete works

Source reference: para 13, 101

NHAI terminated the CAs in 2019 due to financial defaults

Source reference: para 16

The Lenders invoked arbitration under the EAs and SAs, seeking a direction for NHAI to deposit the "Termination Payment" into the Escrow Account

Source reference: para 17

The Arbitral Tribunal ruled in favor of the Lenders, and a Single Judge dismissed NHAI’s Section 34 challenge

Source reference: para 19-20, 44

NHAI appealed under Section 37 of the Arbitration Act

Source reference: para 1
02

Issues

1. Whether the Concession Agreement (CA) forms part of the Escrow Agreement (EA) and Substitution Agreement (SA) through incorporation by reference.

Source reference: para 92, 98

2. Whether the Independent Engineer (IE) has the authority to keep a Provisional Completion Certificate (PCC) in abeyance or withdraw it once issued under the CA.

Source reference: para 101, 107

3. Whether the Lenders, as non-signatories to the CA, have the standing to demand the deposit of Termination Payments into the Escrow Account under the EA/SA.

Source reference: para 51, 115

4. Whether the Commercial Operation Date (COD) was achieved, thereby making the Termination Payment "due and payable."

Source reference: para 109-110
03

Law Applied

The court applied Section 37 of the Arbitration and Conciliation Act, 1996, which limits appellate interference to cases of patent illegality or conflict with public policy

Source reference: para 42, 89

It relied on the doctrine of "Incorporation by Reference," distinguishing M.R. Engineers & Contractors (P) Ltd. v. Som Datt Builders Ltd., noting that express language ("to form part of this agreement") integrates an annexed document into the main contract

Source reference: para 47, 99

The court further applied the principle that an Arbitral Tribunal’s interpretation of a contract is final if it is a "plausible view," as held in Jan De Nul Dredging India Pvt. Ltd. v. Tuticorin Port Trust

Source reference: para 89-90

Finally, it applied Clause 2.1 of the SA regarding the "Assignment of Rights" to establish the Lenders' standing

Source reference: para 94, 110
04

Reasoning

The Court found that Recital A of the EA and SA explicitly stated that the CA was annexed "to form part of this Agreement," making the CA's Termination Payment provisions enforceable under the tripartite agreements

Source reference: para 95-98

Regarding the PCC, the Court reasoned that Article 14.5 of the CA only allows for the withholding of a certificate before issuance; it provides no power to suspend or withdraw a PCC once granted

Source reference: para 101, 107

Because NHAI had expressly concurred with the IE’s recommendation to issue the PCC after finding the stretch safe for commercial operation, the COD was legally achieved

Source reference: para 105-106

Consequently, the Termination Payment became "due and payable" upon termination. The Court also held that under Clause 2.1 of the SA, the Concessionaire had assigned its rights and interests to the Lenders, granting them the standing to compel NHAI to perform its obligation of depositing funds into the Escrow Account

Source reference: para 110, 115

The court noted that NHAI failed to dispute the mechanical calculation of the payment before the Tribunal, rendering the quantum a settled finding of fact

Source reference: para 112
05

Holding

The Court answered the issues in the affirmative for the Respondents, holding that the CA was incorporated into the EA/SA and the PCC could not be unilaterally kept in abeyance

The Court upheld the Arbitral Awards and the Single Judge's judgment, confirming that NHAI is contractually mandated to deposit the Termination Payment (₹ 229.50 crore and ₹ 181.81 crore respectively) plus interest into the Escrow Account

Source reference: para 19, 37, 117

The appeals were dismissed

Source reference: para 117
Delhi High Court

Original Court PDF

National Highways Authority Of India NhaivsSouth Indian Bank Ltd And Union Bank Of India Ltd (Throuh South Indian Bank Limited) & Anr.

Delhi High Court · July 09, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment