Delhi High Court

Consolidation of Civil and Criminal Proceedings Does Not Bar Prosecution or Warrant Quashing Under Section 138 NI Act.

Sh. Rajpal Naurang Yadav & Anr. vs M/S. Murli Projects Pvt. Ltd & Anr.

Delhi High CourtJUDGMENT: July 10, 20263 MIN READSOURCE JUDGMENT
THE ORIGINAL LAWLENS SUMMARY
01

Facts

In 2010, the petitioners (Rajpal and Radha Yadav) borrowed ₹5 Crores from the complainant for a film, executing an agreement followed by three supplementary agreements due to repayment delays.

Source reference: p. 3-14

Pursuant to the agreement dated 09.08.2012, eight cheques were issued; seven were dishonored, leading to complaints under Section 138 of the NI Act in 2013.

Source reference: p. 15, 21

During pendency, a Consent Agreement was signed in 2013 providing a payment schedule and fresh cheques, followed by a consent decree in 2016.

Source reference: p. 23-29

Petitioners defaulted on the settlement.

Source reference: p. 91

The Trial Court convicted the petitioners on 13.04.2018.

Source reference: p. 32

The Sessions Court affirmed the conviction on 21.01.2019 but remanded for sentencing.

Source reference: p. 34, 45

After remand and further revisions, the Sessions Court modified the sentence on 29.05.2024.

Source reference: p. 48

The petitioners challenged the conviction after a delay of 1,894 days and sought quashing of the complaints.

Source reference: p. 50, 66
02

Issues

1. Whether the petitioners demonstrated "sufficient cause" to condone the 1,894-day delay in challenging the conviction judgment dated 21.01.2019.

Source reference: p. 67 / para. 65

2. Whether the original complaints under Section 138 of the NI Act became non-maintainable following the subsequent Consent Agreement and issuance of fresh settlement cheques.

Source reference: p. 85 / para. 102

3. Whether the detention of Petitioner No. 1 in civil prison during execution proceedings constitutes "double jeopardy" barring criminal imprisonment.

Source reference: p. 95 / para. 121
03

Law Applied

The Court applied Section 5 of the Limitation Act, 1963, regarding the requirement of "sufficient cause" for condoning delay, emphasizing that gross negligence cannot be excused.

Source reference: p. 73-74

It relied on Esha Bhattacharjee v. Managing Committee and Salil Dutta v. T.M. and M.C. Pvt. Ltd. to establish that litigants cannot shift entire blame to counsel.

Source reference: p. 74, 77

Regarding maintenance of complaints, it distinguished Gimpex (P) Ltd. v. Manoj Goel, noting that a settlement only subsumes original complaints if specifically intended and if fresh cheques are prosecuted.

Source reference: p. 82, 93

It applied Article 20(2) of the Constitution and Section 300 Cr.P.C. on Double Jeopardy, holding that civil and criminal proceedings are distinct as per Vishnu Dutt Sharma v. Daya Sapra.

Source reference: p. 96-99
04

Reasoning

The Court rejected the condonation of delay, finding that the petitioners were actively litigating for five years and were represented by various counsels; their plea of being "misguided" lacked bona fides.

Source reference: p. 73, 79

On maintainability, the Court analyzed Clause 6 of the 2013 Consent Agreement, which expressly stated that original criminal cases would only be withdrawn upon full payment.

Source reference: p. 90-91

Since the petitioners defaulted, the right to continue the original prosecution was contractually and legally preserved.

Source reference: p. 92

The Court distinguished Gimpex because, here, the settlement cheques were never presented, avoiding the risk of "parallel prosecutions" for the same liability.

Source reference: p. 93-94

On double jeopardy, the Court reasoned that civil detention (under Section 58 CPC) is a mode of decree execution and not a punishment for an "offence"; hence, it does not bar subsequent criminal sentencing for the statutory default under Section 138 NI Act.

Source reference: p. 99-101
05

Holding

The Court dismissed the revision petitions challenging the conviction (CRL.REV.P. 797/2024 & others) as barred by limitation.

It rejected the plea for quashing the complaint cases, holding them maintainable due to the breach of settlement terms.

Source reference: p. 94

The Court affirmed the judgment dated 29.05.2024 but modified the sentence to reflect an adjustment for ₹2.25 Crores paid during the High Court proceedings. Petitioner No. 1 was sentenced to three months simple imprisonment per case (concurrent) and a fine of ₹1.05 Crore per case. Petitioner No. 2 was sentenced to a fine of ₹5,51,380 per case. The sentence was suspended for two months to allow for further legal remedies.

Source reference: p. 105-108
Delhi High Court

Original Court PDF

Sh. Rajpal Naurang Yadav & Anr.vsM/S. Murli Projects Pvt. Ltd & Anr.

Delhi High Court · July 10, 2026

Click to open original judgment

Original judgment, available to read, download and summarize on LawLens.in

Click to open original judgment